Quality and verification

Survey conformance and lot release

Use the project survey instruction, contract specification and inspection and test plan to define what will be measured, how it will be verified and who can release the lot.

Establish the acceptance basis

Reference frame and design

Identify the current issued alignment, model or drawing, revision, point or chainage, coordinate reference system, vertical datum and units. Record any site grid transformation, scale and tidal reference. Check control against an independent mark before set-out and again after a disturbance or instrument move.

Criterion and observation plan

Extract the acceptance clause and the applicable lower and upper limits. Define the lot boundary, sample locations, frequency, measurement uncertainty and decision rule. Agree who observes, independently checks, witnesses and releases each stage. Preserve any formal notice periods from the contract.

Inspection and release workflow

  1. Prepare the lot. Record design revision, inspection and test plan reference, nominated control, test method, acceptance criteria and required evidence before work starts.
  2. Observe before concealment. Survey the feature at the specified stage. Keep field files, calibration or instrument-check references, time, conditions, observer, photographs and asset identity. Use independent check observations where required.
  3. Compare and verify. Review coordinate basis, instrument uncertainty, sample completeness and deviations. Link material, installation and functional tests to the same lot. Follow the specified guard band or uncertainty rule for borderline results.
  4. Manage a departure. Identify affected work, record the nonconformance, obtain the authorised engineering disposition and repeat affected observations following correction. Retain both results and all approvals.
  5. Release and hand over. The designated reviewer signs the inspection record and any hold-point release. Supply the as-built plan or model, raw observations, comparison report, test results, dispositions and asset schedule to the receiving crew.

Observation register

Compare one scalar characteristic at a time, such as an elevation, offset, length or independently computed clearance. Enter all four values in the same unit. For a level of 100.000 m with a permissible ±5 mm deviation, enter limits −0.005 and +0.005 m using a keyboard minus sign. A comparison within the entered limits still requires the project uncertainty review and authorised lot release.

·

Observations are stored in this browser where local storage is available. Export the register to retain a copy with the project evidence.

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.