Plant / 28 to 32 t payload articulated dump truck
30-Tonne Articulated Dump Truck
The versatile 6x6 bulk earthworks hauler for rough terrain, steep haul roads, and high-production cut-to-fill civil projects.
- Dump bodySet payload against the material density and the truck limit.
- Articulation jointTurning and spotting time form part of the haul cycle.
- TyresHaul-road condition affects travel speed and tyre wear.
- Rated payload
- 28,000kg
- Heaped capacity
- 17.5m³
- Net power
- 274kW
AUD ex GST. *Unquoted placeholder. In accordance with Vaultix estimating principles, hire rates are never invented or extrapolated. Obtain current supplier quotations.
Choosing this class of articulated dump truck
A 30 t class articulated dump truck (nominal 28.0 t payload, 17.5 m³ heaped capacity) is the industry benchmark high-production earthmoving hauler for civil infrastructure, road construction, bulk cut-to-fill balancing, and quarry operations. Featuring 6x6 all-wheel drive, center-pivot oscillation, automatic traction control, and high ground clearance, it traverses rough haul routes and saturated ground where highway tippers cannot operate. Productivity is modeled from payload capacity, cycle time (load, haul, dump, return), and job operating efficiency.
The versatile 6x6 bulk earthworks hauler for rough terrain, steep haul roads, and high-production cut-to-fill civil projects.
28 to 32 t payload class / 28.0 t rated payload / 17.5 m³ body / 6x6 Articulated hauler / Civil estimating guide
- Bulk earthworks cut-to-fill balancing across major highway corridors, rail formations, and civil subdivisions
- Hauling overburden, ripped rock, and common fill across soft, undulating, or uncompacted subgrade terrain
- Transporting blasted shot-rock, ripped sandstone, and aggregate in quarry and borrow-pit operations
- Wet-weather haulage where 6x6 drive and high flotation tyres maintain site trafficability when highway tippers cannot run
- Spoil haulage to designated environmental mounds, tipheads, and site containment stockpiles
- Dam wall construction, clay liner placement, and tailings facility earthmoving
- Industrial site development, pad levelling, and large-footprint bulk earthmoving
Class planning guide
Published manufacturer specifications for the Cat 730 / 28-32 t payload class articulated dump truck. Use supplier specifications for exact procurement.
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 01.01 | Rated payload | 28,000 kg (28.0 t) | Cat 730 nominal payload rating (31.0 US tons). OEM Form AEXQ2714-03 p. 2, 3. |
| 01.02 | Body capacity (heaped SAE 2:1) | 17.5 m³ (23.0 yd³) | Standard rock/earth body heaped volume; 18.8 m³ with tailgate (derived). OEM Form AEXQ2714-03 p. 2. |
| 01.03 | Operating mass (empty) | 23,900 kg | Includes standard tyres, full lubricants, coolant, fuel, and operator. OEM Form AEXQ2714-03 p. 3. |
| 01.04 | Gross machine weight (loaded) | 51,900 kg (derived) | Derived: 23,900 kg tare + 28,000 kg payload = 51,900 kg GMW. OEM Form AEXQ2714-03 p. 3. |
| 01.05 | Engine power (net ISO 14396) | 276 kW (370 hp) | Cat C13 twin-turbocharged inline 6-cylinder diesel at 1,800 rpm. OEM Form AEXQ2714-03 p. 2. |
| 01.06 | Maximum travel speed | 55 km/h | HDPS 6 forward gears; working speeds typically 15 to 35 km/h. OEM Form AEXQ2714-03 p. 2. |
| 01.07 | Fuel burn allowance | 16.6 L/hr (medium duty) | OEM telematics benchmark (Wheeler Cat CPH); low 12.8, high 20.4 L/hr. CPH Form VST p. 1-2. |
| 01.08 | Shipping mass (bare tare) | About 23,450 kg (derived) | Derived: operating mass less 412 L fuel and operator. Confirm with haulier. OEM Form AEXQ2714-03 p. 2, 3. |
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 02.01 | Bulk cut-to-fill | 28 t payload & 17.5 m³ body | Matched to 30-36 t excavators (3-4 bucket passes) for maximum cycle efficiency. |
| 02.02 | Rough terrain & mud | 6x6 drive & automatic traction | Continuous all-wheel drive and inter-axle lock conquer slippery wet weather haul roads. |
| 02.03 | Steep haul roads | 35% gradeability & engine retarder | High climbing torque and automatic compression retarding on loaded descents. |
| 02.04 | Stockpile & tiphead | 70° dump tip angle | Fast 12-second body hoist and steep tip angle ensure clean discharge in sticky cohesive clays. |
| 02.05 | Float transport | OSOM 3-row / 4-row low loader | Machine travel width 2.95 m and height 3.51 m (approx. 4.41 m loaded on 900 mm drop-deck). |
Dimensions and transport planning
Machine dimensions exclude the transport float trailer. Obtain verified deck height, loaded envelope, axle group weights, route clearance and restraint plans from haulier before mobilisation.
| Code | Dimension | Published value | Planning note |
|---|---|---|---|
| 1 | Body Height – Fully Tipped | 6,468 mm | Dump body raised to maximum 70° tipping angle. OEM Form AEXQ2714-03 p. 4. |
| 2 | Load Over Height | 2,916 mm | Top rail height of body for loading tool clearance. OEM Form AEXQ2714-03 p. 4. |
| 3 | Ground Clearance – Body Fully Tipped | 563 mm | Discharge chute clearance at full dump. OEM Form AEXQ2714-03 p. 4. |
| 4 | Body Length | 5,783 mm | Overall dump body external length. OEM Form AEXQ2714-03 p. 4. |
| 5 | Body Length Inside | 5,411 mm | Internal cargo body length. OEM Form AEXQ2714-03 p. 4. |
| 6 | Ground Clearance | 545 mm | Driveline ground clearance under front axle. OEM Form AEXQ2714-03 p. 4. |
| 7 | Rear Axle Center to Body Rear | 1,556 mm | Rear chassis overhang. OEM Form AEXQ2714-03 p. 4. |
| 8 | Mid Axle Center to Rear Axle Center | 1,700 mm | Trailer bogie axle spacing. OEM Form AEXQ2714-03 p. 4. |
| 9 | Mid Axle Center to Front Axle Center | 3,979 mm | Primary tractor-to-bogie wheelbase. OEM Form AEXQ2714-03 p. 4. |
| 10 | Front Axle Center to Machine Front | 3,210 mm | Front tractor overhang. OEM Form AEXQ2714-03 p. 4. |
| 11 | Overall Length (Standard Body) | 10,445 mm | Overall front bumper to body chute length. OEM Form AEXQ2714-03 p. 4. |
| 12 | Overall Length with Tailgate | 10,593 mm | Overall length with optional scissor tailgate. OEM Form AEXQ2714-03 p. 4. |
| 13 | Height in Transport Position (Top of Cab) | 3,508 mm | Shipping height to top of ROPS cab. OEM Form AEXQ2714-03 p. 4. |
| 14 | Overall Width (Extended Mirrors) | 3,676 mm | Width across mirrors; folded for transport. OEM Form AEXQ2714-03 p. 4. |
| 15 | Width Over Tailgate | 2,984 mm | Maximum body width with tailgate fitted. OEM Form AEXQ2714-03 p. 4. |
| 16 | Body Width | 2,902 mm | External body width across canopy guard. OEM Form AEXQ2714-03 p. 4. |
| 17 | Track Width | 2,275 mm | Transverse track gauge centre-to-centre. OEM Form AEXQ2714-03 p. 4. |
| 18 | Width Over Tyres (Standard 23.5R25) | 2,877 mm | Width across standard 23.5R25 tyres. OEM Form AEXQ2714-03 p. 4. |
| 19 | Width Over Fenders | 2,950 mm | Overall travel width across rubber fenders. OEM Form AEXQ2714-03 p. 4. |
| 20 | Max Laden Width Over Tyre Bulge | 2,950 mm | Maximum loaded transport envelope across tyre bulge. OEM Form AEXQ2714-03 p. 4. |
Working range & capacities
Volumetric capacities, dump geometry, and climbing gradeability for the Cat 730 articulated dump truck. Allow for material bulk density, swell factors, and haul road rolling resistance.
| Code | Kinematic range item | Published value | Planning note |
|---|---|---|---|
| 1 | Rated Payload | 28,000 kg (28.0 t / 31.0 US tons) | Design nominal payload limit. Cat Production Measurement (CPM) telematics provides real-time payload monitoring with external indicator lights. |
| 2 | Body Volume (Struck) | 13.3 m³ (17.4 yd³) | Water-level struck capacity level with top of body side plates. |
| 3 | Body Volume (Heaped SAE 2:1) | 17.5 m³ (23.0 yd³) | Standard heaped body capacity for loose civil earthworks and quarry materials. |
| 4 | Body Volume with Scissor Tailgate | 18.8 m³ (24.6 yd³) | Derived heaped volume with mechanical tailgate preventing spillage on adverse grades (10-15%). |
| 5 | Dump Tipping Angle | 70 degrees | Steep 70° tipping angle powered by dual inverted hydraulic hoist cylinders ensures clean material discharge in cohesive clay and sticky fill. |
| 6 | Maximum Gradeability | Up to 35% (1:2.8) | Mechanical climbing capability in Gear 1 with 6x6 drive engaged; typical continuous civil haul road design grade limit is 10% to 15%. |
Direct cost and market hire prices
Never invent hire rates. In strict accordance with Vaultix estimating governance, all hire rate figures for this 28-32 t payload articulated dump truck class are recorded as not-yet-quoted placeholders. Enter verified project supplier quotes in the calculator below.
Metro and Remote direct costs
| Basis / AUD ex GST | Metro | Remote |
|---|---|---|
| Direct dry / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Direct wet / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Articulated dump truck operator / paid site hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Delivered diesel / L | 1.94 (reference proxy) | 2.23 (reference proxy) |
| Maintenance, parts and freight | Base allowance | Base plus 25% |
| Roster and camp | Metro working-week roster | 14/7 FIFO, 12-hour days, camp and flights |
Standing decision: Rates for this class have not yet been quoted or audited for vaultix.com.au. To ensure estimating integrity, rates are never estimated from other classes without supplier evidence. Estimators can input their project quotes directly in the instrument below.
Mobilisation, separate one-off cost
| Purchased transport / AUD ex GST | Metro | Remote |
|---|---|---|
| One delivery event | To be quoted by haulier | To be quoted by haulier |
Float mobilisation depends on transport distance, route permits, Class 1 OSOM dimensions (2.95 m travel width, 4.41 m loaded height on 900 mm drop-deck) and float deck availability. Allow separate return demobilisation event.
| Source / date | Hire basis | Per hour | Per day | Per week | Conditions |
|---|---|---|---|---|---|
| Awaiting supplier tender verification Status: Unquoted placeholder |
Dry / Wet pending quotes | Not yet quoted | Not yet quoted | Not yet quoted | All hire rate values are unquoted placeholders. Obtain 3 dated project rate cards including scissor tailgate options, body liner wear allowances, fuel inclusion, wear terms and float costs. |
First-principles direct hourly cost
| Component | Direct dry AUD/hr | Direct wet AUD/hr |
|---|---|---|
| Ownership: depreciation and interest | Not yet quoted | Not yet quoted |
| Insurance and registration | Not yet quoted | Not yet quoted |
| Maintenance, servicing, tyres and GET | Not yet quoted | Not yet quoted |
| Fuel and operating lubricants (16.6 L/hr proxy) | 0.00 | Not yet quoted |
| Articulated dump truck operator cost per paid site hour | 0.00 | Not yet quoted |
| Direct cost per operating hour | Not yet quoted | Not yet quoted |
Placeholder. Replace with a current supplier quote; no hire rates are invented or assumed.
Productivity and calculator
Hourly Production (t/hr) = Payload (t) × Trips per Hour. Trips per Hour = (60 min/hr / Total Cycle Time min) × Efficiency Factor. Total Cycle Time = Load Time + Haul Time + Dump Time + Return Time. Volumetric Output (m³/hr) = Hourly Production (t/hr) / Material Bulk Density (t/m³). All cycle times and efficiency allowances are Vaultix estimating assumptions.
Activity estimating guides
Vaultix civil estimating standard, 11 November 2026. Joint planning scenarios based on Caterpillar 730 cycle times.
Low: payload × 0.90, cycle time × 1.20, efficiency × 0.85. High: payload × 1.02, cycle time × 0.85, efficiency × 1.10.
01Bulk earthworks haulage
Large-scale civil earthworks haulage between major mass-haul excavation areas and bulk fill embankments across road corridors, industrial subdivisions, and airport platforms.
Vaultix assumptions: Payload 27.5 t; cycle 8.5 min (load 1.5 min, haul 3.8 min, dump 0.8 min, return 2.4 min); efficiency 75%.
Worked example: 27.5 t × (60 / 8.5 min × 0.75) = 145.6 t/hr, or 1,165 t in an 8-hour shift (~648 BCM at 1.8 t/BCM bulk density).
Allow for: 1.5 min 4-pass loading by 35 t excavator, loaded haul at 24 km/h (900 m), 0.8 min dump/turn, empty return at 32 km/h, and water cart coordination.
Pitfalls: Haul road rutting and excessive dust significantly increase rolling resistance, reducing travel speed and increasing fuel burn.
02Cut to fill
On-alignment roadbed and earthmoving cut-to-fill balancing, transporting excavated subgrade clays, ripped sandstone, and weathered rock directly to adjacent fill structural layers.
Vaultix assumptions: Payload 27.0 t; cycle 6.2 min (load 1.4 min, haul 2.2 min, dump 0.7 min, return 1.9 min); efficiency 78%.
Worked example: 27.0 t × (60 / 6.2 min × 0.78) = 203.8 t/hr, or 1,630 t in an 8-hour shift.
Allow for: Fast turnaround cycle (500 m haul), formation corridor traffic management, dozer push spreading at tiphead, and edge safety berms.
Pitfalls: Congestion at narrow cut sections or fill transitions creates spot delays and excavator queueing.
03Haul road use
Medium to long-distance haulage along established, graded haul corridors connecting regional borrow pits, remote dams, or civil bypass alignments to construction work zones.
Vaultix assumptions: Payload 28.0 t; cycle 13.5 min (load 1.5 min, haul 6.0 min, dump 0.8 min, return 5.2 min); efficiency 75%.
Worked example: 28.0 t × (60 / 13.5 min × 0.75) = 93.3 t/hr, or 747 t in an 8-hour shift.
Allow for: Sustained travel in Gear 4-5 (30-45 km/h over 2,000 m haul) on well-maintained unsealed roads, positive UHF radio protocols, and dust suppression watering.
Pitfalls: Poorly maintained haul roads with potholes or severe washboarding accelerate tire wear and cause suspension damage.
04Spoil to stockpile
Transporting unsuitable organic topsoil, contaminated spoil, or excess cut material from active excavations to permanent off-line spoil mounds or environmental stockpiles.
Vaultix assumptions: Payload 26.0 t; cycle 10.2 min (load 1.5 min, haul 4.6 min, dump 0.9 min, return 3.2 min); efficiency 72%.
Worked example: 26.0 t × (60 / 10.2 min × 0.72) = 110.1 t/hr, or 881 t in an 8-hour shift.
Allow for: Adverse gradient climbing up stockpile ramp (8-12% over 1,200 m haul), spotter positioning at tiphead, and tire wash down before site exit.
Pitfalls: Cohesive wet spoil tends to stick in body corners (carryback), reducing net payload capacity if not cleaned regularly.
05Wet-weather haulage
Operating in wet, slippery conditions, saturated soils, and uncompacted mud where high-flotation 6x6 all-wheel drive and central articulation provide trafficability when highway tippers cannot run.
Vaultix assumptions: Payload 24.0 t; cycle 11.5 min (load 1.6 min, haul 5.1 min, dump 0.9 min, return 3.9 min); efficiency 65%.
Worked example: 24.0 t × (60 / 11.5 min × 0.65) = 81.4 t/hr, or 651 t in an 8-hour shift.
Allow for: Intentional payload derating (24 t) to improve flotation over 700 m haul, low-gear operation (Gear 1-3), automatic traction control lock engagement, and continuous grader clearing.
Pitfalls: Deep mud ruts increase driveline strain and fuel burn; driving on slopes exceeding 15% in saturated conditions risks sliding and loss of directional control.
06Quarry haulage
Heavy-duty transport of blasted shot-rock, ripped basalt/granite, and processed quarry gravel from pit excavation faces up steep ramp systems to the primary crushing plant.
Vaultix assumptions: Payload 28.0 t; cycle 10.5 min (load 1.6 min, haul 4.8 min, dump 0.8 min, return 3.3 min); efficiency 80%.
Worked example: 28.0 t × (60 / 10.5 min × 0.80) = 128.0 t/hr, or 1,024 t in an 8-hour shift.
Allow for: Body wear liner protection, 45 t excavator or Cat 966-class loader matching, steep adverse ramp climb (10-12% over 1,400 m haul), and controlled tipping over crusher bin.
Pitfalls: Impact loading of oversized boulders (>1.0 m) can damage body floor and suspension; require excavator to cushion first bucket pass with fine material.
07Dam wall construction
Placement of selected cohesive impermeable clay core and structural rockfill embankments for water storage dams, agricultural reservoirs, and mine tailings containment facilities.
Vaultix assumptions: Payload 26.5 t; cycle 9.6 min (load 1.5 min, haul 4.2 min, dump 0.8 min, return 3.1 min); efficiency 75%.
Worked example: 26.5 t × (60 / 9.6 min × 0.75) = 124.2 t/hr, or 994 t in an 8-hour shift (~552 BCM at 1.8 t/BCM bulk density).
Allow for: 1.5 min 4-pass loading in borrow pit, adverse embankment access ramp climb (8-10% over 1,000 m haul), controlled thin-lift spreading, and compactor coordination.
Pitfalls: Strict soil moisture window required for clay compaction; wet-weather blinding requires scraper/grader strip before continuing fill placement.
Estimator checks
- Payload matching: Standard rock/earth body provides 17.5 m³ (SAE 2:1 heaped) and 28.0 t rated payload. In cohesive or light materials, fitment of a mechanical scissor tailgate increases volumetric retention to 18.8 m³ and prevents grade spillage.
- Loading tool matching: Optimize excavator pass matching — typically 3 to 4 bucket passes with a 30 to 36 t excavator (1.6 to 2.0 m³ bucket) or 4 passes with a Cat 966-class wheel loader (3.0 to 3.5 m³ bucket) for 1.4 to 1.8 min load times.
- Cycle time estimating: Total cycle time = excavator load time + haul travel + dump/manoeuvre + return travel + queue/spot delays. Haul speed depends heavily on rolling resistance (typically 40 to 60 kg/t on unpaved roads) and effective grade.
- Wet weather flotation: The Cat 730 features all-wheel drive, inter-axle and cross-axle differential locks (automatic traction control), and wide 23.5R25 tyres (or optional 750/65R25) to maintain trafficability in soft mud and cohesive subgrade.
- Transport & Float permitting: Machine width is 2.95 m (over fenders/tyres) and height is 3.51 m. On a 900 mm drop-deck float, loaded convoy height is approximately 4.41 m, exceeding the 4.30 m general height threshold. OSOM permits, route clearances, and 'OVERSIZE' signage are mandatory.
- Shipping tare: Base bare shipping mass is derived as approximately 23,450 kg (operating mass 23,900 kg less fuel and operator). Scissor tailgate adds ~450 kg; wide tyres add ~350 kg.
- Hire rates: In accordance with Vaultix governance, all hire rates remain unquoted placeholders pending verified project tenders. Never invent hire rates.
- Licensing & WHS: No High Risk Work Licence (HRWL) required under Australian WHS regulations; operators must hold national Unit of Competency RIIMPO337E and project Verification of Competency (VOC).
Data basis. Reference model: Caterpillar 730 Articulated Dump Truck (Aus-NZ / Stage V / Tier 4 Final, Build 04A), OEM technical specification sheet AEXQ2714-03. Fuel consumption based on Cat Performance Handbook VisionLink telematics benchmark (16.6 L/hr medium duty). Sourced 11 November 2026. Hire rates remain unquoted placeholders in accordance with Vaultix estimating governance. Sources and verification documented in files/adt-30t.md.
Entry / adt-30t Issue / 2026-11-11