Plant / Highway class tracked asphalt paver
Tracked Asphalt Paver
The quintessential Australian highway-class tracked asphalt paver for motorway carriageways, structural base courses, and airport pavements.
- Receiving hopperCoordinate feed with the truck or transfer vehicle.
- TracksAllow for manoeuvring and setting up each paving run.
- ScreedWidth and layer thickness determine the paving quantity.
- Standard width
- 2.55–5.0m
- Max throughput
- 900t/h
AUD ex GST. *Unquoted placeholder. In accordance with Vaultix estimating principles, hire rates are never invented or extrapolated. Obtain current supplier quotations.
Choosing this class of asphalt paver
A 19 to 22 t highway-class tracked asphalt paver is the production cornerstone of Australian motorway construction, arterial road rehabilitation, airport runways, and heavy civil pavements. Fitted with an AB 500 TV high-compaction extending screed featuring tamper bars and vibration, high-traction crawler tracks with replaceable rubber pads, and proportional conveyor/auger material feed, it places dense-graded asphalt (AC10/AC14), heavy bituminous base courses (AC20/AC28), and stone mastic asphalt up to 300 mm lift thickness. Productivity is modeled per hourly throughput tonnage (t/hr), finished surface area (m²/hr), and linear advance (m/hr) governed by paving width, compacted layer thickness, bulk density (2.40 t/m³), paving travel speed, and delivery logistics continuity.
The quintessential Australian highway-class tracked asphalt paver for motorway carriageways, structural base courses, and airport pavements.
19-22 t class / 2.55 – 5.0 m screed / Tracked undercarriage / Civil estimating guide
- Wearing course paving on motorways, national highways, and state arterial corridors (AC10 / AC14 to tight IRI roughness specifications)
- Heavy structural asphalt base and binder course placement (AC20 / AC28 dense bituminous base up to 100 mm+ compacted thickness)
- Airport runway, taxiway, and heavy-duty apron pavement construction to stringent surface tolerance hold-points
- Major road rehabilitation, cold-planed asphalt inlay (mill-and-fill), and asphalt overlay remediation
- Urban arterial road reconstruction, intersection widening, and bus lane paving
- Subdivision access roads, industrial estates, and port container terminal hardstand pavements
- Narrow shoulder paving and verge road-widening passes using mechanical screed cutoff shoes
Class planning guide
Published manufacturer specifications for the Vögele SUPER 1900-3i / 19-22 t class tracked asphalt paver. Use supplier specifications for exact procurement.
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 01.01 | Operating mass | 21,050 kg (to 5.0 m) / 26,900 kg (to 8.5 m) | Base tractor unit with AB 500 TV screed; add 5,850 kg for bolt-on extension kit up to 8.5 m. |
| 01.02 | Theoretical throughput | 900 t/h (375 m³/h) | Maximum hourly laydown capacity under uninterrupted delivery and continuous paving. |
| 01.03 | Standard paving width | 2.55 m to 5.00 m (up to 8.5 m) | Infinitely variable hydraulic telescoping from 2.55 m to 5.00 m; mechanical extensions to 8.50 m. |
| 01.04 | Diesel engine rated power | 145 kW (194 hp) @ 2,000 rpm | Liquid-cooled Cummins B6.7-C195 6-cylinder diesel (140 kW in fuel-saving ECO mode @ 1,700 rpm). |
| 01.05 | Material hopper payload | 14.0 tonnes (14,000 kg) | Heavy surge reception hopper with hydraulic folding wings and sprung push-rollers. |
| 01.06 | Fuel consumption allowance | About 12.0 to 26.0 L/hr | 17.5 L/hr medium continuous paving duty; 380 L tank provides over 21 hours endurance. |
| 01.07 | Shipping dimensions | 6.60 m (L) x 2.55 m (W) x 3.10 m (H) | Transport envelope with canopy lowered and screed retracted. 21,050 kg shipping tare. |
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 02.01 | Motorway & highway paving | High compaction TV screed & dual skis | Tamper and vibration deliver high pre-compaction density; sonic skis guarantee strict ride roughness (IRI) compliance. |
| 02.02 | Structural asphalt base | 100 mm+ lift thickness & 150 mm auger lift | Places thick AC20/AC28 dense bituminous base courses; augers lift 150 mm hydraulically to clear heavy aggregate head. |
| 02.03 | Urban & intersection work | Hydraulic screed width variation | Instant continuous hydraulic telescoping between 2.55 m and 5.0 m navigates tapers, flare lanes, and kerb returns. |
| 02.04 | Pavement rehabilitation | Mill-and-fill inlay matching cutter width | Accurate 3.5 m to 3.8 m lane inlay paving with tight longitudinal joint compaction against cold-planed asphalt. |
| 02.05 | Float transport | 3.10 m collapsed height & 2.55 m width | Low folded canopy height travels comfortably under 4.30 m bridge clearances on standard low-loader floats. |
Dimensions and transport planning
Machine dimensions exclude the transport float trailer. Obtain verified deck height, loaded envelope, axle group weights, route clearance and restraint plans from haulier before mobilisation.
| Code | Dimension | Published value | Planning note |
|---|---|---|---|
| 1 | Overall operating height to canopy peak | 3,860 mm | Working height from ground line to top of elevated hardtop roof with exhaust stack. |
| 2 | Overall transport height (canopy lowered) | 3,100 mm | Low-profile shipping height with GRP hardtop canopy hydraulically lowered. |
| 3 | Crawler track ground contact length | 3,060 mm | Ground contact length of crawler tracks under load. |
| 4 | Material hopper length to front push-roller | 2,100 mm | Length of front hopper compartment to face of push-rollers. |
| 5 | Tractor chassis length (without screed) | 5,355 mm | Chassis length from front push-rollers to rear screed tow-point pivot. |
| 6 | Overall transport length with AB 500 TV screed | 6,600 mm | Bumper-to-screed transport length with AB 500 TV screed fully retracted. |
| 7 | Overall transport length with AB 500 TP1/TP2 screed | 6,730 mm | Transport length when fitted with high-compaction pressure bar screed options. |
| 8 | Chassis undercarriage ground clearance | 170 mm | Ground clearance beneath tractor frame belly plate. |
| 9 | Crawler track gauge (center-to-center) | 1,970 mm | Transverse track center-to-center spacing. |
| 10 | Transport width across retracted screed | 2,550 mm | Overall width with AB 500 extending screed end gates folded for road float transport. |
| 11 | Material hopper width (open wings) | 3,265 mm | Overall reception width across fully unfolded hydraulic hopper wings. |
| 12 | Crawler track pad width | 305 mm | Width of individual replaceable rubber track pads. |
| 13 | Front approach ramp angle | 14.5° | Approach ramp clearance angle at front push-roller and hopper assembly. |
| 14 | Rear screed departure ramp angle | 12.5° | Departure ramp clearance angle beneath elevated screed for float loading. |
| 15 | Overall operating width across unfolded hopper wings | 3,265 mm | Overall width across fully deployed material reception wings. |
Working range & kinematics
Paving capacity, screed extension limits, material feed kinematics and operating speeds. Allow for haul truck logistics, mix temperature, and downstream compaction capacity.
| Code | Kinematic range item | Published value |
|---|---|---|
| 1 | Material hopper surge capacity | 14.0 tonnes (14,000 kg) |
| 2 | Theoretical laydown rate capacity | 900 t/h |
| 3 | Paving width range (AB 500 extending screed) | 2.55 m to 5.00 m (up to 8.50 m with extensions) |
| 4 | Paving speed range | 0 to 25 m/min |
| 5 | Travel and roading speed | 0 to 4.5 km/h |
| 6 | Paving layer thickness range | Not verified |
| 7 | Fuel operating endurance | 21.7 hours |
| 8 | Material conveyor feed rate | Up to 31 m/min |
| 9 | Material spreading auger speed | Up to 79 rpm |
| 10 | Theoretical volumetric laydown rate | 375.0 m³/h |
Direct cost and market hire prices
Never invent hire rates. In strict accordance with Vaultix estimating governance, all hire rate figures for this 19-22 t tracked asphalt paver class are recorded as not-yet-quoted placeholders. Enter verified project supplier quotes in the calculator below.
Metro and Remote direct costs
| Basis / AUD ex GST | Metro | Remote |
|---|---|---|
| Direct dry / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Direct wet / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Paver operator / paid site hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Delivered diesel / L | 1.94 (reference proxy) | 2.23 (reference proxy) |
| Maintenance, parts and freight | Base allowance | Base plus 25% |
| Roster and camp | Metro working-week roster | 14/7 FIFO, 12-hour days, camp and flights |
Standing decision: Rates for this class have not yet been quoted or audited for vaultix.com.au. To ensure estimating integrity, rates are never estimated from other classes without supplier evidence. Estimators can input their project quotes directly in the instrument below.
Mobilisation, separate one-off cost
| Purchased transport / AUD ex GST | Metro | Remote |
|---|---|---|
| One delivery event | To be quoted by haulier | To be quoted by haulier |
Float mobilisation depends on transport distance, route permits (for 2.55 m transport width under NHVR Class 1 Notice) and float deck availability. Allow separate return demobilisation event.
| Source / date | Hire basis | Per hour | Per day | Per week | Conditions |
|---|---|---|---|---|---|
| Awaiting supplier tender verification Status: Unquoted placeholder |
Dry / Wet pending quotes | Not yet quoted | Not yet quoted | Not yet quoted | All hire rate values are unquoted placeholders. Obtain 3 dated project rate cards including automated grade control options, screed extensions (>5.0 m), crew fitment, fuel inclusion, and float transport. |
First-principles direct hourly cost
| Component | Direct dry AUD/hr | Direct wet AUD/hr |
|---|---|---|
| Ownership: depreciation and interest | Not yet quoted | Not yet quoted |
| Insurance and registration | Not yet quoted | Not yet quoted |
| Maintenance, servicing, tracks and screed wear | Not yet quoted | Not yet quoted |
| Fuel and operating lubricants (17.5 L/hr proxy) | 0.00 | Not yet quoted |
| Paver operator cost per paid site hour | 0.00 | Not yet quoted |
| Direct cost per operating hour | Not yet quoted | Not yet quoted |
Placeholder. Replace with a current supplier quote; no hire rates are invented or assumed.
Productivity and calculator
Throughput t/hr = paving width m x thickness m x density t/m³ x speed m/min x 60 x efficiency; Finished area m²/hr = width m x speed m/min x 60 x efficiency. Linear advance m/hr = speed m/min x 60 x efficiency. All speed, layer thickness, and efficiency allowances are Vaultix civil estimating assumptions based on AS 2150 and Austroads guidelines.
Activity estimating guides
Vaultix estimating standards, 10 November 2026. Joint planning scenarios, not statistical confidence limits.
Throughput and advance rates reflect asphalt density of 2.40 t/m³ per AS 2150. Field output depends upon batch plant logistics, haul fleet availability, and downstream roller compaction capacity.
01Dense-graded asphalt wearing course
Standard Australian highway traffic lane wearing course (AC10 / AC14) placed to strict vertical level tolerances and International Roughness Index (IRI) specifications. Steady paving speed (4.0 m/min) is maintained to ensure uniform surface texture and avoid screed float fluctuation.
Vaultix assumptions: Paving speed 4.0 m/min; effective width 3.5 m; compacted thickness 50 mm (0.050 m); asphalt density 2.40 t/m³; efficiency 72%.
Worked example: Area = 3.5 m x 4.0 m/min x 60 x 0.72 = 605 m²/hr (173 linear m/hr). Throughput = 3.5 m x 0.050 m x 2.40 t/m³ x 4.0 m/min x 60 x 0.72 = 72.6 t/hr (726 tonnes per 10-hour shift).
Allow for: Quad-dog delivery truck turnaround, material transfer vehicle (MTV / shuttle buggy) hopper buffer, joint heater operation, and core sampling hold points.
Pitfalls: Paver stops cause screed indentation marks, cooling aggregate pockets, and localized IRI roughness failures. Maintain continuous forward motion matched to batch plant production.
02Asphalt base / intermediate
Heavy structural asphalt base course (AC20 / AC28 dense bituminous base) placed at 100 mm compacted depth. High mass laydown demand per linear metre requires lower forward speed (3.0 m/min) to prevent screed climb and prevent asphalt batch plant starvation.
Vaultix assumptions: Paving speed 3.0 m/min; effective width 3.6 m; compacted thickness 100 mm (0.100 m); asphalt density 2.40 t/m³; efficiency 70%.
Worked example: Area = 3.6 m x 3.0 m/min x 60 x 0.70 = 454 m²/hr (126 linear m/hr). Throughput = 3.6 m x 0.100 m x 2.40 t/m³ x 3.0 m/min x 60 x 0.70 = 108.9 t/hr (1,089 tonnes per 10-hour shift).
Allow for: High mass delivery logistics, thermal retainment covers on haulage trucks, screed tamper stroke adjustment, and heavy steel breakdown rolling.
Pitfalls: Excessive forward speed on thick courses causes screed climb and density segregation. Auger tunnel height must be raised to 150 mm to prevent aggregate shearing.
03Shoulder paving
Narrow highway hard shoulder or verge road-widening pass (typically 1.8 m width) using mechanical screed cutoff shoes. Higher linear speed (4.5 m/min) is achievable as ride roughness tolerances are less onerous.
Vaultix assumptions: Paving speed 4.5 m/min; effective width 1.8 m; compacted thickness 50 mm (0.050 m); asphalt density 2.40 t/m³; efficiency 65%.
Worked example: Area = 1.8 m x 4.5 m/min x 60 x 0.65 = 316 m²/hr (176 linear m/hr). Throughput = 1.8 m x 0.050 m x 2.40 t/m³ x 4.5 m/min x 60 x 0.65 = 37.9 t/hr (379 tonnes per 10-hour shift).
Allow for: Guardrail barrier offsets, drainage drop-inlets, unpaved shoulder soft edges, and uneven crossfall transitions.
Pitfalls: Operating crawler track off pavement edge can destabilize screed plane. Fit cutoff shoes and maintain tractor tracks firmly on compacted base.
04Intersection and tie-in paving
Urban intersection, roundabout, or turn-lane tying into existing kerbs and cold-milled headers. Paving speed is restrained (2.2 m/min) with constant hydraulic screed width modulation (2.55 to 4.8 m), frequent handwork raking, and live traffic staging.
Vaultix assumptions: Paving speed 2.2 m/min; effective width 3.5 m; compacted thickness 50 mm (0.050 m); asphalt density 2.40 t/m³; efficiency 50%.
Worked example: Area = 3.5 m x 2.2 m/min x 60 x 0.50 = 231 m²/hr (66 linear m/hr). Throughput = 3.5 m x 0.050 m x 2.40 t/m³ x 2.2 m/min x 60 x 0.50 = 27.7 t/hr (277 tonnes per 10-hour shift).
Allow for: Extensive handwork raking by 3 rakers, manual plate compaction along kerb lips, transverse joint feathering, and complex traffic staging.
Pitfalls: Frequent start-stops and sharp radius turns create material segregation and cool mix pockets. Screed operators must coordinate hydraulic extensions smoothly.
05Overlay and inlay
Pavement rehabilitation including mill-and-fill inlay into cold-planed asphalt boxes or structural overlay over profiled bitumen bases. Matches milling cutter width (typically 3.5 m) with steady travel and sonic joint matching.
Vaultix assumptions: Paving speed 4.2 m/min; effective width 3.5 m; compacted thickness 45 mm (0.045 m); asphalt density 2.40 t/m³; efficiency 72%.
Worked example: Area = 3.5 m x 4.2 m/min x 60 x 0.72 = 635 m²/hr (181 linear m/hr). Throughput = 3.5 m x 0.045 m x 2.40 t/m³ x 4.2 m/min x 60 x 0.72 = 68.6 t/hr (686 tonnes per 10-hour shift).
Allow for: Tack coat curing verification, sonic averaging ski tracking on adjacent milled rebate, joint sealant tape application, and tight night possession hours.
Pitfalls: Mismatching milled cutter width results in screed riding on un-milled shoulder, causing longitudinal level defect. Align screed end gate precisely with milling joint.
06Bridge approach paving
Controlled transition paving onto bridge abutment relief slabs, waterproofing membrane protection courses, and expansion joint block-outs. Steady, restrained speed (2.8 m/min) prevents dynamic bump formation at bridge joints.
Vaultix assumptions: Paving speed 2.8 m/min; effective width 3.6 m; compacted thickness 50 mm (0.050 m); asphalt density 2.40 t/m³; efficiency 60%.
Worked example: Area = 3.6 m x 2.8 m/min x 60 x 0.60 = 363 m²/hr (101 linear m/hr). Throughput = 3.6 m x 0.050 m x 2.40 t/m³ x 2.8 m/min x 60 x 0.60 = 43.6 t/hr (436 tonnes per 10-hour shift).
Allow for: Surveyor elevation checks, protective steel plates over expansion joints, membrane protection verification, and manual joint edging.
Pitfalls: Dynamic impact over bridge joint blockouts can shear screed sole plates or damage expansion joints. Utilize AutoSet Plus screed lift to ramp over joint gap.
07Carpark and industrial hardstand
Commercial retail carparks, logistics distribution centre hardstands, and industrial warehouse exterior pavements. Paving speed (3.5 m/min) and wide screed setting (4.0 m) balance large open bay coverage with layout maneuvering around kerb returns and stormwater pits.
Vaultix assumptions: Paving speed 3.5 m/min; effective width 4.0 m; compacted thickness 50 mm (0.050 m); asphalt density 2.40 t/m³; efficiency 65%.
Worked example: Area = 4.0 m x 3.5 m/min x 60 x 0.65 = 546 m²/hr (137 linear m/hr). Throughput = 4.0 m x 0.050 m x 2.40 t/m³ x 3.5 m/min x 60 x 0.65 = 65.5 t/hr (655 tonnes per 10-hour shift).
Allow for: Storm drainage pit blockouts, light pole island maneuvering, delivery truck staging, and edge handwork.
Pitfalls: Frequent turns and short run bays increase transverse joint count. Coordinate joint layout to align with traffic aisles.
Estimator checks
- Confirm screed configuration: standard AB 500 TV hydraulically extends from 2.55 m to 5.00 m. If paving widths up to 8.50 m are scheduled, allow mechanical bolt-on extension boxes, auger extensions, and fitting labor.
- Paving speed matching: Maintain forward speed between 2.5 and 5.0 m/min to establish thermal and hydrostatic equilibrium beneath the screed. Paver stops cause screed settling and transverse ride bumps.
- Delivery logistics & truck balancing: Continuous paving requires synchronized asphalt batch plant supply and delivery trucking. Hopper surge capacity is 14.0 t; each truck changeover takes approximately 60 to 90 seconds.
- Grade and slope control: Verify automated machine guidance fitment (Niveltronic Plus with dual ultrasonic multi-foot skis, sonic grade sensors, or 3D Total Station UTS machine control) to achieve specified surface level tolerances.
- Transport logistics: Retracted width of 2.55 m requires an NHVR Class 1 Oversize Load Notice in all Australian states (signage, flags, beacons). Travel height of 3.10 m (canopy lowered) loads safely under 4.30 m on a standard drop-deck float.
- Compaction train coordination: Coordinate paver advance with downstream compaction train (typically 10-12 t tandem vibratory roller for breakdown compaction, followed by 15-24 t multi-tyre pneumatic roller for intermediate kneading).
- All hire rate schedules are unquoted placeholders. In accordance with Vaultix estimating principles, never invent hire rates without formal supplier tenders.
- No HRWL class required; operator competency confirmed by VOC and national unit of competency RIIHAN309F (Conduct civil paving operations).
Data basis. Independent check 10 November 2026 against the Vogele SUPER 1900-3i brochure: all 9 values checked matched. The maximum layer thickness of 300 mm is not printed for the AB 500 screed (the sheet gives up to 40 cm for the SB 300 only), so it is Not verified. Reference model: Vögele SUPER 1900-3i Tracked Highway Class Asphalt Paver (equipped with AB 500 TV Extending Screed), OEM specification document 2865477 EN/06.20. Sourced 10 November 2026. Fuel uses Cummins B6.7-C195 engine load-profiling proxy (17.5 L/hr medium duty). Productivity uses Vaultix paving formulas (Austroads / AS 2150). Hire rates remain unquoted placeholders pending verified commercial tenders. Sources and assumptions.