- Material transferContinuity of mix delivery determines how often the paver stops.
- ScreedMeasure paving width and thickness against the issued layer design.
- RollerThe compaction train must keep up with the paving front.
Construction flow by route
Read each package’s incoming releases. Branches can advance on separate crews or chainages. A shared row groups packages by dependency depth. Actual start times appear in the worksheet.
Lot programme and direct estimate
Enter one lot on a common roster. Use rates per productive hour in the displayed package unit. Crew and plant rates are per paid roster hour. Blank programme inputs leave their downstream releases open. Enter quantity zero for a confirmed exclusion.
Illustrative urban lot · 250 m × 7 m = 1,750 m². Each 150 mm granular lift is 262.5 compacted m³. At an assumed 2.4 t/m³, the 60 mm asphalt lift is 252 t and the 40 mm wearing lift is 168 t. Other quantities, outputs and waits are scenario inputs. Replace them with project evidence.
| Package / unit | Qty | Output / productive h | Release wait / shifts | Crew + plant $ / paid h | Variable $ / unit | Fixed $ | Work shifts | Start shift | Release shift | Direct AUD |
|---|
How quantities become time and cost
Work shifts = quantity ÷ measured output per productive hour ÷ workable hours per shift. Earliest start equals the latest release of all predecessors. Release equals earliest start plus work shifts plus the entered wait. An independent branch can run concurrently. Green-edged rows control the final release under these assumptions.
Direct AUD = work shifts × rostered hours × hourly crew and plant cost + quantity × variable unit cost + fixed allowance. Enter explicit zeros where there is no hourly or unit cost. Blank fixed cost and wait each mean zero. Add standby, shift minimums, shared traffic crews and recurring mobilisation once where they are incurred.
The programme uses fractional working shifts and independent branch resources. Convert cure and possession windows to this roster and check the actual opening time. Shared plant, night possessions, procurement lead time and minimum hire periods may extend it. Route inputs are retained in this browser when local storage is available.