 "version": "1.0",
 "packages": [
  {
   "id": "setup",
   "title": "Survey, staging and traffic switches",
   "phase": "Enabling works",
   "unit": "released workfronts",
   "source": "DISC-TRAFFIC-METH-001",
   "guides": [
    "methods/traffic-management-and-staging"
   ],
   "bands": [],
   "plant": "Survey party, traffic crew, protection vehicles and signs. Size the spread by concurrent closures and switch locations.",
   "method": "Split the corridor into chainage, carriageway and stage. Verify survey control, service information and traffic arrangements, then record the usable closure window.",
   "takeoff": "Count workfront releases. Estimate traffic attendance by closure shift and survey by crew attendance separately.",
   "release": "Issue the stage drawing, limits, access times and survey control to each trade. Traffic management continues until the stage switch or reopening.",
   "basis": "Temporary devices, repeat switches and out-of-hours attendance can recur even where permanent quantities stay constant.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [],
     "after": [
      "utilities",
      "strip"
     ]
    },
    "rural-seal": {
     "before": [],
     "after": [
      "utilities",
      "strip"
     ]
    },
    "rigid": {
     "before": [],
     "after": [
      "utilities",
      "strip"
     ]
    },
    "overlay": {
     "before": [],
     "after": [
      "utilities"
     ]
    },
    "rehab-stabilised": {
     "before": [],
     "after": [
      "utilities"
     ]
    }
   }
  },
  {
   "id": "strip",
   "title": "Clearing and topsoil stripping",
   "phase": "Enabling works",
   "unit": "m³ in situ",
   "source": "EW-SITE-PREP-001",
   "guides": [
    "dozer-crawler-20t",
    "adt-30t"
   ],
   "bands": [
    "EW.001"
   ],
   "plant": "Dozer or excavator, haul units and environmental crew. Check stockpile reach and material segregation.",
   "method": "Set out the approved footprint and install the applicable erosion controls. Strip by measured depth and haul reusable topsoil to the nominated stockpile.",
   "takeoff": "Multiply surveyed footprint by stripping depth by zone. Track stockpiled, exported and reinstated volumes separately.",
   "release": "Release exposed formation limits and surveyed stockpile quantities to earthworks and drainage crews.",
   "basis": "Long leads, vegetation boundaries and double handling reduce output. Confirm the volume basis of the reference band.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "setup"
     ],
     "after": [
      "cut",
      "drain"
     ]
    },
    "rural-seal": {
     "before": [
      "setup"
     ],
     "after": [
      "cut",
      "drain"
     ]
    },
    "rigid": {
     "before": [
      "setup"
     ],
     "after": [
      "cut",
      "drain"
     ]
    }
   }
  },
  {
   "id": "cut",
   "title": "Bulk cut and haul",
   "phase": "Earthworks",
   "unit": "bank m³",
   "source": "EW-BULK-EARTHWORKS-001",
   "guides": [
    "excavator-20t",
    "adt-30t",
    "methods/bulk-earthworks"
   ],
   "bands": [
    "EW.002",
    "EW.003",
    "EW.007"
   ],
   "plant": "Excavator or dozer, trucks, grader and water cart. Match loader passes, truck cycles and receiving capacity.",
   "method": "Classify cut by material and destination. Excavate, load and dispatch against a mass-haul schedule. Separate unsuitable material and spoil.",
   "takeoff": "Calculate bank volume from survey surfaces. Reconcile truck payloads using material density or a documented conversion to loose volume.",
   "release": "Give the fill crew the released material type and delivery profile. Issue cut-floor levels and disposal dockets.",
   "basis": "Split short push, long haul and disposal. A band that includes cut-to-fill may overlap the separate fill spread.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "utilities",
      "strip"
     ],
     "after": [
      "fill"
     ]
    },
    "rural-seal": {
     "before": [
      "strip",
      "utilities"
     ],
     "after": [
      "fill"
     ]
    },
    "rigid": {
     "before": [
      "strip",
      "utilities"
     ],
     "after": [
      "fill"
     ]
    }
   }
  },
  {
   "id": "fill",
   "title": "Embankment placement and compaction",
   "phase": "Earthworks",
   "unit": "compacted m³",
   "source": "DISC-EARTH-METH-001",
   "guides": [
    "dozer-crawler-20t",
    "roller-padfoot-12t",
    "water-cart-13kl"
   ],
   "bands": [
    "EW.014",
    "EW.015"
   ],
   "plant": "Spreading dozer or grader, water cart, roller and testing crew. Match roller type and passes to the fill trial.",
   "method": "Prepare the receiving bench, spread in controlled lifts, condition moisture and compact. Keep lot boundaries visible to the test crew.",
   "takeoff": "Take compacted volume from the design surface difference. Convert to imported tonnes using an agreed density and reconcile deliveries.",
   "release": "Record lift acceptance, level and material class. Release the next lift or formation trim for that chainage.",
   "basis": "Distinguish purchased fill, excavated reuse and compacted output. Testing or water supply can control the shift.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "cut",
      "drain"
     ],
     "after": [
      "subsoil",
      "formation"
     ]
    },
    "rural-seal": {
     "before": [
      "cut",
      "drain"
     ],
     "after": [
      "formation"
     ]
    },
    "rigid": {
     "before": [
      "cut",
      "drain"
     ],
     "after": [
      "formation"
     ]
    }
   }
  },
  {
   "id": "utilities",
   "title": "Service verification and protection",
   "phase": "Enabling works",
   "unit": "service conflicts released",
   "source": "methods/utility-relocation-and-protection",
   "guides": [
    "methods/utility-relocation-and-protection",
    "excavator-mini-5t"
   ],
   "bands": [],
   "plant": "Survey, locator, vacuum excavation subcontractor and network representatives. Match plant to access and service-owner conditions.",
   "method": "Register crossings, confirm known locations and levels, coordinate the approved protection or relocation, then update the survey model.",
   "takeoff": "Count conflicts by service type and treatment. Price potholes, relocation lengths and attendance as separate measured resources.",
   "release": "Provide the released service plan and unresolved exclusion zones to drainage and earthworks crews.",
   "basis": "Owner attendance and staged outages can constrain the workfront independently of excavation quantity.",
   "reference_kind": "Vaultix",
   "reference_path": "methods/utility-relocation-and-protection/index.html",
   "paths": {
    "urban-asphalt": {
     "before": [
      "setup"
     ],
     "after": [
      "cut",
      "drain"
     ]
    },
    "rural-seal": {
     "before": [
      "setup"
     ],
     "after": [
      "cut",
      "drain"
     ]
    },
    "rigid": {
     "before": [
      "setup"
     ],
     "after": [
      "cut",
      "drain"
     ]
    },
    "overlay": {
     "before": [
      "setup"
     ],
     "after": [
      "mill"
     ]
    },
    "rehab-stabilised": {
     "before": [
      "setup"
     ],
     "after": [
      "mill"
     ]
    }
   }
  },
  {
   "id": "drain",
   "title": "Cross drainage and culvert installation",
   "phase": "Drainage",
   "unit": "m of pipe barrel",
   "source": "DISC-DRAIN-METH-001",
   "guides": [
    "methods/culvert-installation",
    "excavator-20t",
    "temporary-works/trench-shoring-boxes"
   ],
   "bands": [
    "DR.006",
    "DR.010",
    "DR.011"
   ],
   "plant": "Excavator, lifting spread, bedding crew, compactors and survey. Select the lift arrangement by unit mass, reach and trench geometry.",
   "method": "Set out the outlet and crossing. Excavate, prepare bedding, lay units to line and grade, and backfill in accepted lifts. Stage embankment interfaces at the design elevation.",
   "takeoff": "Sum barrel lengths for each run and diameter. Carry pits, headwalls, bedding and excavation in their own measurement units.",
   "release": "Provide invert survey, joint inspection and backfill release before the pavement crew crosses the trench.",
   "basis": "Separate depth, groundwater, shoring and traffic staging. The DN600 laying band covers a particular pipe size and operation.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "utilities",
      "strip"
     ],
     "after": [
      "fill",
      "kerb"
     ]
    },
    "rural-seal": {
     "before": [
      "strip",
      "utilities"
     ],
     "after": [
      "fill"
     ]
    },
    "rigid": {
     "before": [
      "strip",
      "utilities"
     ],
     "after": [
      "fill"
     ]
    }
   }
  },
  {
   "id": "subsoil",
   "title": "Subsoil drains and outlets",
   "phase": "Drainage",
   "unit": "m of drain",
   "source": "DR-SUBSOIL-001",
   "guides": [
    "methods/trenching-and-pipelaying",
    "excavator-mini-5t"
   ],
   "bands": [],
   "plant": "Trencher or compact excavator, aggregate delivery, geotextile and pipe crew. Confirm outlet access.",
   "method": "Locate outlets, cut the trench, install the specified drainage assembly and tie into the outlet. Survey and inspect before cover.",
   "takeoff": "Measure installed drain length. Take filter aggregate by trench section and outlets by count.",
   "release": "Release the covered drainage line with outlet location and photographs to the formation crew.",
   "basis": "Short runs, service crossings and inaccessible outlets can dominate the metres installed per shift.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "fill"
     ],
     "after": [
      "formation"
     ]
    }
   }
  },
  {
   "id": "formation",
   "title": "Subgrade trim and proof roll",
   "phase": "Formation",
   "unit": "m² released",
   "source": "RD-SUBGRADE-001",
   "guides": [
    "grader-16t",
    "roller-smooth-12t",
    "water-cart-13kl"
   ],
   "bands": [
    "PV.001",
    "PV.020"
   ],
   "plant": "Grader, water cart, roller, nominated proof-roll vehicle and test crew. Allow space for inspection.",
   "method": "Trim to design grade and crossfall, condition and compact the formation, then inspect the nominated lot. Map soft areas for treatment and retest.",
   "takeoff": "Measure accepted formation area once. Record failed areas and treatment quantities separately.",
   "release": "Issue formation survey and lot acceptance before covering it. Unreleased areas remain separate workfronts.",
   "basis": "Proof-roll coverage and preparation output have different scopes. Keep rectification and retesting visible.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "fill",
      "subsoil"
     ],
     "after": [
      "capping"
     ]
    },
    "rural-seal": {
     "before": [
      "fill"
     ],
     "after": [
      "subbase"
     ]
    },
    "rigid": {
     "before": [
      "fill"
     ],
     "after": [
      "subbase"
     ]
    }
   }
  },
  {
   "id": "capping",
   "title": "Select-fill capping layer",
   "phase": "Formation",
   "unit": "compacted m³",
   "source": "RD-SUBGRADE-001",
   "guides": [
    "grader-16t",
    "roller-smooth-12t",
    "water-cart-13kl"
   ],
   "bands": [
    "PV.002"
   ],
   "plant": "Haul fleet, grader, roller and water cart. Check material source and moisture condition.",
   "method": "Release the formation, deliver approved select fill, spread the specified lift and trim after compaction.",
   "takeoff": "Use lot area × compacted thickness. Price delivered tonnes with a documented density and moisture basis.",
   "release": "Provide level and density records for the top of capping before the next pavement layer.",
   "basis": "Use where the pavement design calls for capping. Separate undercut replacement from uniform capping.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "formation"
     ],
     "after": [
      "subbase"
     ]
    }
   }
  },
  {
   "id": "subbase",
   "title": "Unbound granular subbase",
   "phase": "Pavement layers",
   "unit": "compacted m³",
   "source": "RD-PAVEMENT-001",
   "guides": [
    "grader-16t",
    "roller-smooth-12t",
    "water-cart-13kl"
   ],
   "bands": [
    "PV.003",
    "PV.005"
   ],
   "plant": "Truck delivery fleet, grader or spreader, water cart and compaction train. Balance quarry dispatch with lift acceptance.",
   "method": "Confirm substrate release and material compliance. Place and moisture-condition each lift, compact and trim, then test the lot.",
   "takeoff": "Area × compacted lift thickness gives placed volume. Use separate areas for widening, tapers and intersections.",
   "release": "Release level, thickness and test results to base placement, stabilisation or rigid pavement works.",
   "basis": "A 150 mm area band applies only to that lift basis. Include haul once in the supplying or placing spread.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "capping"
     ],
     "after": [
      "base",
      "kerb"
     ]
    },
    "rural-seal": {
     "before": [
      "formation"
     ],
     "after": [
      "base"
     ]
    },
    "rigid": {
     "before": [
      "formation"
     ],
     "after": [
      "concrete"
     ]
    }
   }
  },
  {
   "id": "base",
   "title": "Unbound granular base",
   "phase": "Pavement layers",
   "unit": "compacted m³",
   "source": "DISC-ROAD-METH-002",
   "guides": [
    "grader-16t",
    "roller-smooth-12t",
    "water-cart-13kl"
   ],
   "bands": [
    "PV.004"
   ],
   "plant": "Fine-trim grader, delivery fleet, roller and survey crew. Allow tighter finishing control than bulk fill.",
   "method": "Deliver compliant material to the released subbase, compact, trim to finished profile and inspect drainage paths and crossfall.",
   "takeoff": "Sum compacted lift volumes. Track overbuild and trimming loss separately from accepted design quantity.",
   "release": "Release top-of-base survey, material tests and surface condition to the specified surfacing crew.",
   "basis": "Short night possessions, trimming and correcting levels may govern the lot even with adequate quarry supply.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "subbase"
     ],
     "after": [
      "prime"
     ]
    },
    "rural-seal": {
     "before": [
      "subbase"
     ],
     "after": [
      "primerseal",
      "shoulders"
     ]
    }
   }
  },
  {
   "id": "stabilise",
   "title": "In-situ pavement stabilisation",
   "phase": "Pavement layers",
   "unit": "m² treated",
   "source": "RD-STABILISED-001",
   "guides": [
    "soil-stabiliser-recycler",
    "water-cart-13kl",
    "methods/cement-and-lime-stabilisation"
   ],
   "bands": [
    "PV.006",
    "PV.007",
    "PV.008"
   ],
   "plant": "Calibrated binder spreader, recycler, water cart, grader and rollers. Select the train against the approved binder system.",
   "method": "Release the treatment design and trial. Apply binder, mix the nominated depth, shape and compact inside the project working window, then protect and cure.",
   "takeoff": "Use treated width × length per pass, removing overlap from pay area. Derive binder demand from the approved application basis.",
   "release": "Issue treatment depth, spread records, test results and cure release before the overlying treatment.",
   "basis": "Lime, cement and foamed bitumen have different production and curing constraints. Separate binder supply and remobilisation.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "rehab-stabilised": {
     "before": [
      "patch"
     ],
     "after": [
      "primerseal",
      "shoulders"
     ]
    }
   }
  },
  {
   "id": "kerb",
   "title": "Kerb, channel and pit interfaces",
   "phase": "Roadside works",
   "unit": "m of kerb",
   "source": "RD-KERB-FINISH-001",
   "guides": [
    "methods/kerb-channel-and-drainage-pits",
    "excavator-mini-5t"
   ],
   "bands": [],
   "plant": "Extrusion machine or forms, concrete supply, finishing crew and survey. Use hand forming at short transitions and returns.",
   "method": "Survey line, level and pit throats. Prepare the foundation, construct kerb and channel, finish joints and protect the fresh work.",
   "takeoff": "Measure kerb by profile length. Schedule returns, crossings, adaptors and pit adjustments separately.",
   "release": "Release kerb alignment, drainage levels and cure status before adjacent paving or edge completion.",
   "basis": "Match kerb timing to the pavement detail. Rural sections may have formed shoulders instead.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "subbase",
      "drain"
     ],
     "after": [
      "prime",
      "signs"
     ]
    }
   }
  },
  {
   "id": "mill",
   "title": "Cold milling and reclaimed asphalt removal",
   "phase": "Rehabilitation",
   "unit": "m² milled",
   "source": "methods/road-rehabilitation",
   "guides": [
    "cold-planer",
    "truck-quad-dog",
    "methods/road-rehabilitation"
   ],
   "bands": [
    "PV.018",
    "PV.019"
   ],
   "plant": "Cold planer, cartage trucks, sweeper and survey crew. Match milling width and depth to available fleet and closure.",
   "method": "Mark milling depths and tie-ins, profile in planned passes, load recovered asphalt and sweep. Inspect the exposed surface.",
   "takeoff": "Measure plan area by depth band. Estimate reclaimed tonnes from area × removed thickness × existing density and reconcile dockets.",
   "release": "Release the inspected milled lot or direct local failures to patching before overlay.",
   "basis": "The source band excludes RAP cartage or disposal. Track queueing, pass count and disposal location separately.",
   "reference_kind": "Vaultix",
   "reference_path": "methods/road-rehabilitation/index.html",
   "paths": {
    "overlay": {
     "before": [
      "utilities"
     ],
     "after": [
      "patch"
     ]
    },
    "rehab-stabilised": {
     "before": [
      "utilities"
     ],
     "after": [
      "patch"
     ]
    }
   }
  },
  {
   "id": "patch",
   "title": "Local pavement repairs and tie-ins",
   "phase": "Rehabilitation",
   "unit": "m² repaired",
   "source": "methods/road-rehabilitation",
   "guides": [
    "excavator-mini-5t",
    "roller-smooth-12t",
    "methods/road-rehabilitation"
   ],
   "bands": [],
   "plant": "Saw cutter or planer, excavator, compaction plant and small paving crew. Group patches by depth and material.",
   "method": "Map defects on the milled surface, excavate affected material, reconstruct the specified layers and finish tie-in levels.",
   "takeoff": "Use patch area by repair depth. Derive spoil and replacement volume separately for each patch type.",
   "release": "Document repaired locations and finished level before tack and overlay.",
   "basis": "Scattered patches increase travel and setup per square metre. Allow investigation after milling where scope is provisional.",
   "reference_kind": "Vaultix",
   "reference_path": "methods/road-rehabilitation/index.html",
   "paths": {
    "overlay": {
     "before": [
      "mill"
     ],
     "after": [
      "tack"
     ]
    },
    "rehab-stabilised": {
     "before": [
      "mill"
     ],
     "after": [
      "stabilise"
     ]
    }
   }
  },
  {
   "id": "prime",
   "title": "Prime coat on prepared granular base",
   "phase": "Surfacing",
   "unit": "m² primed",
   "source": "RD-SEAL-001",
   "guides": [
    "methods/asphalt-paving",
    "roller-multi-tyre-20t"
   ],
   "bands": [
    "PV.009"
   ],
   "plant": "Bitumen distributor, sweeper, supply tanker and protection crew. Confirm surface readiness and application design.",
   "method": "Clean the accepted base, apply the specified prime, record the spray area and protect it for the required release interval.",
   "takeoff": "Use net area by lot. Calculate litres against the specified application basis and record surplus separately.",
   "release": "Release the primed surface after the specified absorption or curing interval and inspection.",
   "basis": "Prime, primerseal and tack serve different interfaces. Select the treatment shown in the contract.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "base",
      "kerb"
     ],
     "after": [
      "asphalt-base"
     ]
    }
   }
  },
  {
   "id": "primerseal",
   "title": "Primerseal and holding period",
   "phase": "Surfacing",
   "unit": "m² primersealed",
   "source": "RD-SEAL-001",
   "guides": [
    "roller-multi-tyre-20t",
    "methods/road-rehabilitation"
   ],
   "bands": [
    "PV.010"
   ],
   "plant": "Distributor, chip spreader, aggregate trucks, rollers and broom. Match chip supply to the spray run.",
   "method": "Prepare and inspect the granular base, apply the approved binder and cover aggregate, roll and sweep. Manage the holding interval and traffic.",
   "takeoff": "Measure sealed plan area once. Estimate binder and cover aggregate separately from the final seal quantities.",
   "release": "Record spray sheets and surface condition, then release for the final seal or designated overlay.",
   "basis": "Confirm whether the design calls for a primerseal or prime. Allow return visits and holding-period maintenance where specified.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "rural-seal": {
     "before": [
      "base"
     ],
     "after": [
      "seal"
     ]
    },
    "rehab-stabilised": {
     "before": [
      "stabilise"
     ],
     "after": [
      "seal"
     ]
    }
   }
  },
  {
   "id": "tack",
   "title": "Tack coat and asphalt interface",
   "phase": "Surfacing",
   "unit": "m² of interface",
   "source": "DISC-ROAD-METH-001",
   "guides": [
    "asphalt-paver",
    "methods/asphalt-paving"
   ],
   "bands": [],
   "plant": "Sprayer, sweeper and traffic crew. Match the application width to the paving run and plant access.",
   "method": "Inspect and clean the existing or intermediate surface, apply the approved tack and release the interface in the specified condition.",
   "takeoff": "Measure each treated interface separately. Distinguish residual binder and emulsion quantities when deriving litres.",
   "release": "Release the interface directly to paving and protect it from traffic contamination.",
   "basis": "Where the asphalt supply-and-lay item already includes tack, allocate the resource within that item once.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "asphalt-base"
     ],
     "after": [
      "wearing"
     ]
    },
    "overlay": {
     "before": [
      "patch"
     ],
     "after": [
      "wearing"
     ]
    }
   }
  },
  {
   "id": "asphalt-base",
   "title": "Asphalt base and intermediate lifts",
   "phase": "Surfacing",
   "unit": "t placed",
   "source": "RD-ASPHALT-001",
   "guides": [
    "asphalt-paver",
    "truck-quad-dog",
    "roller-multi-tyre-20t"
   ],
   "bands": [
    "PV.015",
    "PV.016"
   ],
   "plant": "Paver, feeder where required, haul fleet and roller train. Obtain mix dispatch, truck turnaround and compaction coverage.",
   "method": "Accept the supporting surface, sequence truck deliveries, pave the specified lift and complete compaction and joint treatment.",
   "takeoff": "Area × compacted thickness × mix density gives planned tonnes. Reconcile delivered, rejected and accepted tonnes by lift.",
   "release": "Provide layer survey, compaction and lot release before tack and the wearing lift.",
   "basis": "Separate thicknesses, mix designs and restricted runs. Use the existing asphalt-train calculator to test the controlling resource.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "prime"
     ],
     "after": [
      "tack"
     ]
    }
   }
  },
  {
   "id": "wearing",
   "title": "Asphalt wearing course",
   "phase": "Surfacing",
   "unit": "t placed",
   "source": "DISC-ROAD-METH-001",
   "guides": [
    "asphalt-paver",
    "roller-multi-tyre-20t",
    "methods/asphalt-paving"
   ],
   "bands": [
    "PV.013",
    "PV.014",
    "PV.016",
    "PV.017"
   ],
   "plant": "Paver and screed, delivery fleet, rollers, joint crew and survey. Select a feeder where the delivery method warrants one.",
   "method": "Release the paving interface, place the wearing lift to the intended profile, compact and finish joints and tie-ins.",
   "takeoff": "Measure accepted area and thickness by mix. Convert to tonnes using compacted density and reconcile against supply tickets.",
   "release": "Issue test and survey records plus traffic release status to the markings and handover teams.",
   "basis": "Do not use nominal paver capacity as achieved output. Check hot haul, closure length, joints and roller coverage.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "tack"
     ],
     "after": [
      "marking",
      "handover"
     ]
    },
    "overlay": {
     "before": [
      "tack"
     ],
     "after": [
      "marking",
      "handover"
     ]
    }
   }
  },
  {
   "id": "seal",
   "title": "Sprayed bituminous seal",
   "phase": "Surfacing",
   "unit": "m² finished seal",
   "source": "RD-SEAL-001",
   "guides": [
    "roller-multi-tyre-20t",
    "truck-quad-dog"
   ],
   "bands": [
    "PV.011",
    "PV.012"
   ],
   "plant": "Distributor, chip spreader, aggregate trucks, pneumatic rollers and broom. Plan tanker and aggregate replenishment.",
   "method": "Release the substrate treatment, spray and spread to the approved seal design, roll, sweep and record each run and coat.",
   "takeoff": "Measure the footprint once for a complete two-coat item. Compute coat-specific binder litres and aggregate quantities.",
   "release": "Release the finished seal following inspection, sweeping and the project traffic conditions.",
   "basis": "A two-coat production band already includes two passes. Include delayed sweeping and traffic management in the correct package.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "rural-seal": {
     "before": [
      "primerseal"
     ],
     "after": [
      "marking",
      "handover"
     ]
    },
    "rehab-stabilised": {
     "before": [
      "primerseal"
     ],
     "after": [
      "marking",
      "handover"
     ]
    }
   }
  },
  {
   "id": "concrete",
   "title": "Rigid concrete pavement placement",
   "phase": "Surfacing",
   "unit": "m³ placed",
   "source": "DISC-ROAD-METH-003",
   "guides": [
    "methods/rigid-concrete-pavement",
    "conc-boom-pump-42m"
   ],
   "bands": [],
   "plant": "Slipform paver or fixed forms, batch supply, delivery fleet, dowel and finishing crews. Assess fixed forms for short irregular bays.",
   "method": "Release the supporting layer and separation treatment where specified. Survey alignment, inspect embeds, place, texture and commence curing.",
   "takeoff": "Calculate slab volume by panel area × thickness. Measure thickened edges, transitions, dowels and joint accessories separately.",
   "release": "Deliver the pour record, joint layout, finish and curing status to the joint and strength-release crew.",
   "basis": "Continuous pour size, batch supply and concrete delivery govern placement. Keep curing and opening strength visible in the programme.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "rigid": {
     "before": [
      "subbase"
     ],
     "after": [
      "joints"
     ]
    }
   }
  },
  {
   "id": "joints",
   "title": "Concrete joints, curing and traffic release",
   "phase": "Surfacing",
   "unit": "panels released",
   "source": "RD-RIGID-001",
   "guides": [
    "methods/rigid-concrete-pavement"
   ],
   "bands": [],
   "plant": "Sawing and sealing equipment, curing crew, survey and testing team. Schedule return visits by pour lot.",
   "method": "Track cure, undertake specified joint operations, inspect joint geometry and compile strength evidence for the opening decision.",
   "takeoff": "Count panels released. Measure joint cutting and sealing by joint length and treatment type.",
   "release": "Issue the strength and joint release for each carriageway section before unrestricted loading or finishing work.",
   "basis": "Elapsed curing time and crew hours are different inputs. Enter the governing release wait separately from installation effort.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "rigid": {
     "before": [
      "concrete"
     ],
     "after": [
      "shoulders",
      "marking",
      "handover"
     ]
    }
   }
  },
  {
   "id": "shoulders",
   "title": "Shoulders, verges and tie-ins",
   "phase": "Roadside works",
   "unit": "compacted m³",
   "source": "RD-KERB-FINISH-001",
   "guides": [
    "grader-16t",
    "roller-smooth-12t",
    "water-cart-13kl"
   ],
   "bands": [
    "PV.021"
   ],
   "plant": "Grader, trucks, water cart and roller. Select smaller plant for narrow strips or constrained access.",
   "method": "Set shoulder and tie-in levels, place and compact suitable material, trim crossfall and check drainage at transitions.",
   "takeoff": "Sum shoulder lengths × applicable widths × compacted thickness. Treat tapers and sealed shoulder surfacing separately.",
   "release": "Release shoulder level, edge support and clear working width for barriers and guideposts.",
   "basis": "Model one roadside at a time where staging reduces access. Avoid duplicating shoulder quantities in mainline pavement.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "rural-seal": {
     "before": [
      "base"
     ],
     "after": [
      "barriers",
      "signs",
      "handover"
     ]
    },
    "rigid": {
     "before": [
      "joints"
     ],
     "after": [
      "barriers",
      "signs",
      "handover"
     ]
    },
    "rehab-stabilised": {
     "before": [
      "stabilise"
     ],
     "after": [
      "signs",
      "handover"
     ]
    }
   }
  },
  {
   "id": "barriers",
   "title": "Road safety barriers and terminals",
   "phase": "Roadside works",
   "unit": "m of installed barrier",
   "source": "TM-BARRIERS-001",
   "guides": [
    "excavator-mini-5t",
    "methods/traffic-management-and-staging"
   ],
   "bands": [
    "RF.001",
    "RF.002",
    "RF.003",
    "RF.006"
   ],
   "plant": "Post driver or drilling rig, handling vehicle and specialist installation crew. Match equipment to the barrier system and ground.",
   "method": "Set out offsets and terminal zones from the design. Confirm services and ground, install supports and rails or precast units, then inspect transitions.",
   "takeoff": "Measure runs by system and ground class. Count terminals, anchors and transitions independently.",
   "release": "Release chainage, offsets, terminal records and installation inspection to the commissioning register.",
   "basis": "Drivable posts and cored footings have different outputs. Do not apply a linear rail rate to terminals.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "rural-seal": {
     "before": [
      "shoulders"
     ],
     "after": [
      "handover"
     ]
    },
    "rigid": {
     "before": [
      "shoulders"
     ],
     "after": [
      "handover"
     ]
    }
   }
  },
  {
   "id": "signs",
   "title": "Signs, supports and delineators",
   "phase": "Roadside works",
   "unit": "sign assemblies",
   "source": "TM-SIGNS-001",
   "guides": [
    "excavator-mini-5t",
    "franna-25t"
   ],
   "bands": [
    "RF.015",
    "RF.017",
    "RF.009"
   ],
   "plant": "Auger or excavator, lifting vehicle, installation crew and survey. Match foundations and lifts to sign type.",
   "method": "Confirm chainages and sight lines, construct supports and install approved faces. Inspect orientation and clearances.",
   "takeoff": "Count complete assemblies by size and posts. Take face area, foundations and delineators separately where the schedule splits them.",
   "release": "Record chainage, sign type, orientation and as-built evidence for the traffic switch.",
   "basis": "Allow foundation curing and supplier lead time. A multi-post installation band may exclude sign-face supply.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "kerb"
     ],
     "after": [
      "handover"
     ]
    },
    "rural-seal": {
     "before": [
      "shoulders"
     ],
     "after": [
      "handover"
     ]
    },
    "rigid": {
     "before": [
      "shoulders"
     ],
     "after": [
      "handover"
     ]
    },
    "rehab-stabilised": {
     "before": [
      "shoulders"
     ],
     "after": [
      "handover"
     ]
    }
   }
  },
  {
   "id": "marking",
   "title": "Line marking and raised pavement markers",
   "phase": "Finishing",
   "unit": "line-km",
   "source": "TM-LINEMARKING-001",
   "guides": [
    "methods/traffic-management-and-staging"
   ],
   "bands": [
    "RF.020",
    "RF.021",
    "RF.022",
    "RF.024"
   ],
   "plant": "Line-marking truck, premark crew, hand applicators and traffic protection. Choose the plant against marking material and pattern.",
   "method": "Confirm the accepted surface and marking layout, set out lines, apply specified material and complete symbols and markers.",
   "takeoff": "Measure line length by pattern, colour and width. Track route-km, painted line-km, symbols and marker counts separately.",
   "release": "Issue layout and inspection records, plus readiness for the traffic switch.",
   "basis": "Allow curing or opening time for the selected marking system. Existing markings may need removal on rehabilitation work.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "wearing"
     ],
     "after": [
      "handover"
     ]
    },
    "rural-seal": {
     "before": [
      "seal"
     ],
     "after": [
      "handover"
     ]
    },
    "rigid": {
     "before": [
      "joints"
     ],
     "after": [
      "handover"
     ]
    },
    "overlay": {
     "before": [
      "wearing"
     ],
     "after": [
      "handover"
     ]
    },
    "rehab-stabilised": {
     "before": [
      "seal"
     ],
     "after": [
      "handover"
     ]
    }
   }
  },
  {
   "id": "handover",
   "title": "Lot reconciliation and reopening",
   "phase": "Handover",
   "unit": "lots released",
   "source": "DISC-ROAD-OVW-001",
   "guides": [
    "methods/traffic-management-and-staging"
   ],
   "bands": [],
   "plant": "Survey, quality, traffic and superintendent representatives. Schedule inspections against the opening window.",
   "method": "Reconcile finished levels and quantities, close lot records and defects, verify drainage, furniture and markings, then coordinate the authorised traffic switch.",
   "takeoff": "Count released lots by chainage and carriageway. Record outstanding defects and post-opening maintenance commitments separately.",
   "release": "Hand over the accepted as-built plan, test register, asset inventory and traffic-switch record.",
   "basis": "Practical completion and reopening can have different dates. Carry unresolved defects into the agreed close-out process.",
   "reference_kind": "Vaultix",
   "reference_path": "",
   "paths": {
    "urban-asphalt": {
     "before": [
      "wearing",
      "signs",
      "marking"
     ],
     "after": []
    },
    "rural-seal": {
     "before": [
      "seal",
      "marking",
      "shoulders",
      "barriers",
      "signs"
     ],
     "after": []
    },
    "rigid": {
     "before": [
      "joints",
      "shoulders",
      "barriers",
      "marking",
      "signs"
     ],
     "after": []
    },
    "overlay": {
     "before": [
      "wearing",
      "marking"
     ],
     "after": []
    },
    "rehab-stabilised": {
     "before": [
      "marking",
      "signs",
      "shoulders",
      "seal"
     ],
     "after": []
    }
   }
  }
 ],
 "routes": {
  "urban-asphalt": {
   "title": "New urban asphalt road",
   "basis": "A kerbed road with cross drainage, subsoil drainage, select capping, granular layers and two asphalt lifts. Kerb and base share a platform. Surfacing waits for both releases.",
   "nodes": [
    {
     "id": "setup",
     "predecessors": []
    },
    {
     "id": "utilities",
     "predecessors": [
      "setup"
     ]
    },
    {
     "id": "strip",
     "predecessors": [
      "setup"
     ]
    },
    {
     "id": "cut",
     "predecessors": [
      "utilities",
      "strip"
     ]
    },
    {
     "id": "drain",
     "predecessors": [
      "utilities",
      "strip"
     ]
    },
    {
     "id": "fill",
     "predecessors": [
      "cut",
      "drain"
     ]
    },
    {
     "id": "subsoil",
     "predecessors": [
      "fill"
     ]
    },
    {
     "id": "formation",
     "predecessors": [
      "fill",
      "subsoil"
     ]
    },
    {
     "id": "capping",
     "predecessors": [
      "formation"
     ]
    },
    {
     "id": "subbase",
     "predecessors": [
      "capping"
     ]
    },
    {
     "id": "base",
     "predecessors": [
      "subbase"
     ]
    },
    {
     "id": "kerb",
     "predecessors": [
      "subbase",
      "drain"
     ]
    },
    {
     "id": "prime",
     "predecessors": [
      "base",
      "kerb"
     ]
    },
    {
     "id": "asphalt-base",
     "predecessors": [
      "prime"
     ]
    },
    {
     "id": "tack",
     "predecessors": [
      "asphalt-base"
     ]
    },
    {
     "id": "wearing",
     "predecessors": [
      "tack"
     ]
    },
    {
     "id": "signs",
     "predecessors": [
      "kerb"
     ]
    },
    {
     "id": "marking",
     "predecessors": [
      "wearing"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "wearing",
      "signs",
      "marking"
     ]
    }
   ]
  },
  "rural-seal": {
   "title": "New rural sprayed-seal road",
   "basis": "An unkerbed road with a primerseal, a subsequent final seal and granular shoulders. This example includes roadside barriers. Confirm the seal design, holding interval and barrier limits by chainage.",
   "nodes": [
    {
     "id": "setup",
     "predecessors": []
    },
    {
     "id": "utilities",
     "predecessors": [
      "setup"
     ]
    },
    {
     "id": "strip",
     "predecessors": [
      "setup"
     ]
    },
    {
     "id": "cut",
     "predecessors": [
      "strip",
      "utilities"
     ]
    },
    {
     "id": "drain",
     "predecessors": [
      "strip",
      "utilities"
     ]
    },
    {
     "id": "fill",
     "predecessors": [
      "cut",
      "drain"
     ]
    },
    {
     "id": "formation",
     "predecessors": [
      "fill"
     ]
    },
    {
     "id": "subbase",
     "predecessors": [
      "formation"
     ]
    },
    {
     "id": "base",
     "predecessors": [
      "subbase"
     ]
    },
    {
     "id": "primerseal",
     "predecessors": [
      "base"
     ]
    },
    {
     "id": "seal",
     "predecessors": [
      "primerseal"
     ]
    },
    {
     "id": "shoulders",
     "predecessors": [
      "base"
     ]
    },
    {
     "id": "barriers",
     "predecessors": [
      "shoulders"
     ]
    },
    {
     "id": "signs",
     "predecessors": [
      "shoulders"
     ]
    },
    {
     "id": "marking",
     "predecessors": [
      "seal"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "seal",
      "marking",
      "shoulders",
      "barriers",
      "signs"
     ]
    }
   ]
  },
  "rigid": {
   "title": "New rigid concrete pavement",
   "basis": "A rigid carriageway with an approved supporting layer and project-specific separation treatment in the slab package. Joint completion and strength release govern traffic access.",
   "nodes": [
    {
     "id": "setup",
     "predecessors": []
    },
    {
     "id": "utilities",
     "predecessors": [
      "setup"
     ]
    },
    {
     "id": "strip",
     "predecessors": [
      "setup"
     ]
    },
    {
     "id": "cut",
     "predecessors": [
      "strip",
      "utilities"
     ]
    },
    {
     "id": "drain",
     "predecessors": [
      "strip",
      "utilities"
     ]
    },
    {
     "id": "fill",
     "predecessors": [
      "cut",
      "drain"
     ]
    },
    {
     "id": "formation",
     "predecessors": [
      "fill"
     ]
    },
    {
     "id": "subbase",
     "predecessors": [
      "formation"
     ]
    },
    {
     "id": "concrete",
     "predecessors": [
      "subbase"
     ]
    },
    {
     "id": "joints",
     "predecessors": [
      "concrete"
     ]
    },
    {
     "id": "shoulders",
     "predecessors": [
      "joints"
     ]
    },
    {
     "id": "barriers",
     "predecessors": [
      "shoulders"
     ]
    },
    {
     "id": "marking",
     "predecessors": [
      "joints"
     ]
    },
    {
     "id": "signs",
     "predecessors": [
      "shoulders"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "joints",
      "shoulders",
      "barriers",
      "marking",
      "signs"
     ]
    }
   ]
  },
  "overlay": {
   "title": "Mill, patch and asphalt overlay",
   "basis": "A staged overnight resurfacing lot with milling, local repairs and one overlay lift. Confirm that each shift can restore the road to the specified temporary or permanent traffic condition.",
   "nodes": [
    {
     "id": "setup",
     "predecessors": []
    },
    {
     "id": "utilities",
     "predecessors": [
      "setup"
     ]
    },
    {
     "id": "mill",
     "predecessors": [
      "utilities"
     ]
    },
    {
     "id": "patch",
     "predecessors": [
      "mill"
     ]
    },
    {
     "id": "tack",
     "predecessors": [
      "patch"
     ]
    },
    {
     "id": "wearing",
     "predecessors": [
      "tack"
     ]
    },
    {
     "id": "marking",
     "predecessors": [
      "wearing"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "wearing",
      "marking"
     ]
    }
   ]
  },
  "rehab-stabilised": {
   "title": "Rehabilitation with in-situ stabilisation",
   "basis": "Existing surfacing is removed and the underlying pavement is stabilised, cured, primersealed and sealed. Deep local failures are repaired before treatment. Binder and seal systems follow the project design.",
   "nodes": [
    {
     "id": "setup",
     "predecessors": []
    },
    {
     "id": "utilities",
     "predecessors": [
      "setup"
     ]
    },
    {
     "id": "mill",
     "predecessors": [
      "utilities"
     ]
    },
    {
     "id": "patch",
     "predecessors": [
      "mill"
     ]
    },
    {
     "id": "stabilise",
     "predecessors": [
      "patch"
     ]
    },
    {
     "id": "primerseal",
     "predecessors": [
      "stabilise"
     ]
    },
    {
     "id": "seal",
     "predecessors": [
      "primerseal"
     ]
    },
    {
     "id": "shoulders",
     "predecessors": [
      "stabilise"
     ]
    },
    {
     "id": "marking",
     "predecessors": [
      "seal"
     ]
    },
    {
     "id": "signs",
     "predecessors": [
      "shoulders"
     ]
    },
    {
     "id": "handover",
     "predecessors": [
      "marking",
      "signs",
      "shoulders",
      "seal"
     ]
    }
   ]
  }
 },
 "benchmarks": {
  "EW.001": {
   "id": "PRD.EW.001",
   "activity": "Strip & stockpile topsoil",
   "unit": "m3/hr",
   "low": 120.0,
   "typical": 200.0,
   "high": 320.0,
   "source_key": "S-061",
   "file": ""
  },
  "EW.002": {
   "id": "PRD.EW.002",
   "activity": "Bulk excavation cut-to-fill (30t excavator + truck fleet)",
   "unit": "m3/hr",
   "low": 80.0,
   "typical": 120.0,
   "high": 160.0,
   "source_key": "S-061",
   "file": ""
  },
  "EW.003": {
   "id": "PRD.EW.003",
   "activity": "Cut-to-spoil (excavator load-out, no on-site reuse)",
   "unit": "m3/hr (loading limited)",
   "low": 90.0,
   "typical": 130.0,
   "high": 170.0,
   "source_key": "S-061",
   "file": ""
  },
  "EW.007": {
   "id": "PRD.EW.007",
   "activity": "Load & haul - 1 km one-way",
   "unit": "m3/hr",
   "low": 70.0,
   "typical": 110.0,
   "high": 150.0,
   "source_key": "S-061",
   "file": ""
  },
  "EW.014": {
   "id": "PRD.EW.014",
   "activity": "Spread & level fill (place dumped material to grade)",
   "unit": "m3/hr",
   "low": 150.0,
   "typical": 300.0,
   "high": 500.0,
   "source_key": "S-061",
   "file": ""
  },
  "EW.015": {
   "id": "PRD.EW.015",
   "activity": "Compact fill - by layer (roller passes)",
   "unit": "m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes)",
   "low": 150.0,
   "typical": 300.0,
   "high": 500.0,
   "source_key": "S-061",
   "file": ""
  },
  "DR.006": {
   "id": "PRD.DR.006",
   "activity": "RCP pipe lay DN600",
   "unit": "m/day",
   "low": 30.0,
   "typical": 50.0,
   "high": 65.0,
   "source_key": "S-061",
   "file": ""
  },
  "DR.010": {
   "id": "PRD.DR.010",
   "activity": "Bedding & haunch (Type 1 / Type 2)",
   "unit": "m3/day placed",
   "low": 20.0,
   "typical": 40.0,
   "high": 60.0,
   "source_key": "S-061",
   "file": ""
  },
  "DR.011": {
   "id": "PRD.DR.011",
   "activity": "Backfill & compact (select / in-situ)",
   "unit": "m3/day",
   "low": 150.0,
   "typical": 250.0,
   "high": 350.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.001": {
   "id": "PRD.PV.001",
   "activity": "Subgrade preparation & trim (top of formation)",
   "unit": "m2/hr",
   "low": 200.0,
   "typical": 450.0,
   "high": 800.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.020": {
   "id": "PRD.PV.020",
   "activity": "Pavement compaction / proof roll (acceptance)",
   "unit": "m2/hr",
   "low": 1500.0,
   "typical": 3000.0,
   "high": 5000.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.002": {
   "id": "PRD.PV.002",
   "activity": "Capping / select-fill layer (supply + place + compact)",
   "unit": "m3/hr (placing crew)",
   "low": 60.0,
   "typical": 110.0,
   "high": 170.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.003": {
   "id": "PRD.PV.003",
   "activity": "Sub-base unbound granular Type 2.3 (supply + place + compact)",
   "unit": "m3/hr (placing crew)",
   "low": 55.0,
   "typical": 100.0,
   "high": 160.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.005": {
   "id": "PRD.PV.005",
   "activity": "Unbound base/sub-base - per m2 basis (150 mm compacted lift)",
   "unit": "m2/hr (at 150 mm lift)",
   "low": 350.0,
   "typical": 650.0,
   "high": 1100.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.004": {
   "id": "PRD.PV.004",
   "activity": "Base unbound granular Type 2.1 / DGB20 (supply + place + compact)",
   "unit": "m3/hr (placing crew, tighter tolerance)",
   "low": 45.0,
   "typical": 85.0,
   "high": 140.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.006": {
   "id": "PRD.PV.006",
   "activity": "In-situ stabilisation - lime (spread + mix + compact + cure)",
   "unit": "m2/day (≈ 250-600 m2/hr)",
   "low": 2000.0,
   "typical": 4000.0,
   "high": 7000.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.007": {
   "id": "PRD.PV.007",
   "activity": "In-situ stabilisation - cement (spread + mix + compact + cure)",
   "unit": "m2/day (≈ 250-550 m2/hr)",
   "low": 2000.0,
   "typical": 3800.0,
   "high": 6500.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.008": {
   "id": "PRD.PV.008",
   "activity": "In-situ stabilisation - foamed bitumen (FBS, recycler)",
   "unit": "m2/day (≈ 350-700 m2/hr)",
   "low": 3000.0,
   "typical": 5000.0,
   "high": 8500.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.018": {
   "id": "PRD.PV.018",
   "activity": "Profiling / cold planing - shallow (<=50 mm)",
   "unit": "m2/hr (at <=50 mm depth)",
   "low": 300.0,
   "typical": 700.0,
   "high": 1300.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.019": {
   "id": "PRD.PV.019",
   "activity": "Profiling / cold planing - deep / full-depth (>100 mm, multi-pass)",
   "unit": "m2/hr (multi-pass to full depth)",
   "low": 150.0,
   "typical": 400.0,
   "high": 800.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.009": {
   "id": "PRD.PV.009",
   "activity": "Prime coat (cutback / emulsion primer on unbound base)",
   "unit": "m2/day (≈ 1,000-3,000 m2/hr)",
   "low": 8000.0,
   "typical": 15000.0,
   "high": 25000.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.010": {
   "id": "PRD.PV.010",
   "activity": "Primer seal (primer binder + cover aggregate, 1 coat)",
   "unit": "m2/day (≈ 800-2,500 m2/hr)",
   "low": 6000.0,
   "typical": 12000.0,
   "high": 20000.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.015": {
   "id": "PRD.PV.015",
   "activity": "Asphalt AC20 base/intermediate course - by thickness (m2)",
   "unit": "m2/hr (at 60-70 mm lift)",
   "low": 280.0,
   "typical": 550.0,
   "high": 1000.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.016": {
   "id": "PRD.PV.016",
   "activity": "Asphalt - supply + lay + compact (tonnage basis)",
   "unit": "t/hr (paver-and-crew limited; ≈ 350-650 t/day)",
   "low": 40.0,
   "typical": 60.0,
   "high": 85.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.013": {
   "id": "PRD.PV.013",
   "activity": "Asphalt AC10 wearing course - by thickness (m2)",
   "unit": "m2/hr (at 40 mm lift)",
   "low": 300.0,
   "typical": 600.0,
   "high": 1100.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.014": {
   "id": "PRD.PV.014",
   "activity": "Asphalt AC14 - by thickness (m2)",
   "unit": "m2/hr (at 50 mm lift)",
   "low": 300.0,
   "typical": 600.0,
   "high": 1100.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.017": {
   "id": "PRD.PV.017",
   "activity": "Heavy-duty asphalt (EME2 / high-modulus / SMA)",
   "unit": "t/hr (tighter temperature/compaction control)",
   "low": 35.0,
   "typical": 55.0,
   "high": 75.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.011": {
   "id": "PRD.PV.011",
   "activity": "Sprayed seal - single/seal (14 mm, binder + cover aggregate)",
   "unit": "m2/day (≈ 600-1,900 m2/hr)",
   "low": 4000.0,
   "typical": 8000.0,
   "high": 15000.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.012": {
   "id": "PRD.PV.012",
   "activity": "Sprayed seal - double/two-coat (14/7 mm)",
   "unit": "m2/day (≈ 450-1,400 m2/hr, two passes)",
   "low": 3000.0,
   "typical": 6000.0,
   "high": 11000.0,
   "source_key": "S-061",
   "file": ""
  },
  "PV.021": {
   "id": "PRD.PV.021",
   "activity": "Shoulder gravel (supply + place + trim + compact)",
   "unit": "m3/hr (placing crew)",
   "low": 50.0,
   "typical": 95.0,
   "high": 150.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.001": {
   "id": "PRD.RF.001",
   "activity": "W-beam guardrail install (drivable ground)",
   "unit": "m/day",
   "low": 90.0,
   "typical": 150.0,
   "high": 220.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.002": {
   "id": "PRD.RF.002",
   "activity": "W-beam guardrail install (rock / cored / bolted footings)",
   "unit": "m/day",
   "low": 40.0,
   "typical": 80.0,
   "high": 120.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.003": {
   "id": "PRD.RF.003",
   "activity": "Guardrail end terminal (crash-tested, MASH)",
   "unit": "per day",
   "low": 1.5,
   "typical": 3.0,
   "high": 5.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.006": {
   "id": "PRD.RF.006",
   "activity": "Concrete barrier - precast F-shape / single-slope (placed)",
   "unit": "m/day",
   "low": 60.0,
   "typical": 120.0,
   "high": 200.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.015": {
   "id": "PRD.RF.015",
   "activity": "Regulatory / warning / guide sign on single post (<=2.2 m2)",
   "unit": "per day",
   "low": 8.0,
   "typical": 18.0,
   "high": 30.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.017": {
   "id": "PRD.RF.017",
   "activity": "Large / multi-post guide sign (3-10 m2, 2-3 posts)",
   "unit": "per day",
   "low": 0.5,
   "typical": 2.0,
   "high": 4.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.009": {
   "id": "PRD.RF.009",
   "activity": "Guideposts / delineators install",
   "unit": "per day",
   "low": 60.0,
   "typical": 120.0,
   "high": 200.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.020": {
   "id": "PRD.RF.020",
   "activity": "Longitudinal line marking - waterborne paint (single pass)",
   "unit": "km/line-km per day",
   "low": 8.0,
   "typical": 12.0,
   "high": 15.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.021": {
   "id": "PRD.RF.021",
   "activity": "Longitudinal line marking - thermoplastic (sprayed/extruded)",
   "unit": "km/day (machine) / much slower hand-applied",
   "low": 2.0,
   "typical": 6.0,
   "high": 10.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.022": {
   "id": "PRD.RF.022",
   "activity": "Raised pavement markers (RRPMs) install",
   "unit": "per day",
   "low": 150.0,
   "typical": 350.0,
   "high": 600.0,
   "source_key": "S-061",
   "file": ""
  },
  "RF.024": {
   "id": "PRD.RF.024",
   "activity": "Pavement symbols / legends / arrows (applied)",
   "unit": "per day (paint) / 10-30-60 (thermo)",
   "low": 20.0,
   "typical": 50.0,
   "high": 90.0,
   "source_key": "S-061",
   "file": ""
  }
 }
}