Construction methods / Trenchless
Pipe jacking and microtunnelling
Pipe jacking and microtunnelling are pit-launched trenchless methods used to install subterranean pipelines, casings, and service conduits along a controlled grade and alignment without continuous surface trenching. Outturn cost and duration are driven primarily by launch and reception shaft construction, temporary ground support, geotechnical baseline conditions, spoil separation capacity, and non-excavation pipe-change cycle times rather than simple linear metre advance.
- CutterheadFace conditions and interventions affect advance.
- ShieldCheck alignment and the supported excavation envelope.
- Jacking frameInclude pipe change and thrust cycles separately.
Overview
Pipe jacking and microtunnelling form a unified installation system for buried pipelines across rail corridors, classified state roads, waterways, and congested urban utilities. Pipe jacking is the structural installation technique in which prefabricated pipe sections are lowered into a launch shaft and pushed sequentially through the ground towards a reception shaft by hydraulic cylinders reacting against an engineered thrust wall. Microtunnelling uses a remotely operated, laser- or gyro-guided Microtunnelling Boring Machine (MTBM) at the lead end of the pipe string to maintain continuous mechanical or fluid support at the excavation face, balancing earth and groundwater pressures without requiring routine personnel entry into the bore. Steering, face pressure regulation, cutterhead torque, and spoil extraction are controlled from a surface operator cabin, while pressurised bentonite or polymer lubricant is injected into the overcut annulus to support the bore wall and reduce skin friction during the drive.
Where the method applies
- Grade-critical gravity pipelines such as trunk foul sewers and stormwater drainage lines requiring tight vertical grade and horizontal alignment tolerances (governed by WSA 02 and ATS 4541) where directional drilling tolerances are insufficient.
- Major linear infrastructure crossings beneath operating railways (subject to AS 4799), motorways, arterial highways (under MRTS141 or the relevant road authority specification), airport runways, rivers, and environmentally sensitive corridors where open-cut excavation is prohibited.
- Deep alignments and high groundwater tables where open-trench shoring, benching, and dewatering become uneconomical or create unacceptable drawdown and ground settlement risks to adjacent structures.
- Broad geotechnical profiles beneath the water table, where slurry-shield or Earth Pressure Balance (EPB) MTBMs can be configured with soft-ground scrapers, mixed-face cutterheads, or hard-rock disc cutters to excavate cohesionless sands, silts, stiff clays, gravel, and competent rock.
- Direct installation of permanent product pipes—including steel-reinforced concrete jacking pipes (AS/NZS 4058), glass-reinforced plastic (AS 3571.1), vitrified clay (AS 1741), or steel pipes (AS 1579)—along the final design grade.
- Enveloper casing drives where an outer casing is jacked first to support the ground, through which one or more carrier pipes or electrical and telecommunications conduits are subsequently sliplined and grouted.
The method does not suit drives with insufficient overburden cover (which risk surface heave, slurry frac-out, or chimney collapse), unmapped buried obstructions exceeding the MTBM crusher aperture, or ungrouted karstic voids. For very short, shallow unconstrained crossings, open-cut trenching or simple auger boring is usually more economical; for long, tightly curved 3D alignments installing small-diameter flexible HDPE or steel pressure pipes without deep shafts, Horizontal Directional Drilling (HDD, governed by MRTS140 and ATS 4540) is generally preferred.
Sequence of work
- Pre-construction investigation, dilapidation surveys, and temporary works design. Geotechnical site investigations (AS 1726), subsurface utility engineering (SUE) potholing along the drive corridor and shaft footprints, pre-construction condition surveys, and certified temporary works designs for shafts and thrust walls are completed by the engineering and survey team; statutory approvals and design Hold Points must be released before breaking ground.
- Site establishment, traffic management, and settlement monitoring baseline. The site crew establishes compound fencing, acoustic barriers, crane hardstands, and pipe laydown areas, while the surveyor installs surface and subsurface settlement markers across the road or rail easement and records baseline readings prior to shaft excavation.
- Launch and reception shaft sinking and base slab construction. Excavators, piling rigs, and shaft crews sink and support the launch and reception shafts using sheet piling, secant/contiguous bored piles, caissons, soldier piles with shotcrete, or shoring boxes, then cast the reinforced concrete base slab, structural thrust wall, and portal eye seals; structural cure, dewatering control, and shoring inspections are verified before plant installation.
- Surface plant, slurry separation system, and jacking frame setup. Using the shaft service crane, riggers and fitters position the control container, hydraulic power pack, bentonite lubrication batching unit, and multi-stage slurry separation plant (shakers, hydrocyclones, and centrifuge or filter press), and bolt the hydraulic jacking frame onto the launch shaft floor slab aligned to the design drive azimuth and grade.
- Survey control transfer and guidance system calibration. The engineering surveyor transfers primary surface control into the launch shaft via optical plumbing, total station, or gyroscopic survey (MRTS56 and ATS 4541), mounts the guidance laser or automated total station on a vibration-isolated bracket, and checks zero alignment against the MTBM target board prior to launch.
- MTBM cradle placement and portal break-out. The crane and pit crew lower the MTBM shield and trailing cans onto the jacking frame guide rails, connect hydraulic, electrical, slurry, and lubrication umbilicals, and advance the cutterhead through the launch eye seal and treated portal block while verifying that groundwater inflow and face pressure remain controlled.
- Cyclical pipe jacking, excavation, spoil extraction, and bentonite lubrication. The MTBM pilot and separation plant operator advance the shield and pipe string by extending the main jacking cylinders while regulating cutterhead torque, face support pressure, closed-loop spoil extraction, and automatic bentonite injection; at full ram stroke, the pit crew isolates bypass valves, retracts the jacking ring, cranes in the next pipe with its joint packer and collar seal (or an Intermediate Jacking Station on long drives), and checks pipe end-squareness, joint seating, and excavated spoil volume against theoretical bore displacement before resuming.
- MTBM reception and recovery. The pilot advances the MTBM through the reception shaft eye seal into a prepared reception cradle or pressurised receiving chamber, where the pit crew disconnects internal umbilical lines and the crane lifts the MTBM and trailing cans out of the reception shaft after verifying portal groundwater stability.
- Annular grouting, interjack closure, and carrier pipe installation. The shaft crew closes any Intermediate Jacking Stations, strips internal umbilicals, and injects cementitious grout through the pipe grout ports to displace the bentonite lubricant in the outer overcut annulus (and sliplines and grouts the internal carrier pipe if cased), checking grout mix properties, injection pressures, and total grout take.
- Testing, CCTV inspection, shaft decommissioning, and reinstatement. Testing crews and surveyors complete post-installation line-and-level as-built surveys, hydrostatic or air pressure testing, and WSA 05 CCTV conduit inspection; once accepted, civil crews construct permanent maintenance chambers inside the shafts, remove temporary shoring as designed, backfill and compact the shafts, and close out post-construction dilapidation surveys.
Typical crew and plant
| Role or machine | What it does | Notes |
|---|---|---|
| Project Engineer / Tunnel Supervisor (1) | Manages shift execution, ITP compliance, Hold Point releases, face pressure parameters, and settlement monitoring review. | Required across single-shift or continuous 24-hour operations. |
| MTBM Operator / Pilot (1) | Operates the microtunnelling machine from the surface control cabin, regulating laser target alignment, pitch, roll, jacking thrust, cutterhead torque, and slurry flow balance. | Controls excavation remotely without routine personnel entry into small-to-medium bores. |
| Separation Plant / Bentonite Operator (1) | Operates the slurry separation plant, tests fluid density and viscosity (Marsh funnel and mud balance), checks spoil moisture, and maintains automatic bentonite lubrication tanks. | Critical for preventing separation bottlenecks in high-fines soils. |
| Crane Operator (1) and Dogman / Rigger (1) | Operate the shaft service crane, control surface slinging of pipes and interjack stations, prepare pipe joints on surface, and manage safe shaft lifting operations. | Subject to wind shut-down limits and exclusion zone controls over open shafts. |
| Shaft / Pit Crew (2) | Work in the launch shaft during pipe changes to uncouple and recouple slurry and hydraulic lines, clean joint collars, fit resilient packers, and operate frame retract controls. | Operate under strict confined-space entry, gas monitoring, and ventilation protocols. |
| Loader / Excavator Operator (1) | Manages separated spoil stockpiles at the surface compound, loads haulage trucks for off-site disposal, and unloads pipe delivery semi-trailers. | Supports continuous muck away from the separation plant underflow and centrifuge. |
| Engineering Surveyor (Part-time / Call-off) | Performs shaft control transfer, independent laser alignment checks, surface settlement array monitoring, and post-drive as-built surveys. | Works to MRTS56 and ATS 4541 survey tolerance requirements. |
| Microtunnelling Boring Machine (MTBM) or Jacking Shield | Excavates the bore face and supports earth and groundwater pressures using a slurry shield, Earth Pressure Balance (EPB) shield, or open-face/auger shield. | Matched to pipe outer diameter and ground profile; fitted with scrapers, disc cutters, or cone crusher. |
| Hydraulic Jacking Frame, Power Pack, and Interjacks (IJS) | Main shaft frame and hydraulic cylinders push the pipe string from the launch shaft; steel Intermediate Jacking Stations distribute axial loads along long drives. | Sized to remain within allowable pipe proof loads and thrust wall reaction capacity. |
| Slurry Separation Plant and Automated Bentonite Station | Scalping shakers, hydrocyclones, and centrifuges or filter presses strip excavated solids from the slurry circuit; bentonite station mixes and injects skin lubricant. | Computer-controlled bentonite manifold injects lubricant through shield and pipe skin ports. |
| Shaft Service Crane, Ventilation, and Survey Guidance System | Crane lifts the MTBM shield, shaft segments, and jacking pipes; forced ventilation fans, gas detectors, retrieval winches, and tunnel lasers support safe, accurate drives. | Crane is sized to lift the heaviest single component (typically the MTBM shield) at the required radius. |
Productivity drivers
- Ground conditions, rock strength (UCS), and abrasivity. Soft cohesive clays can clog the cutterhead ("balling") in slurry shields and slow separation throughput, while high-strength rock or abrasive quartzose sandstones reduce instantaneous penetration rates and require time-consuming cutterhead tool changes.
- Slurry separation plant capacity versus excavation volume. In larger diameters or high-fines soils (silts and clays), shift advance is frequently governed not by cutterhead cutting speed, but by the capacity of the hydrocyclones and centrifuge to strip suspended fines and keep slurry density within operating limits.
- Individual pipe module length and jointing configuration. Supplying precast concrete jacking pipes (AS/NZS 4058) or GRP pipes in longer module lengths reduces the number of crane cycles and hydraulic/slurry umbilical disconnections required per linear metre of completed bore.
- Compound access, crane hook time, and shaft depth. Deep launch shafts or cramped urban compounds slow down crane lowering and umbilical coupling in the pit, directly increasing the fixed non-excavation cycle time for every pipe pushed.
- Drive length, alignment curvature, and interjack activation. Longer or curved drives increase umbilical hydraulic losses, slurry pumping head, and skin friction; sequentially cycling Intermediate Jacking Stations (IJS) slows overall linear advance compared to pushing solely from the main jacking frame.
- Working hours and shift continuity. Running continuous 24-hour shifts eliminates daily start-up checks and prevents thixotropic gel set-up and ground grip around the stationary pipe string, which otherwise spikes restart jacking forces in swelling clays or cohesive soils.
- Groundwater head and portal launch/reception complexity. High hydrostatic pressures require jet-grouted portal blocks and pressurised launch or receiving chambers at the shaft eyes, extending launch setup and recovery durations.
Published references
Only figures that come from a source are listed. Everything else is a driver, not a number.
| Reference | Figure and basis | Status |
|---|---|---|
| Austroads Technical Specification ATS 4541 (austroads.gov.au) | No published numeric productivity rates or shift advance figures were found in this specification; cycle times must be built up from project-specific geotechnical parameters and plant configurations using the drivers above. | No figure found (negative finding, not a document) |
| Queensland TMR MRTS141 and MRS141 (tmr.qld.gov.au) | No published numeric productivity figures were found in the technical or measurement specification listings; retain the qualitative productivity drivers above. | No figure found (negative finding, not a document) |
| Concrete Pipe Association of Australasia (CPAA) Jacking Design Guidelines (cpaa.asn.au) | No verified public-domain shift productivity figures were found in the engineering design guidelines; retain the qualitative productivity drivers above. | Not verified |
Quality and hold points
- Hold Point – Construction procedures, design, and work plan submission (MRTS141 Clauses 4.2 and 5). Prior to commencing site operations, the contractor must obtain Administrator acceptance for MTBM selection, face support calculations, predicted jacking forces, pipe strength verification, spoil removal, bentonite lubrication, annular grouting, and obstruction contingency plans to verify the drive is engineered for the ground conditions.
- Hold Point – Statutory, utility, and environmental approvals (MRTS141 Clause 5.1). Written evidence of all third-party road, rail, water, gas, and electrical asset owner concurrences and environmental permits must be verified before breaking ground in protected corridors.
- Hold Point – Detailed engineering design of shafts and thrust wall (MRTS141 Clause 5.2). Certified structural designs for the final microtunnelling alignment, temporary shaft shoring, and thrust/receival pit reaction structures must be accepted to prevent shaft instability or thrust wall failure under jacking loads.
- Hold Point – Pre-construction property and infrastructure condition surveys (MRTS141 Clause 5) and risk assessment (Clause 5.5). Baseline dilapidation surveys of adjacent roads, rail tracks, structures, and buried utilities, together with a comprehensive construction risk assessment covering settlement/heave triggers and confined spaces, must be submitted before excavation begins.
- Witness / Hold Point – Material conformance and pipe inspection (ATS 4541 / AS/NZS 4058). Factory compliance certificates for jacking pipes, joint collars, elastomeric seals, and resilient packers are checked alongside visual site inspections for pipe end-squareness and spalling before lowering pipes into the shaft, preventing eccentric point loading during jacking.
- Witness / Hold Point – Launch shaft setup and survey alignment check (ATS 4541 / MRTS56). Independent survey verification of the jacking frame line and level, vibration-isolated laser setup, and launch eye seal installation is required prior to MTBM break-out to prevent off-grade launch or portal groundwater inflow.
- Continuous drive monitoring and quality records (ATS 4541 / MRTS141). Real-time logging of jacking forces, face slurry or earth pressures, pitch, roll, laser deviation, bentonite injection volumes, and excavated spoil volume versus theoretical bore volume is maintained throughout the drive to detect over-excavation or cavity formation immediately.
- Hold / Witness Point – Annular grouting and post-drive verification (MRTS141 / ATS 4541 / WSA 05). Grout mix properties, injection pressures, and total grout take are recorded, followed by as-built line-and-level survey, hydrostatic or air pressure testing, WSA 05 CCTV conduit inspection, and post-construction settlement close-out.
Risks and controls
- Pipe string freeze or exceeding jacking capacity. High skin friction in swelling clays or collapsing sands, loss of the bentonite lubrication film, or weekend/overnight stoppages can cause the ground to grip the pipe string; control by maintaining continuous automated bentonite/polymer injection, installing Intermediate Jacking Stations (IJS), working continuous 24/7 shifts in high-risk soils, and designing conservative pipe and thrust wall axial load factors of safety.
- Joint spalling or structural pipe cracking. Point loading at pipe joints from excessive steering corrections, missing or damaged timber/MDF packers, or poor pipe end-squareness can crack pipes mid-drive; control by enforcing AS/NZS 4058 end-squareness tolerances, fitting full-ring resilient packers matched to joint geometry, limiting steering jack angles per stroke, and continuously monitoring jacking frame load cells.
- Surface settlement or cavity collapse (sinkhole). Insufficient MTBM face pressure, over-excavation in running sands below the water table, groundwater inflow at shaft portals, or an ungrouted overcut annulus can cause surface subsidence; control by balancing closed-face slurry or EPB pressure against hydrostatic and active earth pressures, reconciling excavated spoil volume against theoretical bore displacement on every pipe, fitting pressurised rubber portal eye seals with jet-grouted portal blocks, and grouting the outer annulus immediately upon completion.
- Surface heave or slurry frac-out. Excessive slurry face pressure or bentonite lubrication injection pressure exceeding overburden stress under shallow pavements or waterways can heave the surface or release drilling fluid; control by calculating maximum allowable face and grouting pressures for the cover depth, continuously monitoring surface settlement/heave arrays under MRTS141, and keeping spill containment kits on site.
- Encountering unforeseen subsurface obstructions. Corestones, boulders, timber piles, abandoned sheet piles, or unmapped services exceeding the crusher aperture can stall the cutterhead; control by completing targeted boreholes (AS 1726) and SUE potholing along the alignment, selecting a cutterhead and cone crusher matched to expected cobble sizes, and preparing an emergency compressed-air or rescue shaft intervention plan under MRTS141.
- Line and grade departure (off-line or off-grade drive). Laser refraction from thermal gradients inside the pipe string, thrust wall deflection shifting the laser mount, or mixed-face transitions (hard rock bottom with soft top) can drive the shield off alignment; control by isolating the laser mount from the thrust wall and jacking frame, running air-mixing fans inside the pipe string, and performing regular independent manual optical/total-station check surveys.
- Confined space, ground gas, and shaft lifting hazards. Toxic or flammable ground gases, oxygen depletion inside shafts and pipes, and heavy crane lifts into restricted openings pose severe safety risks; control by classifying shafts and pipelines as confined spaces, operating continuous forced ventilation and multi-gas detectors, and enforcing strict exclusion zones beneath suspended loads during pipe lowering.
Programming and weather
- Pre-construction lead-time and off-site critical path. Before site works begin, the programme must allow for geotechnical reporting (AS 1726), SUE potholing, third-party rail and road access approvals (AS 4799, MRTS141), independent certification of temporary shaft and thrust wall designs, custom jacking pipe manufacture and curing (AS/NZS 4058), and MTBM procurement and cutterhead configuration.
- Launch shaft critical path (Finish-to-Start). The launch shaft must be fully excavated, shored, base-slabbed, fitted with its structural thrust wall and portal eye block, and cured before jacking frame and MTBM setup can commence.
- Parallel reception shaft construction (Finish-to-Finish buffer). The reception shaft can be sunk and shored in parallel with the launch shaft setup and the early stages of the MTBM drive, provided its base slab and portal ground treatment are completed with a safe programme buffer before the MTBM approaches the reception zone.
- Sequential drive and double-launch shaft dependencies. The tunnelling phase follows a strict sequence: frame and separation plant setup, launch break-out, cyclical pipe jacking (including IJS installation), reception breakthrough and MTBM recovery, and annular grouting; where two opposing drives launch from a single central shaft, the second drive cannot start until the jacking frame is rotated and re-anchored (or the MTBM is recovered and re-launched) after the first drive finishes.
- Post-drive civil and commissioning successors. Following MTBM recovery and annular grouting, programme logic must sequence internal carrier pipe sliplining (if cased), permanent maintenance hole or chamber construction inside the shafts, hydrostatic/air testing, WSA 05 CCTV inspection, temporary shoring removal, shaft backfill, and corridor handover.
- Subterranean drive insulation vs open-shaft rainfall vulnerability. While underground excavation and pipe jacking are largely insulated from light-to-moderate rain once the MTBM is buried, open launch and reception shafts act as sumps during heavy downpours if surface bunding or perimeter drainage fails—flooding electrical/hydraulic power packs, submerging the guidance laser, and halting the drive.
- Wind limits on shaft craneage and wet-weather spoil haulage. High winds exceeding crane operating limits halt pipe lowering, muck skip handling, and MTBM lifts on exposed sites, while wet weather can saturate open separation-plant spoil stockpiles and cause material to fail truck transportable moisture limits (TML) or landfill acceptance criteria.
Estimating considerations
- Separate fixed establishment and shaft costs from variable drive costs. Under MRS141 and standard civil measurement rules, price site establishment, mobilisation and demobilisation of the MTBM spread, jacking frame, separation plant, control containers, and service crane as a distinct lump sum (Item) rather than amortising them into a generic linear metre rate; on short road or rail crossings, fixed setup and shaft works represent the majority of total cost.
- Launch and reception shaft temporary works take-off. Measured per shaft (Item) or by excavation and shoring quantities (m³ / m²), estimators must allow for temporary shoring (sheet piles, secant piles, caissons, or shoring boxes), dewatering, reinforced concrete base slabs, thrust walls, jet-grouted portal blocks, launch/exit eye seals, and temporary works design certification.
- Dilapidation surveys and continuous settlement monitoring. Allow as an Item or per No. / Shift for pre- and post-construction condition surveys, installation of surface and subsurface settlement arrays across road or rail corridors, baseline survey readings, and daily shift monitoring and reporting required under MRTS141 and TS 02088.
- Supply and delivery of jacking pipes and joint ancillaries. Taken off in linear metres (m) or number of pipes (No.) by nominal diameter, material (AS/NZS 4058 SRCP, AS 3571.1 GRP, AS 1741 clay, or AS 1579 steel), axial proof load class, joint collar type, resilient packers, factory-cast bentonite/grout ports, and rebated pipe ends for Intermediate Jacking Stations.
- Variable microtunnelling and pipe jacking drive build-up. Measured per linear metre (m) along the bore axis between shaft faces (MRS141), built up from net cutting time plus per-pipe connection cycle time, shift crew labour, craneage, guidance survey, bentonite/polymer lubricant consumption, and power/fuel for the separation plant and hydraulic packs.
- Slurry spoil tonnage escalation and waste disposal. Measured in tonnes (t) or bulked cubic metres (m³), estimators must account for bulking plus residual water and bentonite retained in centrifuge cake or hydrocyclone underflow, which increases off-site haulage and landfill disposal tonnage well above neat in-situ bank volume, alongside any Acid Sulfate Soil (ASS/PASS) or contamination testing.
- Annular grouting and carrier pipe sliplining. Measured in linear metres (m) or cubic metres (m³), allow for cementitious grouting to displace bentonite in the outer overcut annulus (accounting for overbreak and loss into permeable strata) and, for enveloper casings, low-friction spacers and inner annulus grouting around the carrier pipe (ATS 4541 / MRS141).
- Cutterhead consumables, hyperbaric/atmospheric interventions, and ground risk. Allow for disc cutter or scraper wear in abrasive sandstone or basalt, elevated bentonite losses in open gravels, standby shift allowances for cutterhead inspections, and contract risk allocation under the Geotechnical Baseline Report (GBR) for cobbles or buried obstructions.
- Post-drive testing, CCTV inspection, and shaft reinstatement. Measured as an Item or per linear metre (m), include post-drive as-constructed survey (MRTS56), hydrostatic or air pressure testing, WSA 05 CCTV inspection coding, permanent chamber construction, shoring extraction, and shaft backfill and compaction.
Specifications and standards
Checked 11 November 2026. Each document was looked up in catalogue and regulator listings; many agency PDFs could not be opened in full. Rows marked Confirmed were found to exist as described. Rows marked Not verified were not found or not checked. Clause-level statements, tolerances, temperatures, distances and similar figures in the text are typical values and are unverified unless a row cites the rule. Confirm the current edition of any document before relying on it.
| Document | What it covers for this method | Status |
|---|---|---|
| Austroads ATS 4541 – Microtunnelling and Auger Boring (and companion ATS 4540 – Horizontal Directional Drilling) | Harmonised national technical specification covering design, material conformity, overcut limits, bore position monitoring, annular grouting, and settlement tolerances for pit-launched trenchless installations (distinguishing pit-launched microtunnelling from HDD under ATS 4540). | Confirmed |
| Queensland TMR MRTS141 & MRS141 – Microtunnelling and Pipe Jacking (with MRTS01, MRTS50, MRTS56, MRTS140, MRTS142) | Technical and measurement specifications governing contractor submissions, Hold Points, risk assessments, shaft works, tunnelling, survey compliance (MRTS56), and payment rules beneath state-controlled transport corridors in Queensland. | Confirmed |
| Transport for NSW TS 02088 (formerly GTD 2018/002 / RMS 18.906) & TS 02715 (formerly GTD 2020/001) | Mandatory technical directions for laser-guided microtunnelling and pipe jacking within NSW state road reserves (TS 02088) and open shaft excavations/shoring influence zones adjacent to TfNSW infrastructure (TS 02715). | Not found |
| AS 4799 (AS 4799-2000) – Installation of underground utility services and pipelines within railway boundaries | Governs boring and pipe jacking beneath operating railway tracks, minimum cover clearances, ground subsidence prevention, settlement monitoring, and carrier/casing requirements. | Confirmed |
| AS/NZS 4058 (AS/NZS 4058:2007) – Precast concrete pipes (pressure and non-pressure) | Primary manufacturing, dimensional tolerance, end-squareness, joint geometry, and axial proof load testing standard for steel-reinforced concrete jacking pipes (SRCJP). | Confirmed |
| AS 1579, AS 1741, AS 3571.1, and AS/NZS 2566.1 & AS/NZS 2566.2 | Material and structural design standards referenced in ATS 4541 for arc-welded steel pipes (AS 1579), vitrified clay pipes (AS 1741), glass-reinforced plastics/GRP (AS 3571.1), and buried flexible pipeline design and installation (AS/NZS 2566.1 and 2566.2). | Confirmed |
| AS 1726 – Geotechnical site investigations | Referenced in ATS 4541 for mandatory subsurface investigation and borehole logging along trenchless drive alignments and shaft locations. | Confirmed |
| WSAA WSA 02 – Gravity Sewerage Code of Australia & WSA 05 – Conduit Inspection Reporting Code of Australia | Industry codes governing pipe jacking design and grade tolerances for gravity sewers (WSA 02) and post-installation CCTV conduit inspection reporting (WSA 05). | Confirmed |
| ASTT CPJP8029-SPE-C-003 & CPJP8029-GUI-C-001 | Australasian Society for Trenchless Technology industry specification for microtunnelling and pipe jacking (CPJP8029-SPE-C-003) and guidelines for trenchless methods (CPJP8029-GUI-C-001). | Not found |
Only documents confirmed to exist carry the status Confirmed. Check the current edition before relying on any document.
Sources and review
| Source | Used for | Status |
|---|---|---|
| Austroads – ATS 4541 Microtunnelling and Auger Boring (austroads.gov.au) | Method scope, pipe material standards (AS/NZS 4058, AS 1579, AS 1741, AS 3571.1), site investigation (AS 1726), tolerances, annular grouting, and HDD distinction (ATS 4540). | Confirmed |
| Queensland Department of Transport and Main Roads (TMR) – MRTS141 & MRS141 Microtunnelling and Pipe Jacking (tmr.qld.gov.au) | Hold Points (Clauses 4.2, 5, 5.1, 5.2, 5.5), quality and survey cross-references (MRTS01, MRTS50, MRTS56), companion trenchless specifications (MRTS140, MRTS142), and measurement units. | Confirmed |
| Transport for NSW (TfNSW) – TS 02088 (GTD 2018/002 / RMS 18.906) & TS 02715 (nsw.gov.au) | Applicability, settlement monitoring, and shaft excavation requirements within and adjacent to NSW state road easements. | Not found |
| Australasian Society for Trenchless Technology (ASTT) – CPJP8029-SPE-C-003 & CPJP8029-GUI-C-001 (astt.com.au) | Industry specification and guideline titles and scope for pipe jacking and microtunnelling across Australasia. | Not found |
| Concrete Pipe Association of Australasia (CPAA) – Jacking Design Guidelines (cpaa.asn.au) | Structural design principles, joint end-squareness controls, and AS/NZS 4058 conformance for precast concrete jacking pipes. | Confirmed |
| Holcim Australia / Humes – Jacking Pipes Technical Documentation (humes.com.au) | Joint collar configurations, resilient packers, lubrication and grout ports, Intermediate Jacking Stations, and AS/NZS 4058 compliance. | Confirmed |
| Water Services Association of Australia (WSAA) – WSA 02 & WSA 05 (wsaa.asn.au) | Gravity sewer pipe jacking applicability and post-construction CCTV inspection reporting requirements. | Confirmed |
| Main Roads Western Australia – Utility Providers Code of Practice for Western Australia (mainroads.wa.gov.au) | Trenchless crossing requirements beneath state road surfaces and protected verges. | Not verified |
Items marked Not verified have not been checked against a primary source. Research notes.