 "packages": [
  {
   "id": "control",
   "title": "Marine control and berth access",
   "phase": "Common works",
   "unit": "released workfronts",
   "ref": "MAR-WHARF-001",
   "codes": [],
   "plant": "Shore survey team, survey launch, tide logger and marine coordinator. Agree vessel access and survey control before either production spread mobilises.",
   "method": "Register berth limits, navigation windows, chart-to-project datum relationship and controlled drawings. Verify shore marks independently and issue the control sheet to both fleets.",
   "production": "Count released workfronts. Build hours from control transfer, independent checks and coordination of each access window.",
   "survey": "Confirm grid, units, tide reference, benchmark levels and transformation using independent observations. Retain the closure and instrument checks.",
   "handover": "Marine coordinator and survey lead issue the referenced control sheet and accessible footprint to dredge and pile leads.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [],
     "after": [
      "baseline",
      "material",
      "fleet",
      "stone"
     ]
    },
    "bored-wharf": {
     "before": [],
     "after": [
      "baseline",
      "material",
      "fleet",
      "stone"
     ]
    },
    "anchored-quay": {
     "before": [],
     "after": [
      "baseline",
      "material",
      "fleet",
      "stone"
     ]
    },
    "maintenance": {
     "before": [],
     "after": [
      "baseline",
      "material",
      "fleet"
     ]
    },
    "reclamation": {
     "before": [],
     "after": [
      "baseline",
      "material",
      "fleet"
     ]
    },
    "mattress-repair": {
     "before": [],
     "after": [
      "baseline",
      "fleet"
     ]
    }
   }
  },
  {
   "id": "baseline",
   "title": "Pre-dredge hydrographic survey",
   "phase": "Dredging",
   "unit": "accepted ha surveyed",
   "ref": "MAR-DREDGE-001",
   "codes": [],
   "plant": "Survey launch, multibeam or specified sounder, GNSS, motion sensor, sound-velocity equipment and processing team. Allow for obstruction shadows and infill lines.",
   "method": "Agree the pay polygon and survey order, acquire baseline soundings, validate offsets and corrections, then freeze the accepted surface version.",
   "production": "Use net hectares on the accepted grid. Derive field time from planned line length and achieved line speed, adding turns, cross-lines and processing.",
   "survey": "Check water-level correction, sound velocity, positioning, coverage and reported uncertainty. Agree common boundaries and grid resolution for the final comparison.",
   "handover": "Hydrographer issues raw and reduced data, metadata, baseline surface and coverage plot to the dredge superintendent and quantity surveyor.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "control"
     ],
     "after": [
      "backhoe"
     ]
    },
    "bored-wharf": {
     "before": [
      "control"
     ],
     "after": [
      "backhoe"
     ]
    },
    "anchored-quay": {
     "before": [
      "control"
     ],
     "after": [
      "wall"
     ]
    },
    "maintenance": {
     "before": [
      "control"
     ],
     "after": [
      "hopper"
     ]
    },
    "reclamation": {
     "before": [
      "control"
     ],
     "after": [
      "cell"
     ]
    },
    "mattress-repair": {
     "before": [
      "control"
     ],
     "after": [
      "toe"
     ]
    }
   }
  },
  {
   "id": "material",
   "title": "Sediment classification and destination release",
   "phase": "Dredging",
   "unit": "accepted material zones",
   "ref": "MAR-DREDGE-001",
   "codes": [],
   "plant": "Sampling vessel, coring or grab spread, laboratory and environmental lead. Separate sailing and laboratory turnaround.",
   "method": "Correlate samples with the dredge blocks. Assign each material class to its approved reuse or disposal destination and brief the tracking crew.",
   "production": "Count classified zones. Build effort from accessible stations and repeat samples. Enter analytical turnaround as a release wait.",
   "survey": "Locate sample stations and depth intervals on the baseline surface. Check certificate and chain-of-custody identifiers against block and destination.",
   "handover": "Environmental lead issues the block-to-destination schedule, monitoring requirements and applicable approvals before material movement.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "control"
     ],
     "after": [
      "haul"
     ]
    },
    "bored-wharf": {
     "before": [
      "control"
     ],
     "after": [
      "haul"
     ]
    },
    "anchored-quay": {
     "before": [
      "control"
     ],
     "after": [
      "haul"
     ]
    },
    "maintenance": {
     "before": [
      "control"
     ],
     "after": [
      "hopper"
     ]
    },
    "reclamation": {
     "before": [
      "control"
     ],
     "after": [
      "cell"
     ]
    }
   }
  },
  {
   "id": "fleet",
   "title": "Marine spread mobilisation and positioning",
   "phase": "Common works",
   "unit": "spread setups",
   "ref": "MAR-PILE-001",
   "codes": [],
   "plant": "Tug, workboat, pontoon or jack-up, deck crane, mooring crew and surveyor. Include launch, tow, set-up and demobilisation in the agreed cost items.",
   "method": "Mobilise the nominated fleet to the access area. Establish its working position and confirm deck configuration, interfaces and planned relocations.",
   "production": "Count discrete primary setups. Time tow, site entry, positioning and release separately from planned weather standby.",
   "survey": "Check platform position and orientation against marine control and the approved work envelope. Record offsets used by machine guidance.",
   "handover": "Marine superintendent issues the vessel readiness record, position check and available working window to the operating crew.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "control"
     ],
     "after": [
      "haul",
      "template"
     ]
    },
    "bored-wharf": {
     "before": [
      "control"
     ],
     "after": [
      "haul",
      "template"
     ]
    },
    "anchored-quay": {
     "before": [
      "control"
     ],
     "after": [
      "wall",
      "haul"
     ]
    },
    "maintenance": {
     "before": [
      "control"
     ],
     "after": [
      "hopper"
     ]
    },
    "reclamation": {
     "before": [
      "control"
     ],
     "after": [
      "cutter"
     ]
    },
    "mattress-repair": {
     "before": [
      "control"
     ],
     "after": [
      "toe"
     ]
    }
   }
  },
  {
   "id": "haul",
   "title": "Barge cycle and spoil reception readiness",
   "phase": "Dredging",
   "unit": "haul spreads commissioned",
   "ref": "MAR-DREDGE-001",
   "codes": [],
   "plant": "Split-hopper barges or scows, tug, tracking system and receiving crew. Match allowable loaded condition and receiver service time to the dredger.",
   "method": "Confirm dispatch sequence, receiver acceptance and contingency destination. Measure load, outward sail, discharge, return and positioning from a representative cycle.",
   "production": "Fleet limit in bank m³/h = operating vessels × accepted bank-equivalent payload ÷ full cycle hours. Restrict dredger output to this limit. Charge production cartage once within the dredge spread or a separate cost item.",
   "survey": "Verify navigation track and placement area. Document the basis for converting loose payload to in-situ quantity, with density or bulking evidence.",
   "handover": "Logistics lead releases vessel IDs, payload basis, working cycle and approved reception location. Voyage and disposal records accompany the closing survey.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "material",
      "fleet"
     ],
     "after": [
      "backhoe"
     ]
    },
    "bored-wharf": {
     "before": [
      "material",
      "fleet"
     ],
     "after": [
      "backhoe"
     ]
    },
    "anchored-quay": {
     "before": [
      "fleet",
      "material"
     ],
     "after": [
      "backhoe"
     ]
    }
   }
  },
  {
   "id": "backhoe",
   "title": "Backhoe dredging and barge load-out",
   "phase": "Dredging",
   "unit": "in-situ m³",
   "ref": "MAR-DREDGE-001",
   "codes": [
    "PRD.MAR.015"
   ],
   "plant": "Backhoe dredger, spuds, scows, tugs and hydrographic support. Compare bucket cycle with barge arrival and discharge capacity.",
   "method": "Divide the berth pocket into cells, excavate to the approved surface and load the accepted destination fleet. Run progress surveys before moving cells.",
   "production": "Take bank volume between common surfaces. Model the lower of digging output and bank-equivalent haul capacity. Distinguish payable dredge, agreed overdepth and excess excavation.",
   "survey": "Survey cell edges, batters and high spots with the nominated coverage. Compare reduced elevations against the released dredge surface.",
   "handover": "Dredge lead supplies cell diary, progress bathymetry, material class and receiver dockets for the acceptance survey.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "baseline",
      "haul"
     ],
     "after": [
      "bed"
     ]
    },
    "bored-wharf": {
     "before": [
      "baseline",
      "haul"
     ],
     "after": [
      "bed"
     ]
    },
    "anchored-quay": {
     "before": [
      "anchors",
      "haul"
     ],
     "after": [
      "bed"
     ]
    }
   }
  },
  {
   "id": "hopper",
   "title": "Trailing suction hopper dredging",
   "phase": "Dredging",
   "unit": "in-situ m³",
   "ref": "MAR-DREDGE-001",
   "codes": [
    "PRD.MAR.014",
    "PRD.MAR.016"
   ],
   "plant": "Trailing suction hopper dredger, survey launch and destination monitoring. Use an achieved bank-equivalent load for the nominated sediment.",
   "method": "Coordinate dredging tracks with berth movements. Load, sail, discharge and return on the approved voyage cycle, tracking each source block and destination.",
   "production": "Achieved bank m³ per voyage ÷ elapsed voyage hours gives fleet output. Use an hourly or weekly Vaultix band only after matching the operating regime and inclusions.",
   "survey": "Check coverage and residual shoals from an independent closing surface. Reconcile hopper records by material class to the hydrographic volume.",
   "handover": "Master and hydrographer issue voyage register, discharge evidence and completed dredge cells for berth-depth review.",
   "source": "",
   "routes": {
    "maintenance": {
     "before": [
      "baseline",
      "material",
      "fleet"
     ],
     "after": [
      "bed"
     ]
    }
   }
  },
  {
   "id": "cell",
   "title": "Reclamation bund and receiving cell",
   "phase": "Dredging",
   "unit": "m³ of accepted bund",
   "ref": "MAR-DREDGE-001",
   "codes": [
    "PRD.MAR.018"
   ],
   "plant": "Rock trucks or barges, excavator, dozer and survey crew. Include decant and monitoring equipment specified for the cell.",
   "method": "Set out containment and outlets, construct the designed bund, verify storage and discharge arrangements, then release the cell to the pump crew.",
   "production": "Measure accepted bund sections between surveyed surfaces. Assess rock supply, spreading and compaction as separate constraints.",
   "survey": "Survey toe, crest, outlet and receiving area in a common datum. Verify the available fill footprint and stage level.",
   "handover": "Reclamation lead signs the cell readiness plan and receiving capacity before hydraulic placement begins.",
   "source": "",
   "routes": {
    "reclamation": {
     "before": [
      "baseline",
      "material"
     ],
     "after": [
      "cutter"
     ]
    }
   }
  },
  {
   "id": "cutter",
   "title": "Cutter suction dredge and hydraulic placement",
   "phase": "Dredging",
   "unit": "in-situ m³ dredged",
   "ref": "MAR-DREDGE-001",
   "codes": [
    "PRD.MAR.013",
    "PRD.MAR.017"
   ],
   "plant": "Cutter suction dredger, discharge pipeline, booster if specified, workboat and reclamation cell crew. Match pump duty and receiver capacity to the cut.",
   "method": "Release the cut and receiving cell together. Dredge and pump concurrently, move the discharge point as required and record stoppages and material zones.",
   "production": "Use the lower bank-equivalent output of excavation, pumping and reception. Record placed fill separately by survey. The placement comparator uses a different quantity basis.",
   "survey": "Compare pre- and post-dredge bed surfaces and track fill levels within the receiving cell. Document the conversion basis for any material balance.",
   "handover": "Dredge lead hands over cut-cell records. Reclamation lead hands over placed-fill surveys, discharge logs and environmental records for independent review.",
   "source": "",
   "routes": {
    "reclamation": {
     "before": [
      "cell",
      "fleet"
     ],
     "after": [
      "bed",
      "settlement"
     ]
    }
   }
  },
  {
   "id": "settlement",
   "title": "Reclamation settlement and platform release",
   "phase": "Dredging",
   "unit": "released fill stages",
   "ref": "MAR-DREDGE-001",
   "codes": [],
   "plant": "Settlement plates, monitoring instruments, survey crew and geotechnical reviewer. Allow separate occupation time for surcharge and monitoring.",
   "method": "Establish baseline readings, track staged filling and movements, then release the platform to the next trade under the approved geotechnical criteria.",
   "production": "Count stages signed off. Estimate instrument reading and review effort separately from elapsed settlement time.",
   "survey": "Reference instrument heads to external control; check settlement trends and crest or platform profile against the issued design stage.",
   "handover": "Geotechnical reviewer issues the stage disposition, movement history and released platform limits.",
   "source": "",
   "routes": {
    "reclamation": {
     "before": [
      "cutter"
     ],
     "after": [
      "handover"
     ]
    }
   }
  },
  {
   "id": "bed",
   "title": "Dredge acceptance and high-spot closeout",
   "phase": "Dredging",
   "unit": "accepted dredge cells",
   "ref": "MAR-DREDGE-001",
   "codes": [],
   "plant": "Survey launch, processing crew, quantity surveyor and local rework spread where needed.",
   "method": "Survey the finished pocket, identify exceptions, agree any local recut and resurvey the affected footprint before closing the cell.",
   "production": "Compare the agreed baseline and final surfaces inside the pay mask. Keep high spots, payable overdepth and material outside limits separately identifiable.",
   "survey": "Report least depth or highest bed elevation on the specified datum, coverage, uncertainty, boundary treatment and excluded shadows. Reconcile destination records.",
   "handover": "Hydrographer and reviewer issue the accepted bathymetric surface and volume report to piling, scour or port operations as applicable.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "backhoe"
     ],
     "after": [
      "template",
      "toe"
     ]
    },
    "bored-wharf": {
     "before": [
      "backhoe"
     ],
     "after": [
      "template",
      "toe"
     ]
    },
    "anchored-quay": {
     "before": [
      "backhoe"
     ],
     "after": [
      "toe",
      "handover"
     ]
    },
    "maintenance": {
     "before": [
      "hopper"
     ],
     "after": [
      "handover"
     ]
    },
    "reclamation": {
     "before": [
      "cutter"
     ],
     "after": [
      "handover"
     ]
    }
   }
  },
  {
   "id": "template",
   "title": "Pile delivery, gate and template set-out",
   "phase": "Piling",
   "unit": "released pile groups",
   "ref": "MAR-PILE-001",
   "codes": [],
   "plant": "Crane barge or jack-up, steel gate or template, survey instruments and handling crew. Sequence delivered piles by bent and length.",
   "method": "Check pile identification and condition. Position the gate to the design grid, record the working offsets and release the pitch locations.",
   "production": "Count setups by pile group. Time moves and checks, keeping repeated pitching within the production cycle where already included.",
   "survey": "Independently observe gate position and orientation, pile centres and intended rake from shore control. Check again after a platform move.",
   "handover": "Surveyor releases the group set-out and pile schedule to the installation lead.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "bed",
      "fleet"
     ],
     "after": [
      "drive"
     ]
    },
    "bored-wharf": {
     "before": [
      "bed",
      "fleet"
     ],
     "after": [
      "bore"
     ]
    }
   }
  },
  {
   "id": "drive",
   "title": "Driven marine steel piles",
   "phase": "Piling",
   "unit": "piles installed",
   "ref": "MAR-PILE-001",
   "codes": [
    "PRD.MAR.001",
    "PRD.MAR.002"
   ],
   "plant": "Marine crane, hammer, template, handling crew and supply barge. Select floating or jack-up spread against the approved installation arrangement.",
   "method": "Pitch the identified pile, check position and rake, install to the approved founding criteria and record interruptions and splices. Review departures before trimming.",
   "production": "Split counts by length, founding domain and platform type. Measure pitch, install, splice and reposition time; match the Vaultix comparator to the whole cycle.",
   "survey": "Observe the as-driven centre and inclination at known elevations. Tie the installation record, toe evidence and head observation to the unique pile ID.",
   "handover": "Piling engineer releases the as-driven group with installation logs, splice inspection and disposition of refusal or position departures.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "template"
     ],
     "after": [
      "heads"
     ]
    }
   }
  },
  {
   "id": "bore",
   "title": "Bored marine piles and rock sockets",
   "phase": "Piling",
   "unit": "completed bored piles",
   "ref": "MAR-PILE-001",
   "codes": [
    "PRD.MAR.006",
    "PRD.MAR.007",
    "PRD.MAR.008"
   ],
   "plant": "Jack-up or suitable drill platform, rotary rig, casing, spoil handling, cage lift and tremie supply. Separate soil and rock domains.",
   "method": "Set casing on the released coordinates, log the excavation and socket, inspect the base under the approved method, lower the cage and place concrete.",
   "production": "Use the whole-pile shift band or build up drilling metres, cage and concrete time. Adding the component bands to a whole-pile duration duplicates work.",
   "survey": "Check casing centre and verticality, depth reference, socket termination and cage top. Reconcile concrete placement and integrity records by pile.",
   "handover": "Piling lead provides bore log, founding acceptance, cage and concrete records, integrity evidence and surveyed pile group for head works.",
   "source": "",
   "routes": {
    "bored-wharf": {
     "before": [
      "template"
     ],
     "after": [
      "heads"
     ]
    }
   }
  },
  {
   "id": "heads",
   "title": "Pile cut-off, plugs and cap release",
   "phase": "Piling",
   "unit": "pile heads released",
   "ref": "MAR-PILE-001",
   "codes": [
    "PRD.MAR.005"
   ],
   "plant": "Marine access platform, cutting and handling crew, cleaning plant and concrete pump where the design requires a plug.",
   "method": "Review the as-installed group, trim heads to issued levels, prepare the connection or place the designed plug. Resolve eccentricities before cap formwork.",
   "production": "Count heads by detail. Convert a plug-only m³/h band to time from plug volume and carry access, trim, cleaning and cure separately.",
   "survey": "Survey cut-off level, head coordinates, connection orientation and plug level where applicable. Compare the group with the cap interface drawing.",
   "handover": "Structural reviewer releases the pile-head register and reviewed connection detail to the cap and scour leads.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "drive"
     ],
     "after": [
      "toe",
      "caps",
      "cp"
     ]
    },
    "bored-wharf": {
     "before": [
      "bore"
     ],
     "after": [
      "toe",
      "caps",
      "cp"
     ]
    }
   }
  },
  {
   "id": "stone",
   "title": "Scour material qualification and supply",
   "phase": "Scour protection",
   "unit": "accepted t delivered",
   "ref": "MAR-SCOUR-001",
   "codes": [],
   "plant": "Quarry sorting and weighing plant, stockpile crew, road or barge transport and material inspector.",
   "method": "Confirm grading, durability and stone class. Segregate filter, underlayer and armour, then track delivery lots to the intended protection cells.",
   "production": "Use certified tonnes by grade. Check supply-and-stockpile output against rock-placement demand; record rejected or rehandled material separately.",
   "survey": "Survey stockpile boundaries where quantity reconciliation requires it. Carry grading certificates, load dockets and destination cell IDs into the placement plan.",
   "handover": "Materials lead releases each graded stockpile and delivery allocation to the placing spread.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "control"
     ],
     "after": [
      "filter",
      "armour"
     ]
    },
    "bored-wharf": {
     "before": [
      "control"
     ],
     "after": [
      "filter",
      "armour"
     ]
    },
    "anchored-quay": {
     "before": [
      "control"
     ],
     "after": [
      "filter"
     ]
    }
   }
  },
  {
   "id": "toe",
   "title": "Toe and scour footprint preparation",
   "phase": "Scour protection",
   "unit": "m² released bed",
   "ref": "MAR-SCOUR-001",
   "codes": [],
   "plant": "Survey launch, grab or backhoe and inspection team. Check access around piles and clearance for the placing vessel.",
   "method": "Inspect bed condition, prepare the designated footprint and record any local variation in toe or transition geometry.",
   "production": "Measure the prepared polygon; take extra excavation by surveyed volume. Use actual cell preparation time and vessel moves.",
   "survey": "Observe the toe trench or preparation surface before filter placement. Show pile shadows, edges and coverage gaps for review.",
   "handover": "Marine works lead releases the toe and base survey to the filter crew with marked exceptions.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "heads",
      "bed"
     ],
     "after": [
      "filter"
     ]
    },
    "bored-wharf": {
     "before": [
      "heads",
      "bed"
     ],
     "after": [
      "filter"
     ]
    },
    "anchored-quay": {
     "before": [
      "bed",
      "anchors"
     ],
     "after": [
      "filter"
     ]
    },
    "mattress-repair": {
     "before": [
      "baseline",
      "fleet"
     ],
     "after": [
      "filter"
     ]
    }
   }
  },
  {
   "id": "filter",
   "title": "Geotextile or granular scour filter",
   "phase": "Scour protection",
   "unit": "m² covered",
   "ref": "MAR-SCOUR-001",
   "codes": [
    "PRD.MAR.030"
   ],
   "plant": "Lay barge, lifting frame or placement spread, survey and underwater inspection support. Select method for the specified filter system.",
   "method": "Place panels or graded bedding on the accepted base, maintain the designed continuity around piles and inspect laps or layer coverage before concealment.",
   "production": "Pay net covered area; account for overlaps and waste in supply. For a granular filter use the specified thickness and density to build delivered tonnes.",
   "survey": "Verify boundaries, lap or edge positions and discontinuities by georeferenced inspection. Record granular layer surface before armour where accessible.",
   "handover": "Inspector releases filter panels or bedding cells with photographs, placement logs and exception closure.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "toe",
      "stone"
     ],
     "after": [
      "armour"
     ]
    },
    "bored-wharf": {
     "before": [
      "toe",
      "stone"
     ],
     "after": [
      "armour"
     ]
    },
    "anchored-quay": {
     "before": [
      "toe",
      "stone"
     ],
     "after": [
      "armour"
     ]
    },
    "mattress-repair": {
     "before": [
      "toe"
     ],
     "after": [
      "mattress"
     ]
    }
   }
  },
  {
   "id": "armour",
   "title": "Rock armour placement around piles and toes",
   "phase": "Scour protection",
   "unit": "accepted t placed",
   "ref": "MAR-SCOUR-001",
   "codes": [
    "PRD.MAR.035",
    "PRD.MAR.036"
   ],
   "plant": "Rock barge and grab or long-reach shore excavator, survey launch and delivery fleet. Separate land-based and floating spreads.",
   "method": "Place the approved grading by cell, build toe and transitions, and retain access to the pile group and adjacent works.",
   "production": "Use accepted tonnes and reconcile to the designed footprint and layer profile. Measure operating output after positioning and rock supply interruptions.",
   "survey": "Survey toe, crest, perimeter and as-placed surface. Compare against filter survey for thickness where both surfaces have adequate coverage.",
   "handover": "Scour lead submits cell placement and delivery records for final profile inspection; mark thin areas for correction.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "filter",
      "stone"
     ],
     "after": [
      "scour-release"
     ]
    },
    "bored-wharf": {
     "before": [
      "filter",
      "stone"
     ],
     "after": [
      "scour-release"
     ]
    },
    "anchored-quay": {
     "before": [
      "filter"
     ],
     "after": [
      "scour-release"
     ]
    }
   }
  },
  {
   "id": "mattress",
   "title": "Articulated or grout-filled scour mattresses",
   "phase": "Scour protection",
   "unit": "m² installed",
   "ref": "MAR-SCOUR-001",
   "codes": [
    "PRD.MAR.037",
    "PRD.MAR.038"
   ],
   "plant": "Work barge, lifting frame, handling crew and ROV or dive inspection under the approved marine plan; include grout spread for fabric forms.",
   "method": "Set units to the released filter or prepared bed, complete joints and pile transitions, then inspect alignment and edge restraint.",
   "production": "Measure net protected area. Separate fabricated overlaps, special closures, lifting moves and any grout quantities from net area.",
   "survey": "Record corners, joints, lifted edges and pile interfaces by cell. Supplement sounding coverage with georeferenced underwater inspection.",
   "handover": "Inspector releases installed unit IDs and continuity evidence to the final scour survey.",
   "source": "",
   "routes": {
    "mattress-repair": {
     "before": [
      "filter"
     ],
     "after": [
      "scour-release"
     ]
    }
   }
  },
  {
   "id": "scour-release",
   "title": "Scour profile and underwater acceptance",
   "phase": "Scour protection",
   "unit": "protection cells released",
   "ref": "MAR-SCOUR-001",
   "codes": [],
   "plant": "Hydrographic vessel, ROV or approved diver inspection, processing crew and placing plant on call for correction.",
   "method": "Compare as-placed footprint and profile with the released bed and design, investigate shadows at piles, remedy agreed deficiencies and close the cell.",
   "production": "Count accepted cells; price line coverage, targeted inspection, processing and corrective placement separately.",
   "survey": "Report toe, crest, thickness basis, coverage gaps and uncertainty. Do not infer buried filter continuity solely from a finished-surface survey.",
   "handover": "Reviewer issues the accepted scour drawing and inspection map to wharf operations and the maintenance baseline.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "armour"
     ],
     "after": [
      "precast",
      "handover"
     ]
    },
    "bored-wharf": {
     "before": [
      "armour"
     ],
     "after": [
      "handover"
     ]
    },
    "anchored-quay": {
     "before": [
      "armour"
     ],
     "after": [
      "handover"
     ]
    },
    "mattress-repair": {
     "before": [
      "mattress"
     ],
     "after": [
      "handover"
     ]
    }
   }
  },
  {
   "id": "caps",
   "title": "Over-water pile caps and headstocks",
   "phase": "Wharf construction",
   "unit": "m³ of cap concrete",
   "ref": "MAR-WHARF-001",
   "codes": [
    "PRD.MAR.009",
    "PRD.MAR.012"
   ],
   "plant": "Over-water forms or precast shells, reinforcement crew, crane, pump and concrete supply. Include form access, hold points and stripping.",
   "method": "Set forms from the accepted pile group, verify connection reinforcement and embeds, place the pour and protect it until the specified strength release.",
   "production": "Take concrete by cap geometry; estimate reinforcement separately only where excluded from the cap spread. Add cure and inspection waits by pour lot.",
   "survey": "Check cap centre, seat elevations, bolt or dowel layout and finished bearing line. Link each observation to the pile group and pour ID.",
   "handover": "Structural lead issues strength evidence, bearing-seat survey and cap release before deck-unit erection.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "heads"
     ],
     "after": [
      "precast"
     ]
    },
    "bored-wharf": {
     "before": [
      "heads"
     ],
     "after": [
      "precast"
     ]
    }
   }
  },
  {
   "id": "precast",
   "title": "Precast wharf deck units",
   "phase": "Wharf construction",
   "unit": "units erected",
   "ref": "MAR-WHARF-001",
   "codes": [
    "PRD.MAR.010"
   ],
   "plant": "Marine or shore crane, transport barge, rigging crew and survey. Sequence units by lift radius, delivery slot and bearing availability.",
   "method": "Receive identified units, inspect bearing seats, erect to the nominated span and complete the specified restraints and connections.",
   "production": "Count units by type and span. Measure receipt, rigging, lift, seating and release time. Charge crane relocation and delivery standby explicitly.",
   "survey": "Observe bearing engagement, plan alignment, soffit or top level and joint gaps by unit ID before topping conceals interfaces.",
   "handover": "Erection lead releases the unit register and connection inspections to deck reinforcement and topping.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "caps",
      "scour-release"
     ],
     "after": [
      "deck"
     ]
    },
    "bored-wharf": {
     "before": [
      "caps"
     ],
     "after": [
      "deck"
     ]
    }
   }
  },
  {
   "id": "deck",
   "title": "Wharf topping, deck falls and curing",
   "phase": "Wharf construction",
   "unit": "m² of deck accepted",
   "ref": "MAR-WHARF-001",
   "codes": [
    "PRD.MAR.011",
    "PRD.MAR.012"
   ],
   "plant": "Concrete pump, delivery fleet, reinforcement and finishing crew, surveyor and testers. Confirm access and weather window for each pour.",
   "method": "Inspect deck units, fix the detailed reinforcement and cast-ins, place and finish the topping, then cure and verify the released loading stage.",
   "production": "Use net deck area × thickness for theoretical concrete volume; count thickened zones separately. Price return visits, cure and strength waits per pour.",
   "survey": "Check deck line and level, crossfall, drainage lows, edge face and cast-in positions. Reconcile survey with concrete test and pour records.",
   "handover": "Structural lead releases the deck load stage and as-built surface to berth furniture, services and operations.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "precast"
     ],
     "after": [
      "fender",
      "bollard"
     ]
    },
    "bored-wharf": {
     "before": [
      "precast"
     ],
     "after": [
      "fender",
      "bollard"
     ]
    }
   }
  },
  {
   "id": "fender",
   "title": "Fenders, panels and berth-face interfaces",
   "phase": "Wharf construction",
   "unit": "fender sets",
   "ref": "MAR-WHARF-001",
   "codes": [
    "PRD.MAR.039",
    "PRD.MAR.041"
   ],
   "plant": "Barge or deck crane, fitting crew, access platform and survey. Confirm panel and chain assemblies against vendor drawings.",
   "method": "Verify cast-ins or approved anchor positions, install the identified fender assembly, adjust to the berth face and complete vendor inspections.",
   "production": "Count complete sets. Track anchor works separately only when the whole-set scope excludes them; include tidal access and handling time.",
   "survey": "Check berth-face offset, fender centre elevation, orientation and panel projection on the marine datum. Record anchor and connection inspections.",
   "handover": "Vendor or authorised inspector hands over each fender set, as-built coordinates and installation record to the berth operator.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "deck"
     ],
     "after": [
      "handover"
     ]
    },
    "bored-wharf": {
     "before": [
      "deck"
     ],
     "after": [
      "handover"
     ]
    },
    "anchored-quay": {
     "before": [
      "coping"
     ],
     "after": [
      "handover"
     ]
    }
   }
  },
  {
   "id": "bollard",
   "title": "Bollards, mooring fittings and deck services",
   "phase": "Wharf construction",
   "unit": "mooring fittings installed",
   "ref": "MAR-WHARF-001",
   "codes": [
    "PRD.MAR.040",
    "PRD.MAR.041"
   ],
   "plant": "Lifting equipment, fitting and services crews, torque equipment and survey. Identify free-issued items and interface trades.",
   "method": "Verify the released deck or coping and embeds, set fittings, connect designated services and compile the asset schedule.",
   "production": "Count mooring fittings by type. Price services by run or connection, and tests by item. Add service quantities separately from the fitting count.",
   "survey": "Survey fitting centres, orientation, deck level and service penetrations. Check clearances and retain vendor inspection and required test results.",
   "handover": "Wharf lead releases tagged assets, installation tests, service records and outstanding items to the operator.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "deck"
     ],
     "after": [
      "handover"
     ]
    },
    "bored-wharf": {
     "before": [
      "deck"
     ],
     "after": [
      "handover"
     ]
    },
    "anchored-quay": {
     "before": [
      "coping"
     ],
     "after": [
      "handover"
     ]
    }
   }
  },
  {
   "id": "cp",
   "title": "Marine steel corrosion protection",
   "phase": "Wharf construction",
   "unit": "anodes installed",
   "ref": "DUR-CP-001",
   "codes": [
    "PRD.MAR.042",
    "PRD.MAR.043",
    "PRD.MAR.044"
   ],
   "plant": "Workboat or access platform, coating and cathodic-protection specialists, inspection instruments and tagged anodes.",
   "method": "Inspect coating repairs and designed jacket or anode installation, identify test locations and complete specialist verification before the interface becomes inaccessible.",
   "production": "Count anodes, measure coating by area and jackets by pile. If the lot combines systems, carry separate allowances for the other quantities.",
   "survey": "Locate installed anodes, test points and jacket bounds by pile or wall panel. Pair the asset map with continuity, coating and commissioning records.",
   "handover": "Corrosion specialist issues the protected-asset schedule, inspected connections and initial readings to the maintenance team.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "heads"
     ],
     "after": [
      "handover"
     ]
    },
    "bored-wharf": {
     "before": [
      "heads"
     ],
     "after": [
      "handover"
     ]
    },
    "anchored-quay": {
     "before": [
      "wall"
     ],
     "after": [
      "handover"
     ]
    }
   }
  },
  {
   "id": "wall",
   "title": "Quay wall piles and interlock closure",
   "phase": "Quay wall",
   "unit": "m² installed wall",
   "ref": "DISC-MARINE-METH-003",
   "codes": [
    "PRD.MAR.004"
   ],
   "plant": "Crane barge or jack-up, pile gate, driving equipment and survey. Identify combi-wall king-pile and intermediate sheet sequences.",
   "method": "Pitch and install the designed wall elements to the required founding and interlock arrangement. Monitor line throughout the panel and record obstructions.",
   "production": "Measure wall face area on the agreed depth basis. Count king piles or special closures separately where the schedule requires it.",
   "survey": "Survey wall line, head elevation and inclination. Tie pile length and installation records to embedment evidence and interlock inspection.",
   "handover": "Wall engineer releases the accepted panel to walers and anchors, with a drawing of unresolved deviations.",
   "source": "",
   "routes": {
    "anchored-quay": {
     "before": [
      "baseline",
      "fleet"
     ],
     "after": [
      "anchors",
      "cp"
     ]
    }
   }
  },
  {
   "id": "anchors",
   "title": "Quay walers, anchors and staged dredge release",
   "phase": "Quay wall",
   "unit": "anchor bays released",
   "ref": "DISC-MARINE-METH-003",
   "codes": [],
   "plant": "Waler installation crane, tie-rod or anchor crew, specialist testing plant and survey. Select the designed restraint system.",
   "method": "Install and inspect the designed restraints, verify the specified proof or preload records, and obtain the engineer’s stage release before deepening the adjacent face.",
   "production": "Count complete bays by restraint type. Estimate drilling or tie installation, testing, acceptance and staged support waits separately.",
   "survey": "Survey anchor alignment, waler level and wall movements against the stage baseline. Link load-test records to each anchor ID.",
   "handover": "Designated engineer issues the permissible dredge stage, footprint and monitoring conditions to the dredge superintendent.",
   "source": "",
   "routes": {
    "anchored-quay": {
     "before": [
      "wall"
     ],
     "after": [
      "backhoe",
      "toe",
      "coping"
     ]
    }
   }
  },
  {
   "id": "coping",
   "title": "Quay coping, retained fill and edge completion",
   "phase": "Quay wall",
   "unit": "m of quay completed",
   "ref": "DISC-MARINE-METH-003",
   "codes": [],
   "plant": "Form and concrete crew, pump, graded fill deliveries and compaction plant. Coordinate staging with the wall engineer.",
   "method": "Place retained fill and drainage in the authorised stages, inspect anchors before concealment and cast the coping and embedded fittings.",
   "production": "Measure coping length; derive pour volume and accepted fill by zone. Account for stage restrictions and shared access with berth dredging.",
   "survey": "Survey coping face, crest, embed positions and adjacent fill surface. Attach movement records and concealed-work inspections.",
   "handover": "Wall lead releases the coping and retained-side lot for fittings and final berth survey.",
   "source": "",
   "routes": {
    "anchored-quay": {
     "before": [
      "anchors"
     ],
     "after": [
      "fender",
      "bollard"
     ]
    }
   }
  },
  {
   "id": "handover",
   "title": "Berth or reach handover",
   "phase": "Handover",
   "unit": "accepted lots",
   "ref": "MAR-WHARF-001",
   "codes": [],
   "plant": "Hydrographer, surveyor, engineering reviewers, port representative and asset-information coordinator. Book review against the actual berth access date.",
   "method": "Assemble signed package releases by polygon, pile group, bay or panel. Resolve conflicts between deck geometry, protected bed and navigable limits before issuing the final dossier.",
   "production": "Count signed workfronts. Estimate survey reconciliation, review and defect closure time; distinguish construction completion from permission to operate.",
   "survey": "Overlay final bathymetry, scour footprint, berth face, fittings and land survey on the stated grids and datums. Identify any unsurveyed shadow or use restriction.",
   "handover": "Designated authority receives the as-built plan, test and survey files, approved departures, asset schedule and maintenance baseline. Record the operational release separately.",
   "source": "",
   "routes": {
    "driven-wharf": {
     "before": [
      "scour-release",
      "fender",
      "bollard",
      "cp"
     ],
     "after": []
    },
    "bored-wharf": {
     "before": [
      "scour-release",
      "fender",
      "bollard",
      "cp"
     ],
     "after": []
    },
    "anchored-quay": {
     "before": [
      "bed",
      "scour-release",
      "fender",
      "bollard",
      "cp"
     ],
     "after": []
    },
    "maintenance": {
     "before": [
      "bed"
     ],
     "after": []
    },
    "reclamation": {
     "before": [
      "bed",
      "settlement"
     ],
     "after": []
    },
    "mattress-repair": {
     "before": [
      "scour-release"
     ],
     "after": []
    }
   }
  }
 ],
 "routes": {
  "driven-wharf": {
   "title": "Open piled wharf · driven steel piles",
   "basis": "A dredged berth with over-water caps and precast deck. Caps and scour start from the accepted pile heads. In this bay, the open deck is the access route for placing and inspecting rock, so scour acceptance also gates deck-unit erection.",
   "nodes": [
    {
     "id": "control",
     "predecessors": []
    },
    {
     "id": "baseline",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "material",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "fleet",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "haul",
     "predecessors": [
      "material",
      "fleet"
     ]
    },
    {
     "id": "backhoe",
     "predecessors": [
      "baseline",
      "haul"
     ]
    },
    {
     "id": "bed",
     "predecessors": [
      "backhoe"
     ]
    },
    {
     "id": "template",
     "predecessors": [
      "bed",
      "fleet"
     ]
    },
    {
     "id": "drive",
     "predecessors": [
      "template"
     ]
    },
    {
     "id": "heads",
     "predecessors": [
      "drive"
     ]
    },
    {
     "id": "stone",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "toe",
     "predecessors": [
      "heads",
      "bed"
     ]
    },
    {
     "id": "filter",
     "predecessors": [
      "toe",
      "stone"
     ]
    },
    {
     "id": "armour",
     "predecessors": [
      "filter",
      "stone"
     ]
    },
    {
     "id": "scour-release",
     "predecessors": [
      "armour"
     ]
    },
    {
     "id": "caps",
     "predecessors": [
      "heads"
     ]
    },
    {
     "id": "cp",
     "predecessors": [
      "heads"
     ]
    },
    {
     "id": "precast",
     "predecessors": [
      "caps",
      "scour-release"
     ]
    },
    {
     "id": "deck",
     "predecessors": [
      "precast"
     ]
    },
    {
     "id": "fender",
     "predecessors": [
      "deck"
     ]
    },
    {
     "id": "bollard",
     "predecessors": [
      "deck"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "scour-release",
      "fender",
      "bollard",
      "cp"
     ]
    }
   ]
  },
  "bored-wharf": {
   "title": "Open piled wharf · bored piles and sockets",
   "basis": "The drill spread works from the released berth. Independent waterside access remains available for scour and corrosion works while the shore-based crane erects the deck. Handover waits for both fronts.",
   "nodes": [
    {
     "id": "control",
     "predecessors": []
    },
    {
     "id": "baseline",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "material",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "fleet",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "haul",
     "predecessors": [
      "material",
      "fleet"
     ]
    },
    {
     "id": "backhoe",
     "predecessors": [
      "baseline",
      "haul"
     ]
    },
    {
     "id": "bed",
     "predecessors": [
      "backhoe"
     ]
    },
    {
     "id": "template",
     "predecessors": [
      "bed",
      "fleet"
     ]
    },
    {
     "id": "bore",
     "predecessors": [
      "template"
     ]
    },
    {
     "id": "heads",
     "predecessors": [
      "bore"
     ]
    },
    {
     "id": "stone",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "toe",
     "predecessors": [
      "heads",
      "bed"
     ]
    },
    {
     "id": "filter",
     "predecessors": [
      "toe",
      "stone"
     ]
    },
    {
     "id": "armour",
     "predecessors": [
      "filter",
      "stone"
     ]
    },
    {
     "id": "scour-release",
     "predecessors": [
      "armour"
     ]
    },
    {
     "id": "caps",
     "predecessors": [
      "heads"
     ]
    },
    {
     "id": "cp",
     "predecessors": [
      "heads"
     ]
    },
    {
     "id": "precast",
     "predecessors": [
      "caps"
     ]
    },
    {
     "id": "deck",
     "predecessors": [
      "precast"
     ]
    },
    {
     "id": "fender",
     "predecessors": [
      "deck"
     ]
    },
    {
     "id": "bollard",
     "predecessors": [
      "deck"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "scour-release",
      "fender",
      "bollard",
      "cp"
     ]
    }
   ]
  },
  "anchored-quay": {
   "title": "Anchored quay wall and berth deepening",
   "basis": "Wall and anchor acceptance release the adjacent dredge stage. This scenario permits retained-side coping and pocket dredging on separate fronts after restraint acceptance. The design staging plan governs the actual order.",
   "nodes": [
    {
     "id": "control",
     "predecessors": []
    },
    {
     "id": "baseline",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "material",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "fleet",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "wall",
     "predecessors": [
      "baseline",
      "fleet"
     ]
    },
    {
     "id": "anchors",
     "predecessors": [
      "wall"
     ]
    },
    {
     "id": "haul",
     "predecessors": [
      "fleet",
      "material"
     ]
    },
    {
     "id": "backhoe",
     "predecessors": [
      "anchors",
      "haul"
     ]
    },
    {
     "id": "bed",
     "predecessors": [
      "backhoe"
     ]
    },
    {
     "id": "stone",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "toe",
     "predecessors": [
      "bed",
      "anchors"
     ]
    },
    {
     "id": "filter",
     "predecessors": [
      "toe",
      "stone"
     ]
    },
    {
     "id": "armour",
     "predecessors": [
      "filter"
     ]
    },
    {
     "id": "scour-release",
     "predecessors": [
      "armour"
     ]
    },
    {
     "id": "coping",
     "predecessors": [
      "anchors"
     ]
    },
    {
     "id": "cp",
     "predecessors": [
      "wall"
     ]
    },
    {
     "id": "fender",
     "predecessors": [
      "coping"
     ]
    },
    {
     "id": "bollard",
     "predecessors": [
      "coping"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "bed",
      "scour-release",
      "fender",
      "bollard",
      "cp"
     ]
    }
   ]
  },
  "maintenance": {
   "title": "Maintenance dredging · hopper cycle",
   "basis": "The vessel performs dredging, transport and discharge in a single voyage cycle. The accepted post-dredge survey and reconciled destination records release the reach.",
   "nodes": [
    {
     "id": "control",
     "predecessors": []
    },
    {
     "id": "baseline",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "material",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "fleet",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "hopper",
     "predecessors": [
      "baseline",
      "material",
      "fleet"
     ]
    },
    {
     "id": "bed",
     "predecessors": [
      "hopper"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "bed"
     ]
    }
   ]
  },
  "reclamation": {
   "title": "Cutter suction dredging and reclamation",
   "basis": "A prepared receiving cell and classified cut are required before pumping. Dredging and fill placement operate together. Final bed acceptance and reclamation settlement are separate release branches.",
   "nodes": [
    {
     "id": "control",
     "predecessors": []
    },
    {
     "id": "baseline",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "material",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "fleet",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "cell",
     "predecessors": [
      "baseline",
      "material"
     ]
    },
    {
     "id": "cutter",
     "predecessors": [
      "cell",
      "fleet"
     ]
    },
    {
     "id": "bed",
     "predecessors": [
      "cutter"
     ]
    },
    {
     "id": "settlement",
     "predecessors": [
      "cutter"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "bed",
      "settlement"
     ]
    }
   ]
  },
  "mattress-repair": {
   "title": "Local scour repair · mattresses",
   "basis": "Repair an existing berth footprint with an approved filter and mattress system. Verify exposed bed and pile interfaces, inspect the filter before concealment and return the reach after underwater acceptance.",
   "nodes": [
    {
     "id": "control",
     "predecessors": []
    },
    {
     "id": "baseline",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "fleet",
     "predecessors": [
      "control"
     ]
    },
    {
     "id": "toe",
     "predecessors": [
      "baseline",
      "fleet"
     ]
    },
    {
     "id": "filter",
     "predecessors": [
      "toe"
     ]
    },
    {
     "id": "mattress",
     "predecessors": [
      "filter"
     ]
    },
    {
     "id": "scour-release",
     "predecessors": [
      "mattress"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "scour-release"
     ]
    }
   ]
  }
 },
 "benchmarks": {
  "PRD.MAR.015": {
   "id": "PRD.MAR.015",
   "name": "Backhoe dredger, stiff clay / soft rock (in-situ m3)",
   "unit": "m3/day",
   "low": 1500.0,
   "typ": 4000.0,
   "high": 8000.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.014": {
   "id": "PRD.MAR.014",
   "name": "TSHD loose sand/silt (in-situ m3)",
   "unit": "m3/week",
   "low": 50000.0,
   "typ": 150000.0,
   "high": 400000.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.016": {
   "id": "PRD.MAR.016",
   "name": "Maintenance dredge silt (in-situ m3), TSHD",
   "unit": "m3/hr",
   "low": 300.0,
   "typ": 800.0,
   "high": 1500.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.018": {
   "id": "PRD.MAR.018",
   "name": "Rock bund construction",
   "unit": "m3/day",
   "low": 300.0,
   "typ": 800.0,
   "high": 1500.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.013": {
   "id": "PRD.MAR.013",
   "name": "CSD in soft-medium material (in-situ m3)",
   "unit": "m3/week",
   "low": 30000.0,
   "typ": 80000.0,
   "high": 200000.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.017": {
   "id": "PRD.MAR.017",
   "name": "Hydraulic fill placement (pumped from CSD)",
   "unit": "m3/week",
   "low": 30000.0,
   "typ": 90000.0,
   "high": 250000.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.001": {
   "id": "PRD.MAR.001",
   "name": "Drive large-dia steel tubular pile (<=914 mm) to set, jack-up, good ground",
   "unit": "no/shift",
   "low": 2.0,
   "typ": 4.0,
   "high": 6.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.002": {
   "id": "PRD.MAR.002",
   "name": "Drive large-dia steel tubular pile, floating barge (swell-limited)",
   "unit": "no/shift",
   "low": 1.0,
   "typ": 2.5,
   "high": 4.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.006": {
   "id": "PRD.MAR.006",
   "name": "Bored marine pile in soil, 1200-1500 mm dia (drill+cage+tremie)",
   "unit": "no/shift",
   "low": 0.5,
   "typ": 1.0,
   "high": 2.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.007": {
   "id": "PRD.MAR.007",
   "name": "Rock-socket advance (medium-strong rock)",
   "unit": "m/hr",
   "low": 0.3,
   "typ": 0.8,
   "high": 1.5,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.008": {
   "id": "PRD.MAR.008",
   "name": "Tremie concrete placement, marine bored pile",
   "unit": "m3/hr",
   "low": 10.0,
   "typ": 18.0,
   "high": 30.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.005": {
   "id": "PRD.MAR.005",
   "name": "Tremie/pump concrete plug to driven tubular",
   "unit": "m3/hr",
   "low": 8.0,
   "typ": 15.0,
   "high": 25.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.030": {
   "id": "PRD.MAR.030",
   "name": "Place geotextile filter / bedding",
   "unit": "m2/day",
   "low": 300.0,
   "typ": 800.0,
   "high": 1500.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.035": {
   "id": "PRD.MAR.035",
   "name": "Place rock rip-rap scour protection (land-based)",
   "unit": "t/day",
   "low": 300.0,
   "typ": 700.0,
   "high": 1500.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.036": {
   "id": "PRD.MAR.036",
   "name": "Place rip-rap from barge (around piles)",
   "unit": "t/day",
   "low": 150.0,
   "typ": 400.0,
   "high": 800.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.037": {
   "id": "PRD.MAR.037",
   "name": "Place articulated concrete mattress",
   "unit": "m2/day",
   "low": 100.0,
   "typ": 300.0,
   "high": 600.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.038": {
   "id": "PRD.MAR.038",
   "name": "Grout-bag / fabric-form mattress around piles (diver-assisted)",
   "unit": "m2/day",
   "low": 30.0,
   "typ": 80.0,
   "high": 150.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.009": {
   "id": "PRD.MAR.009",
   "name": "In-situ pile cap / headstock concrete over water (form, fix, pour)",
   "unit": "m3/day",
   "low": 8.0,
   "typ": 20.0,
   "high": 40.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.012": {
   "id": "PRD.MAR.012",
   "name": "Reinforcement fixing, marine deck/cap",
   "unit": "t/day per gang",
   "low": 1.0,
   "typ": 2.5,
   "high": 4.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.010": {
   "id": "PRD.MAR.010",
   "name": "Place precast deck planks / soffit units",
   "unit": "no/day",
   "low": 8.0,
   "typ": 20.0,
   "high": 35.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.011": {
   "id": "PRD.MAR.011",
   "name": "In-situ topping deck pour (pump from deck)",
   "unit": "m2/day",
   "low": 60.0,
   "typ": 150.0,
   "high": 300.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.039": {
   "id": "PRD.MAR.039",
   "name": "Install fender system (cone/cell + panel + chains), per set",
   "unit": "set/day",
   "low": 0.5,
   "typ": 1.5,
   "high": 3.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.041": {
   "id": "PRD.MAR.041",
   "name": "Install chemical/mechanical anchor set for fittings",
   "unit": "no/day",
   "low": 8.0,
   "typ": 16.0,
   "high": 30.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.040": {
   "id": "PRD.MAR.040",
   "name": "Install bollard / QRH (set out, anchor, set, torque)",
   "unit": "no/day",
   "low": 1.0,
   "typ": 3.0,
   "high": 6.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.042": {
   "id": "PRD.MAR.042",
   "name": "Abrasive blast + coat marine steel (multi-coat system)",
   "unit": "m2/day per crew",
   "low": 60.0,
   "typ": 150.0,
   "high": 300.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.043": {
   "id": "PRD.MAR.043",
   "name": "Install HDPE/concrete pile jacket + grout (splash zone)",
   "unit": "no/day",
   "low": 2.0,
   "typ": 5.0,
   "high": 10.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.044": {
   "id": "PRD.MAR.044",
   "name": "Install sacrificial anodes (bolt-on/stand-off)",
   "unit": "no/day",
   "low": 6.0,
   "typ": 15.0,
   "high": 30.0,
   "source": "S-065",
   "path": ""
  },
  "PRD.MAR.004": {
   "id": "PRD.MAR.004",
   "name": "Pitch & vibrate steel sheet pile (combi/anchored wall)",
   "unit": "m2/shift",
   "low": 40.0,
   "typ": 80.0,
   "high": 140.0,
   "source": "S-065",
   "path": ""
  }
 }
}