Construction methods / Earthworks
Rock excavation
Rock excavation loosens, fragments, loads and hauls intact rock masses, weathered strata and boulders to form design cuttings, structural foundations and utility trenches, while supplying durable rock fill for engineered embankments. Cost and programme duration are driven by intact rock strength, defect spacing, the extraction method required (mechanical ripping, hydraulic breaking or drill and blast), fragmentation oversize ratios, ground engaging tool wear and vibration or airblast limits.
- Face shovelBucket cycles and truck spotting determine loading output.
- Rigid haul truckTrack payload and cycle time on the same operating basis.
- Haul roadDistance, grade and condition affect the achieved fleet rate.
Overview
Rock excavation in civil earthworks covers loosening, fragmenting, loading and hauling intact rock masses, weathered rock strata and large boulders to achieve design cutting profiles, structural foundations or utility trenches. Unlike bulk soil excavation where excavators, scrapers or loaders dig directly from the bank, rock excavation requires dedicated energy input to fracture the rock mass along bedding planes, joints and foliations before extraction can proceed. Across Australian road, rail and infrastructure projects, rock is extracted using three primary methods: mechanical ripping with heavy track-type tractors (bulldozers) fitted with single-shank or multi-shank rippers in weak-to-moderately strong, jointed or weathered rock; hydraulic breaking with excavator-mounted percussion breakers, rock saws or rotary drum cutters where environmental, proximity or regulatory constraints prohibit blasting; and drill and blast using patterned boreholes and commercial explosives in massive, high-strength rock, paired with controlled perimeter pre-splitting. Suitable durable won rock is frequently placed into engineered rock fill embankments, bridging layers or erosion protection zones.
Where the method applies
- Open bulk cuttings in low-to-medium strength sedimentary rocks (shales, mudstones, siltstones, sandstones), weathered igneous or metamorphic formations, and cemented pedocretes (calcrete, ferricrete, silcrete) where defect spacing allows ripper tooth entry.
- Formations where compressional seismic wave velocity (P-wave) sits within the rippable or marginal envelope for heavy bulldozers (up to roughly 1,800–2,100 m/s for D9 class, 2,300–2,450 m/s for D10 class, and 2,700–3,000+ m/s for D11 class, subject to jointing).
- Confined excavations such as bridge footings, retaining wall foundations, and drainage or service trenches where hydraulic rock breakers, rock saws or rotary drum cutters can operate accurately.
- Bulk cuttings located adjacent to sensitive receivers, live utilities, heritage structures or buildings where blasting is disallowed by the contract or environmental limits.
- Secondary breaking of oversize boulders at the excavation face or tip head, and trimming localised rock high spots along cutting subgrades.
- Large-volume rural or peri-urban road and rail cuttings in fresh, massive, high-to-extremely-high strength rock (unweathered basalt, granite, dolerite, quartzite or massive limestone classified under AS 1726 Table 19 from 20 MPa to over 200 MPa UCS) suited to drill and blast.
- Projects requiring engineered rock fill embankments, bridging layers over soft ground, or gabion and erosion protection zones sourced from durable cutting rock.
Mechanical ripping does not suit massive, unjointed crystalline rock where the ripper tooth cannot penetrate, or narrow trenches where a heavy dozer cannot manoeuvre, requiring hydraulic breaking or drill and blast instead. Conversely, drill and blast does not suit contracts where blasting is prohibited (such as TfNSW R44 Annexure R44/A7 exclusions), shallow rock bands under 1.0 m deep with insufficient stemming depth to contain flyrock, or sites near critical utilities and residences where AS 2187.2 ground vibration and airblast limits cannot be met, where hydraulic breaking or non-explosive rock saws are used.
Sequence of work
- Geotechnical review, seismic assessment and dilapidation surveys. Geotechnical engineers and estimators review borehole core logs (AS 1726), Point Load Strength Index, Uniaxial Compressive Strength (UCS) results and seismic refraction profiles to classify rippable and non-rippable zones, while dilapidation surveyors inspect adjacent properties and utilities within the zone of influence before site works begin.
- Management plan approvals and Hold Point release. The project engineering team submits the Earthworks Construction Procedure (TMR MRTS04) or Earthworks Plan (TfNSW R44), together with the Vibration and Airblast Management Sub-Plan and Blast Management Plan (TMR MRTS55 / TfNSW G36), verifying formal Hold Point release before disturbing the rock mass.
- Overburden stripping and rock surface exposure. Scrapers, excavators and dump trucks strip topsoil and overlying residual or completely weathered soils down to the top-of-rock horizon, after which surveyors capture the exposed rock surface by terrestrial pickup or UAV photogrammetry to establish the baseline digital terrain model (DTM) and confirm classification where rock is measured separately.
- Surface drainage and bench access establishment. Graders and excavators construct catch drains and diversion bunds above the cutting crest to stop surface water inflow, then form stable access ramps and level working benches checked for grade and bearing stability for drill rigs, heavy dozers or excavators.
- Perimeter definition and pre-splitting. Surveyors set out design batter crests and bench offsets, and where blasting is used in deep cuts, surface crawler drill rigs and the shotfirer crew drill and fire closely spaced, lightly charged pre-split or trim holes along the design batter plane to form a continuous fracture plane prior to production firing.
- Primary rock loosening (ripping, breaking or production blasting). Depending on the zone, a heavy single-shank dozer (D9–D11 class) rips downhill along the alignment maintaining a loose rock cushion under the tracks; a 30 t to 50 t excavator with a hydraulic breaker shears blocks from a free face inward; or the drill and blast crew drills production holes, stems collars with angular aggregate, establishes exclusion zones and road closures (TfNSW G10), and detonates millisecond delay sequences while recording triaxial geophone and linear microphone data (AS 2187.2).
- Post-blast or post-break face scaling and geotechnical inspection. After fume clearance or mechanical loosening, an excavator fitted with a bucket, scaling bar or breaker scales loose and overhanging blocks from the cutting batter, and the exposed lift is presented to the Geotechnical Assessor (Hold Point under TfNSW R44) to map defects and confirm whether rock bolts, dowels, shotcrete or mesh must be installed before excavating the next bench lift.
- Load, haul and oversize management. A 45 t to 85 t hydraulic excavator or loader loads fragmented rock into articulated or rigid off-highway dump trucks, while oversize boulders are segregated at the face for secondary hydraulic breaking or crushing so all hauled rock meets the maximum particle size for its target fill zone.
- Rock fill placement and mechanical interlock compaction. Dump trucks tip rock on the advancing embankment head and a heavy dozer pushes it forward using the mechanical interlock method (TMR MRTS04 / VicRoads Section 205) so finer fragments fill voids between larger stones, followed by 18 t to 25 t heavy vibrating smooth-drum or padfoot rollers and placement of a transition or geotextile separation layer (ATS 2160) verified by proof rolling.
- Cutting floor undercut, drainage and subgrade trimming. Excavators and graders undercut the cutting floor below design subgrade level where specified (such as the 150 mm undercut in Main Roads WA Specification 302) to remove shattered rock pinnacles, install slotted subsoil edge drains at the rock-pavement interface, inspect the floor Hold Point, and backfill and compact the selected capping layer to final tolerances.
Typical crew and plant
| Role or machine | What it does | Notes |
|---|---|---|
| Heavy track-type tractor (Cat D9, D10 or D11 class, or Komatsu D275/D375/D475 equivalent) | Fractures weak-to-moderately strong or jointed rock using a single-shank deep or standard ripper, pushes rock to the loading face, and spreads rock fill on the embankment tip head. | Fitted with heavy-duty grouser shoes; tandem dozer pushing may be added in marginal seismic velocity rock. |
| Heavy hydraulic excavator (45 t to 85 t class) | Loads ripped or blasted rock into haul trucks, scales exposed cutting batters, and manages oversize boulders at the face. | Equipped with a heavy-duty rock bucket; smaller 30 t to 45 t units with hydraulic thumb or grapple support rock breaker load-out. |
| Hydraulic rock breaker excavator (30 t to 50 t class) | Fractures non-rippable rock in confined trenches, structural footings,vibration-sensitive corridors, and performs secondary breaking of oversize spalls. | Fitted with matched hydraulic percussion breaker, auto-greasing system, and FOPS/mesh cabin protection. |
| Articulated dump trucks (30 t to 45 t class) or rigid off-highway haul trucks | Haul fragmented rock from the cutting bench to engineered rock fill embankments, crushing stockpiles, or spoil sites. | Typically 3 to 5 trucks per primary loading excavator, or 2 to 3 truck-and-dog/ADT units for a hydraulic breaking crew. |
| Top-hammer or Down-The-Hole (DTH) surface crawler drill rigs (1 to 2 units) | Drill patterned production blast holes and closely spaced perimeter pre-split holes to design burden, spacing and sub-drill depth. | Fitted with onboard dust-extraction skirts and cyclones to control respirable crystalline silica (RCS) dust. |
| Mobile Manufacturing Unit (MMU) and stemming loader | MMU blends and pumps bulk emulsion explosives into blast holes; skid-steer or telehandler stems collars with crushed angular aggregate. | Supported by light vehicles licensed for explosive transport. |
| Motor grader (16H/140M class), heavy vibrating roller (18 t to 25 t) and water cart (15,000 L) | Grader maintains rock haul roads and trims cutting floors; smooth-drum or padfoot roller compacts rock fill layers; water cart suppresses dust and conditions moisture. | Support plant shared across the cutting and embankment placement operations. |
| Earthworks and specialist blast crew | Earthworks Supervisor/Leading Hand, Dozer, Excavator, Loader, Grader, Roller, Water Cart and Haul Truck Operators, Grade Checker/Surveyor, Spotter, plus Licensed Shotfirer, Drillers, Blast Crew/Nippers, Monitoring Technician and Traffic Control crew (TfNSW G10). | Monitoring technician operates NATA-calibrated triaxial geophones and linear airblast microphones compliant with AS 2187.2 Appendix J. |
Productivity drivers
- Intact rock strength versus defect spacing and orientation. Intact UCS (AS 1726) governs how hard individual blocks are to drill or crush, whereas joint spacing, persistence and dip govern whether ripper teeth or breaker points can pry blocks apart; thinly bedded high-strength rock often rips faster than massive medium-strength rock.
- Ripping direction and pass geometry. Ripping downhill uses gravity to assist machine weight and tractive effort, and ripping parallel to the strike of steeply dipping beds keeps the tooth in the weak plane instead of skipping or chattering across vertical beds.
- Ground engaging tools (GET) wear and maintenance. Abrasive siliceous rocks such as quartzite, sandstone and granite rapidly blunt ripper tips, shank protectors, breaker points and drill bits; a rounded ripper tip loses penetration angle and rides over the surface, cutting hourly production sharply.
- Fragmentation distribution and oversize ratio. Poor blast design or over-spaced ripping passes produce slabbing and oversize boulders (commonly 2% to 10% of bank volume), forcing the loading excavator to pause for sorting or secondary breaking and increasing truck cycle times.
- Bench staging and geotechnical hold point cycle time. Deep cuttings must be worked in sequential top-down lifts (typically 3 m to 6 m drops), where drilling, charging, blasting, scaling, geotechnical inspection and rock bolting or shotcreting dictate bench turnover speed.
- Environmental cut-offs and permitted working hours. Blasting is restricted to daytime windows (Queensland guidance allows blasting from 7:00 am to 6:00 pm Monday to Saturday and not on Sundays or public holidays; project and licence conditions are often tighter), while high-noise hydraulic hammering in urban corridors is frequently subject to respite periods (such as 3 hours on, 1 hour off).
- Bulking (swell) factor in haulage. Solid bank rock expands significantly when fractured into loose spalls, meaning haul trucks reach their payload weight or volumetric struck limit with fewer bank cubic metres (BCM) per trip than in soil earthworks.
Published references
Only figures that come from a source are listed. Everything else is a driver, not a number.
| Reference | Figure and basis | Status |
|---|---|---|
| Volumetric output tables (BCM/hr) | No primary OEM volumetric production chart tables or state road authority output rates (in BCM/hr) were opened in the primary sources during research; volumetric output must be built up from the site-specific drivers above. | None found |
| Caterpillar Performance Handbook / Handbook of Ripping (cat.com / tmr.qld.gov.au) | Seismic P-wave velocity rippability thresholds: Cat D9 class marginal/non-rippable at ~6,000–7,000 fps (~1,800–2,100 m/s); Cat D10 class at ~7,500–8,000 fps (~2,300–2,450 m/s); Cat D11 class up to ~9,000–10,000+ fps (~2,700–3,000+ m/s). Basis: seismic refraction P-wave velocity paired with open fractures or bedding for tooth penetration. | Not verified |
| AS 1726:2017 Geotechnical site investigations, Table 19 (standards.org.au) | Rock material strength tiers by UCS and Point Load Index (Is(50)): Very Low 0.6–2 MPa UCS (Is(50) 0.03–0.1 MPa); Low 2–6 MPa (0.1–0.3 MPa); Medium 6–20 MPa (0.3–1 MPa); High 20–60 MPa (1–3 MPa); Very High 60–200 MPa (3–10 MPa); Extremely High >200 MPa (>10 MPa). Basis: intact core testing to AS 4133.4.2.1 (50 MPa and above) and AS 4133.4.2.2 (weaker rock) and AS 4133.4.1. | Confirmed (covers 50 MPa and above; weaker rock is AS 4133.4.2.2) |
| AS 2187.2:2006 Explosives — Storage and use — Part 2: Use of explosives, Appendix J & ANZEC Guidelines (detsi.qld.gov.au) | Human comfort ground vibration (residences): ≤5 mm/s PPV for 9 of 10 consecutive blasts, max 10 mm/s at any time. Structural damage limits depend on structure type and frequency (check the applicable guideline) for residential, 50 mm/s for heavy industrial, up to 100 mm/s for unoccupied reinforced concrete/steel. Airblast overpressure: ≤115 dBL peak for 9 of 10 consecutive blasts, max 120 dBL at any time. Basis: triaxial geophone and linear microphone monitoring (2–250 Hz, ≥500 Hz sampling). | Confirmed |
Quality and hold points
- Hold Point — Earthworks Plan and Vibration/Blast Management Sub-Plans. Before starting heavy rock breaking, ripping near structures or drilling and blasting, the contractor must submit the Earthworks Construction Procedure (TMR MRTS04) or Earthworks Plan (TfNSW R44), including the Vibration and Airblast Management Sub-Plan (TfNSW R44 Clause 4.6.1 / G36) and pre-construction building condition survey reports.
- Hold Point — Classification and survey of rock horizon. Where the contract separates General Earthworks from Rock Excavation or Non-Rippable Material (such as TMR MRS04 or Main Roads WA Specification 302), a joint site inspection, proof-ripping demonstration with the specified tractor class and joint survey pickup of the exposed rock surface are required before excavation proceeds.
- Hold Point — Individual blast design submission. Under TfNSW R44 Clause 4.6.1 and TMR MRTS55, a Hold Point applies prior to charging each blast or blast series, requiring submission of the Shotfirer's design covering hole diameter, depth, sub-drill, burden, spacing, maximum instantaneous charge (MIC), delay sequence, predicted PPV/airblast contours and flyrock exclusion zones.
- Hold Point — Geotechnical inspection of exposed batter faces and benches. As each cutting lift (typically 3 m to 6 m vertical bench drop) is excavated and scaled, the Geotechnical Assessor (TfNSW R44) must inspect the face to map defects, check for planar, wedge or toppling instability, and confirm rock bolting, dowelling or shotcrete requirements before lowering the floor further.
- Hold Point — Cutting floor and improved subgrade inspection. When excavation reaches design rock floor or undercut level, the surface is inspected to verify no intact rock pinnacles protrude into the pavement zone, over-break pockets are cleaned and drained, and foundation treatment complies prior to placing the bridging or capping layer.
- Quality verification — Rock fill grading, layer thickness and mechanical interlock. Continuous verification during embankment placement under TMR MRTS04 and VicRoads Section 205 ensures maximum particle size does not exceed specified fractions of compacted layer thickness and proof-rolling tolerances are achieved.
Risks and controls
- Uncontrolled flyrock during blasting. Caused by insufficient front-row burden, geological voids or mud seams, or inadequate collar stemming; controlled by driller log recording of voids, bore-tracking deviation surveys on front-row holes, stemming with crushed angular aggregate rather than drill dust, blast mats in urban corridors, and strict road closure and exclusion zones (TfNSW G10 / TMR MRTS55).
- Ground vibration or airblast exceedance at sensitive receivers. Caused by excessive Maximum Instantaneous Charge (MIC) per delay, atmospheric temperature inversions or unstemmed surface cord; controlled by electronic delay detonators, deck-charging holes, calibrated trial blasts, and continuous compliance monitoring with NATA-calibrated AS 2187.2 seismographs (5 mm/s PPV and 115 dBL residential targets).
- Batter face instability, planar slide or wedge failure. Caused by unfavourable joint sets dipping out of the face, production blast back-break or pore-water pressure; controlled by perimeter pre-splitting or line-drilling (TMR MRTS04), progressive bench scaling, geotechnical mapping Hold Points (TfNSW R44), tensioned rock bolts, passive dowels, shotcrete and horizontal weepholes.
- Subgrade undercut and over-break cost blowout. Caused by excessive sub-drilling on the final lift or aggressive ripping tearing deep craters below design subgrade; controlled by laser or GPS drill depth control, reduced final-lift sub-drill and charge weights, and backfilling over-break voids with approved granular fill or lean-mix concrete with positive subsoil drainage (VicRoads Section 204 / TfNSW R44).
- Latent condition and rippability classification disputes. Caused by wide borehole spacing missing unweathered corestones ("floaters") or low fracture density in moderate seismic velocity rock; controlled by pairing seismic refraction traverses with cored boreholes (AS 1726) and keeping machine telematics, ripper tip consumption logs and joint survey pickups to substantiate claims under TMR MRS04 or Main Roads WA Specification 302.
- Respirable crystalline silica (RCS) dust exposure. Caused by dry drilling, hydraulic hammering or ripping in quartz-rich sandstone, granite or quartzite; controlled by wet-suppression sprays on breakers and rippers, dust-extraction skirts and cyclones on drill rigs, positive-pressure HEPA-filtered operator cabins, and personal air monitoring.
Programming and weather
- Key predecessors before rock excavation starts. Environmental approvals, heritage clearances, utility relocations, pre-construction dilapidation surveys, Earthworks and Blast Management Plan Hold Point release (TMR MRTS55 / TfNSW R44), vegetation clearing (Main Roads WA Specification 301) and overburden soil stripping must finish before rock loosening begins.
- Sequential top-down bench staging logic. Deep rock cuttings must be programmed as sequential top-down bench lifts, where each bench follows a strict Finish-to-Start chain: drill and pre-split, charge and blast, scale and muck out, geotechnical inspection Hold Point, and batter stabilisation (rock bolting or shotcreting) before the bench below is excavated.
- Mass haul critical-path dependency. Rock cuttings frequently act as the critical-path supply source for high-embankment rock fill zones (VicRoads Section 205), bridge approach embankments or onsite crushing plants producing capping layers, meaning delays in cutting release directly stall downstream fill construction.
- Following activities at cutting completion. Once final cutting depth is reached, successor activities comprise cutting floor undercut (such as 150 mm under Main Roads WA Specification 302), slotted subsoil edge drain installation, Selected Material Zone (SMZ) or bridging layer placement, and pavement construction.
- Lower general rainfall sensitivity than cohesive soils. Because durable rock contains minimal plastic fines, excavation, haulage and mechanical interlock rock fill placement can often continue during light-to-moderate rainfall that would shut down clay earthworks.
- Electrical storm stand-downs and wet blast holes. Approaching lightning triggers an immediate safety stand-down of all explosive charging and blast areas, while heavy rain or groundwater filling drilled holes requires dewatering pumps or switching from water-soluble dry ANFO to water-resistant bulk emulsion explosives.
- Haul ramp traction, post-storm scaling and atmospheric inversions. Heavy rain lubricates steep rock haul ramps—increasing haul truck tyre cut damage—and washes clay infill from rock joints, requiring extra batter scaling inspections after storms, while low cloud cover, high winds toward receivers or morning temperature inversions amplify airblast overpressure (dBL) and can force blast postponement under AS 2187.2.
- Calendar and daytime curfew windows. Programmes must account for permitted blasting windows (Queensland guidance allows blasting from 7:00 am to 6:00 pm Monday to Saturday and not on Sundays or public holidays; project and licence conditions are often tighter) and urban hydraulic breaker noise respite periods, which cap effective daily operating hours.
Estimating considerations
- Primary unit of measure and survey takeoff. Rock excavation is measured in Bank Cubic Metres (BCM / m³ in situ), taken off by comparing the initial pre-excavation ground or exposed top-of-rock survey TIN against the final design cutting lines.
- Composite unclassified rate versus separate rock pay items. Under standard TMR MRS04 unclassified schedules and TfNSW R44 composite schedules, all cutting excavation is priced in a single composite rate with no separate payment for blasting unless scheduled; where separate Rippable vs. Non-Rippable (MRS04) or Rock Excavation items (Main Roads WA Specification 302, including machine refusal or boulders >0.8 m³) apply, estimators must price the specific contractual proof test.
- Swell (bulking) and embankment conversion in the mass haul. One BCM of intact rock swells substantially when broken into loose truck trays and compacts into a rock fill embankment at a net volume greater than 1.00 ECM (Embankment Cubic Metre) due to interstitial voids, requiring verified geotechnical bulking factors for both truck fleet sizing and mass-haul balance calculations.
- Mandatory cutting floor undercut and unpaid over-break backfill. Estimators must take off the specified rock floor undercut volume (such as 150 mm across the cutting floor under Main Roads WA Specification 302) plus an allowance for inevitable ripping or blasting over-break craters and the imported or processed granular backfill required to restore design subgrade level (VicRoads Section 204 / TfNSW R44).
- Pre-splitting and perimeter batter trimming takeoffs. Even when absorbed inside the composite BCM excavation rate, pre-splitting must be taken off internally per square metre (m²) of design batter face area and converted to linear metres (m) of closely spaced perimeter drilling and light explosive charging.
- Elevated GET, undercarriage and tyre wear allowances. Working D10/D11 dozers, hydraulic breakers, excavators and haul trucks on sharp fractured siliceous rock accelerates wear on ripper tips, shank protectors, track chains, bucket teeth and tyres well beyond standard dirt earthmoving owning and operating allowances.
- Secondary breaking and oversize processing plant. Because blasts and heavy ripping routinely generate 2% to 10% oversize boulders, the estimate must allow for a dedicated hydraulic breaker excavator at the face or tip head so all material meets rock fill particle size limits.
- Transition, bridging and geotextile separation layers. When placing coarse rock fill into embankments, estimators must include the cost and quantities for graded stone transition zones or geotextile separation membranes (ATS 2160) between the rock fill and overlying finer earthworks or subgrade layers.
- Compliance monitoring, dilapidation surveys and traffic control. Preliminaries or activity build-ups must allow for pre- and post-construction dilapidation surveys, NATA-calibrated triaxial geophone and airblast monitoring (AS 2187.2), geotechnical assessor face mapping attendances, and temporary road closure traffic management crews (TfNSW G10).
Specifications and standards
Checked 11 November 2026. Each document was looked up in catalogue and regulator listings; many agency PDFs could not be opened in full. Rows marked Confirmed were found to exist as described. Rows marked Not verified were not found or not checked. Clause-level statements, tolerances, temperatures, distances and similar figures in the text are typical values and are unverified unless a row cites the rule. Confirm the current edition of any document before relying on it.
| Document | What it covers for this method | Status |
|---|---|---|
| TMR MRTS04 & MRS04 General Earthworks (QLD) | Cutting excavation, rippable vs. non-rippable classifications, mechanical interlock rock fill placement, transition/capping zones, and Earthworks Construction Procedure Hold Points. | Confirmed |
| TMR MRTS55 & MRS55 Use of Explosives in Roadworks (QLD) | Quality system procedures, statutory liaison, blast design Hold Points, and ground vibration and airblast controls for roadworks blasting. | Confirmed |
| TfNSW QA Specification R44 Earthworks (including D&C R44, Clause 4.6 & Annexures R44/A7, R44/C) (NSW) | Earthworks Plan, rock excavation, cutting floor preparation, progressive geotechnical batter Hold Points, and blasting permissions and controls. | Not verified |
| TfNSW G36 Environmental Protection & G10 Traffic Management (NSW) | Environmental compliance frameworks for noise, vibration and airblast sub-plans (G36) and temporary road closures during blasting exclusion windows (G10). | Not verified |
| VicRoads Standard Section 204 Earthworks & Section 205 Rock Fill (VIC) | General and rock excavation, cutting floor over-break backfilling and regulating layers (Section 204), and engineered rock fill embankments and bridging layers (Section 205). | Confirmed |
| Main Roads WA Specification 301 Vegetation Clearing and Demolition & Specification 302 Earthworks (WA) | Precursor clearing (301) and rock excavation classification (machine refusal and >0.8 m³ boulder criteria), rock batter trimming, 150 mm rock cutting floor undercut, and rock fill placement (302). | Confirmed |
| Austroads ATS 2130 Construction of Earthworks & ATS 2160 Geotextiles (Separation and Filtration) | National harmonised technical specification for road earthworks construction (ATS 2130) and geotextile separation layers over coarse rock fill (ATS 2160). | Confirmed |
| Austroads Guide to Pavement Technology Part 4I: Earthworks Materials & Part 4J: Aggregate and Source Rock | Rock and earthworks material classification, durability assessment, and cutting/borrow material properties. | Not verified |
| AS 1726:2017 Geotechnical site investigations (and AS 4133.4.1 / AS 4133.4.2.1 (50 MPa and above) and AS 4133.4.2.2 (weaker rock)) | Table 19 Rock Material Strength Classification from Very Low (0.6–2 MPa UCS) to Extremely High (>200 MPa UCS), supported by Point Load and UCS laboratory testing standards. | Confirmed (covers 50 MPa and above; weaker rock is AS 4133.4.2.2) |
| AS 2187.2:2006 Explosives — Storage and use — Part 2: Use of explosives | Safe storage, handling and detonation of explosives, including Appendix J ground vibration (PPV) and airblast overpressure monitoring and guidance limits. | Confirmed |
Only documents confirmed to exist carry the status Confirmed. Check the current edition before relying on any document.
Sources and review
| Source | Used for | Status |
|---|---|---|
| TMR Technical Specifications Index — MRTS04 & MRS04 General Earthworks (tmr.qld.gov.au) | Rippable vs. non-rippable rock excavation, mechanical interlock rock fill, transition zones, and Earthworks Construction Procedure Hold Points. | Confirmed |
| TMR Technical Specifications — MRTS55 Use of Explosives in Roadworks (tmr.qld.gov.au) | Administrative controls, blast management plans, and quality compliance for explosives in roadworks. | Confirmed |
| Transport for NSW Standards Portal — QA Specification R44 Earthworks, G36 & G10 (standards.transport.nsw.gov.au) | Earthworks Plan, Clause 4.6 Blasting, Annexure R44/A7, Vibration and Airblast Sub-Plan Hold Points, building condition surveys, and geotechnical face inspections. | Not verified |
| Main Roads WA Technical Library — Specification 301 & Specification 302 Earthworks (mainroads.wa.gov.au) | Rock excavation definitions (>0.8 m³ boulders and heavy ripping thresholds), 150 mm undercut in rock cuttings, batter trimming, and rock fill. | Confirmed |
| Department of Transport and Planning / Big Build (VIC) — VicRoads Sections 204 & 205 (bigbuild.vic.gov.au) | Rock excavation vs. standard excavation, cutting floor over-break treatment, regulating layers, and Section 205 engineered rock fill. | Confirmed |
| Austroads Technical Specifications ATS 2130 & ATS 2160 and Guide to Pavement Technology Parts 4I & 4J (austroads.gov.au) | National earthworks construction framework, geotextile separation layers, rock material classification, and durability assessment. | Confirmed |
| AS 2187.2 Explosives — Storage and use — Part 2 & Environmental Blasting Guidelines (detsi.qld.gov.au) | Ground vibration PPV limits (5 mm/s and 10 mm/s residential; 15–100 mm/s structural), airblast limits (115 dBL and 120 dBL), daytime hours, and Appendix J instrumentation rules. | Confirmed |
| AS 1726:2017 Geotechnical site investigations Table 19 (standards.org.au) | Intact rock UCS (MPa) and Point Load (Is(50)) strength tiers from Very Low (0.6–2 MPa) to Extremely High (>200 MPa), referencing AS 4133.4.1 and AS 4133.4.2.1 (50 MPa and above) and AS 4133.4.2.2 (weaker rock). | Confirmed (covers 50 MPa and above; weaker rock is AS 4133.4.2.2) |
| Caterpillar Performance Handbook / Handbook of Ripping (cat.com) | D9, D10 and D11 seismic P-wave velocity rippability envelopes, tooth penetration requirements, and tandem ripping conditions. | Not verified |
Items marked Not verified have not been checked against a primary source. Research notes.