Marine works / Construction flow and estimating

Marine lot programme

Piled wharf bay, floating crane and exposed seabed armour. Illustrative workfront.
  1. Precast deckDeck units span between headstocks. Keep the open bay available for scour placement and inspection.
  2. Steel pilesThe accepted pile-head group releases the cap and scour crews.
  3. Crane pontoonVessel access and positioning determine which bay the lifting spread can serve.
Marine packages
31
Construction routes
6
Productivity benchmarks
28

Construction flow by workfront

Follow the incoming releases on each card. Packages on different branches can overlap where vessel access, exclusion zones and plant availability permit. Open a package for the working method, plant spread, productivity basis, survey checks and receiving party.

Lot worksheet

Use accepted quantities in the units shown and output per productive hour. Paid hours drive spread cost. Workable hours drive production. Override the workable window on a row where tide, navigation or lifting access limits that operation. A blank override uses the common window.

Package / unitQuantityOutput / productive hWorkable h / shiftRelease wait (shifts)Spread AUD / paid hVariable AUD / unitFixed AUDWork shiftsStart shiftRelease shiftDirect AUD

Start is the latest incoming release. Release includes productive duration and any inspection, curing or access wait entered in shifts. Estimates use fractional shifts. Charge shared plant once across concurrent activities. Price standby, remobilisation or other wait costs explicitly. Enter zero for a known zero cost and leave unknown costs blank.

Lot handover register

Record the disposition for each package against its named evidence and receiver. A release counts when it has an evidence reference, reviewer and date, and every incoming package has a complete release. The authorised project reviewer decides acceptance against the applicable drawings, specifications and survey limits.

Package / required handoverDispositionEvidence referenceReviewerDateRelease check

Programme inputs and handover records are saved in this browser for each route and workfront. The JSON export includes the lot inputs, calculated shifts, release requirements and evidence references.

Marine package directory

Dredging

Backhoe dredger and hopper barge at the dredge face. Illustrative plant spread.
  1. Bucket and cut faceMeasure the accepted in-situ cut against the agreed dredge surfaces.
  2. Backhoe pontoonAllow for repositioning and the workable tide window.
  3. Hopper bargePayload and round-trip time can limit the excavator’s productive rate.

Piling

Floating crane, driving hammer and guide frame at a tubular pile group.
  1. Crawler craneInclude positioning and pile handling in the spread cycle.
  2. Driving hammerLink installation and founding records to the individual pile.
  3. Guide frameVerify position and inclination before releasing the pile group.

Scour protection

Graded rock armour and its filter around the steel pile interfaces.
  1. Rock armourReconcile placed tonnes with the surveyed layer profile.
  2. Pile interfaceInspect transitions and gaps around the pile group.
  3. Placement spreadRock supply and reach affect the production window.

Wharf construction

Piled wharf bay, floating crane and exposed seabed armour. Illustrative workfront.
  1. Precast deckDeck units span between headstocks. Keep the open bay available for scour placement and inspection.
  2. Steel pilesThe accepted pile-head group releases the cap and scour crews.
  3. Crane pontoonVessel access and positioning determine which bay the lifting spread can serve.

Quay wall

Quay wall beside the berth pocket, with landward restraint and retained fill.
  1. Quay wall and walerCheck wall alignment and restraint connections before the next excavation stage.
  2. Landward anchorageRecord the accepted anchor system and the stage it releases.
  3. Berth pocketSurvey the pocket against the approved deepening stage and surface.

Handover

Wharf deck, pile supports and berth fittings at the inspection stage.
  1. Deck and headstockTie survey and concrete release records to the completed bay.
  2. Berth-face fenderVerify installed position and retain the fitting inspection records.
  3. Pile supportsReconcile the as-built support locations with the berth handover plan.

Library references

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.