Plant / 40 to 45 m truck-mounted concrete boom pump
42 m Concrete Boom Pump
The primary high-reach placement workhorse for civil infrastructure, commercial structures, bridge decks, and deep foundation pours throughout Queensland and Australia.
- Receiving hopperTruck supply rate must support the pour.
- Placing boomPosition and reach determine the area served from each setup.
- OutriggersInclude setup and relocation time in the programme.
- Vertical reach
- 41.6m
- Max pump output
- 160m³/hr
AUD ex GST. *Unquoted placeholder. In accordance with Vaultix estimating principles, hire rates are never invented or extrapolated. Obtain current supplier quotations.
Choosing this class of concrete boom pump
A 42 m class truck-mounted concrete placing boom pump (such as the Putzmeister BSF 42-5.16 H on an 8x4 carrier) is the primary high-output placement platform for Australian civil engineering works, multi-storey commercial floors, bridge infrastructure, and deep shaft or piling pours. Featuring a 5-section Roll-Z (RZ) boom with 41.6 m vertical reach height, 37.3 m gross horizontal reach, 31.0 m depth reach, and a compact 8.6 m unfolding clearance, it is equipped with a Putzmeister .16 H pump unit delivering up to 160 m³/hr output at 85 bar line pressure via twin 230 mm x 2,100 mm cylinders. Productivity is modeled by volumetric placement rate (m³/hr) governed by rated pump speed, batching/transit mixer turnaround, formwork capacity, rebar congestion, and fixed allowances for outrigger setup and pipeline washout.
The primary high-reach placement workhorse for civil infrastructure, commercial structures, bridge decks, and deep foundation pours throughout Queensland and Australia.
40-45 m class / 5-section Roll-Z boom / 160 m³/hr output / Civil estimating guide
- High-volume slab on ground placement for industrial warehouse floors, apron pavements, hardstands, and commercial slabs
- Multi-storey commercial suspended slabs, post-tensioned (PT) transfer plates, and elevated podium decks
- Controlled vertical placement into high-density columns, shear walls, retaining walls, and core structures
- Civil infrastructure bridge decks, Super-T stitch joints, piers, headstocks, and abutment pours
- Continuous pressurized concrete delivery into continuous flight auger (CFA) piling rigs and tremie pipes
- Deep vertical shaft placement (up to 31 m reach depth) and tunnel lining inverts and caissons
Class planning guide
Published manufacturer specifications for the Putzmeister BSF 42-5.16 H / 40 to 45 m class concrete boom pump. Use supplier specifications for exact procurement.
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 01.01 | Vertical reach | 41.6 m | Ground level to tip of boom pipeline at full vertical extension. |
| 01.02 | Gross horizontal reach | 37.3 m | Radius from center of turret slewing axis to end of delivery line. |
| 01.03 | Net horizontal reach | 34.5 m | Reach from front vehicle bumper / outrigger line to flexible end hose tip. |
| 01.04 | Maximum reach depth | 31.0 m | Downward reach below outrigger support level for shafts and basements. |
| 01.05 | Unfolding height | 8.6 m | Low headroom clearance required to unfold 5-section RZ boom. |
| 01.06 | Max pump output | 160 m³/hr | Theoretical maximum volumetric delivery rate on rod side hydraulic drive. |
| 01.07 | Max line pressure | 85 bar (8.5 MPa) | Maximum continuous concrete pressure in delivery pipeline. |
| 01.08 | Outrigger footprint | 7.50 m (front) / 8.30 m (rear) | Transverse outrigger spread at standard full deployment. |
| 01.09 | Travel GVM | Not verified | Operating road transit mass on 4-axle twin-steer carrier. |
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 02.01 | 5-section RZ fold | Low 8.6 m unfolding height | Enables boom deployment under warehouse roofs, bridge decks, and inside covered structures. |
| 02.02 | High-output pump cell | 160 m³/hr @ 85 bar | Twin 230 mm x 2,100 mm cylinders provide fast placement for mass concrete and slabs. |
| 02.03 | Flexible outriggers | ESC & One-Sided Support (OSS) | Allows setups in narrow street lanes, alongside excavations, or within confined site boundaries. |
| 02.04 | Deep reach capability | 31.0 m downward reach | Reaches deep basement excavations, subway shafts, and retention wall caissons. |
| 02.05 | Highway mobility | Self-propelled SPV Level 1 | Operates under NHVR Special Purpose Vehicle notice at highway speeds without low-loader float mobilization. |
Dimensions and transport planning
Machine dimensions reflect road transit configuration on 8x4 carrier chassis. Obtain verified axle group weights, route clearance and permit requirements before mobilisation.
| Code | Dimension | Published value | Planning note |
|---|---|---|---|
| L | Overall transport length | 11,350 mm | Bumper-to-hopper overall vehicle length in highway road travel trim. |
| W | Overall transport width | 2,500 mm | Complies with Australian general access limits (excluding side mirrors). |
| H | Overall transport height | 4,000 mm | Road travel height to apex of folded boom; complies with 4.3 m envelopes. |
| WB1 | Twin-steer axle spacing (Axle 1 to 2) | 2,800 mm | Center-to-center spacing between first and second steer axles. |
| WB2 | Wheelbase span (Axle 2 to Tandem Center) | 5,500 mm | Center distance from second steer axle to center of drive bogie. |
| WB3 | Tandem drive axle spacing (Axle 3 to 4) | 1,350 mm | Center-to-center axle spacing across rear drive bogie. |
| OF | Front overhang | 1,360 mm | Front steer axle center to foremost bumper point. |
| OR | Rear overhang | 3,060 mm | Rear drive axle center to rearmost edge of concrete hopper. |
| SF | Front outrigger support spread (full) | Not verified | Full transverse spread between front diagonal outrigger centers. |
| SR | Rear outrigger support spread (full) | Not verified | Full transverse spread between rear swing-out outrigger centers. |
| UH | Minimum boom unfolding height | 8,600 mm | Low ceiling clearance required to unfold 5-section RZ placing boom. |
| SP | Outrigger swivel foot diameter | 350 mm | Circular steel swivel pads; mandates crane spreader mats per AS 2550.15. |
Working range & kinematics
Kinematic reach envelope and pumping performance for the Putzmeister BSF 42-5.16 H placing boom pump. Allow for outrigger exclusion zones, ground bearing capacity, and pipeline delivery resistance.
| Code | Kinematic range item | Published value |
|---|---|---|
| 1 | Maximum vertical reach height | 41.6 m (Ground level to tip of boom pipeline at full elevation) |
| 2 | Maximum gross horizontal reach | 37.3 m (From center of turret slewing axis to end of delivery line) |
| 3 | Maximum net horizontal reach | 34.5 m (From front vehicle bumper / outrigger line to flexible end hose tip) |
| 4 | Maximum downward reach depth | 31.0 m (Vertical reach below outrigger level for shafts and caissons) |
| 5 | Minimum boom unfolding height | 8.6 m (Vertical clearance to unfold 5-section RZ boom inside structures) |
| 6 | Flexible delivery end hose length | 4.0 m (Standard DN 125 hose with safety whip restraint cable per AS 2550.15) |
| 7 | Boom slewing rotation range | 365° continuous (Continuous turret slewing circle with electro-hydraulic control) |
| 8 | Maximum concrete output (rod side) | 160 m³/hr (Theoretical maximum delivery rate of Putzmeister .16 H pump cell) |
| 9 | Maximum concrete delivery pressure | 85 bar (8.5 MPa / 1,233 psi on boom pipeline system) |
| 10 | Delivery cylinder stroke & diameter | Ø 230 mm x 2,100 mm (High-volume displacement, 87.2 L per double stroke) |
| 11 | Onboard washdown water tank | 700 L (Water reservoir supporting 160 L/min @ 25 bar washdown pump) |
Direct cost and market hire prices
Never invent hire rates. In strict accordance with Vaultix estimating governance, all hire rate figures for this 40 to 45 m concrete boom pump class are recorded as not-yet-quoted placeholders. Enter verified project supplier quotes in the calculator below.
Metro and Remote direct costs
| Basis / AUD ex GST | Metro | Remote |
|---|---|---|
| Direct dry / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Direct wet / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Boom pump operator & line hand crew / paid site hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Delivered diesel / L | 1.94 (reference proxy) | 2.23 (reference proxy) |
| Maintenance, parts and freight | Base allowance | Base plus 25% |
| Roster and camp | Metro working-week roster | 14/7 FIFO, 12-hour days, camp and flights |
Standing decision: Rates for this class have not yet been quoted or audited for vaultix.com.au. To ensure estimating integrity, rates are never estimated from other classes without supplier evidence. Estimators can input their project quotes directly in the instrument below.
Mobilisation, separate one-off cost
| Purchased transport / AUD ex GST | Metro | Remote |
|---|---|---|
| One delivery event | To be quoted by haulier | To be quoted by haulier |
Self-propelled SPV road transit mobilization depends on travel distance, NHVR permits, bridge engineering assessments, and local council travel curfew windows. Allow separate return demobilisation event.
| Source / date | Hire basis | Per hour | Per day | Per week | Conditions |
|---|---|---|---|---|---|
| Awaiting supplier tender verification Status: Unquoted placeholder |
Dry / Wet pending quotes | Not yet quoted | Not yet quoted | Not yet quoted | All hire rate values are unquoted placeholders. When procuring 42 m concrete boom pumps in Australia, solicit formal quotations covering wet/dry hire, travel/mobilisation, minimum hire hours (typically 4-6 hrs), primer slurry supply, excess pipeline wear, and line hand / offsider inclusion. |
First-principles direct hourly cost
| Component | Direct dry AUD/hr | Direct wet AUD/hr |
|---|---|---|
| Ownership: depreciation, finance and capital return | Not yet quoted | Not yet quoted |
| Insurance, registration and CTP | Not yet quoted | Not yet quoted |
| Maintenance, pipeline wear, boom inspections and certification | Not yet quoted | Not yet quoted |
| Fuel, lubricants and DEF (35.0 L/hr pumping proxy) | 0.00 | Not yet quoted |
| Boom pump operator and line hand crew per site hour | 0.00 | Not yet quoted |
| Direct cost per operating hour | Not yet quoted | Not yet quoted |
Placeholder. Replace with a current supplier quote; no hire rates are invented or assumed.
Productivity and calculator
Effective Placement Rate (m³/hr) = Rated Pump Output (m³/hr) × Efficiency. Total Pour Duration (hr) = (Pour Volume m³ / Placement Rate m³/hr) + Setup Time (hr) + Wash-Out Time (hr). Efficiency factor accounts for transit mixer changeover times, concrete sampling/testing pauses, rebar congestion, vibrator crew pacing, screeding operations, and incremental boom articulation. All factors are Vaultix estimating assumptions.
Activity estimating guides
Vaultix estimating standards, 10 November 2026. Joint planning scenarios, not statistical confidence limits.
Low scenario: rated output x 0.85, efficiency x 0.80, setup/washout x 1.25. High scenario: rated output x 1.15, efficiency x 1.10 (cap 1.00), setup/washout x 0.85.
01Slab on ground pour
High-volume unconstrained concrete placement for industrial warehouse floors, apron slabs, hardstands, and large residential/commercial ground footing slabs.
Vaultix assumptions: Rated output 100 m³/hr; efficiency 68%; setup time 45 min; wash-out time 45 min.
Worked example: 100 m³/hr x 0.68 efficiency = 68.0 m³/hr effective placement rate. A 400 m³ pour requires (400 / 68.0) + 1.5 hr setup/washout = 7.4 hours.
Allow for: Concrete transit mixer turnaround (3-5 min swap), dual-truck discharge, laser screed progression, bull floating, and initial slurry prime.
Pitfalls: Agitator truck delivery delays cause cold joints and pipeline blockages; site access bottle-necking around pump hopper.
02Suspended slab pour
Structural concrete placement for multi-storey commercial building floors, post-tensioned (PT) decks, transfer slabs, and podium levels.
Vaultix assumptions: Rated output 80 m³/hr; efficiency 58%; setup time 50 min; wash-out time 50 min.
Worked example: 80 m³/hr x 0.58 efficiency = 46.4 m³/hr effective placement rate. A 250 m³ deck pour requires (250 / 46.4) + 1.67 hr setup/washout = 7.1 hours.
Allow for: PT duct inspection hold points, conduit protection, vibrating teams, manual screeding, and boom articulation between deck bays.
Pitfalls: Exceeding allowable formwork deck live load; end-hose dragging over delicate post-tensioning ducts; perimeter barrier drop hazards.
03Column and wall pours
Controlled vertical structural concrete delivery into core walls, shear walls, retaining walls, columns, and bridge abutments.
Vaultix assumptions: Rated output 40 m³/hr; efficiency 42%; setup time 45 min; wash-out time 45 min.
Worked example: 40 m³/hr x 0.42 efficiency = 16.8 m³/hr effective placement rate. An 80 m³ core wall pour requires (80 / 16.8) + 1.5 hr setup/washout = 6.3 hours.
Allow for: Restricted pump output to control lateral hydrostatic pressure; incremental 500-1,000 mm horizontal layer lifts; intensive internal pencil needle vibration.
Pitfalls: Formwork hydrostatic bursting blowout from rapid vertical pour rates; honeycombing around dense rebar; end-hose blockage on restart.
04Bridge deck / pier pours
High-specification civil infrastructure pours including bridge piers, headstocks, Super-T girder deck stitch joints, and monolithic composite bridge decks.
Vaultix assumptions: Rated output 70 m³/hr; efficiency 52%; setup time 60 min; wash-out time 55 min.
Worked example: 70 m³/hr x 0.52 efficiency = 36.4 m³/hr effective placement rate. A 180 m³ bridge deck pour requires (180 / 36.4) + 1.92 hr setup/washout = 6.9 hours.
Allow for: Strict state road authority testing per agitator truck (slump, flow, air, temp, cylinders); roller screed finishing; crane mat verification on embankments.
Pitfalls: Rejection of out-of-spec batches causing pump line stall; slurry wash water runoff into live watercourses or environmental corridors.
05Piling concrete delivery
Direct pressurized pumping into continuous flight auger (CFA) piling rigs, bored pile tremie strings, and diaphragm wall panels.
Vaultix assumptions: Rated output 85 m³/hr; efficiency 62%; setup time 50 min; wash-out time 45 min.
Worked example: 85 m³/hr x 0.62 efficiency = 52.7 m³/hr effective placement rate. A 200 m³ continuous CFA piling shift requires (200 / 52.7) + 1.58 hr setup/washout = 5.4 hours.
Allow for: Direct coupling of boom pipeline to auger swivel adapter hose; uninterrupted pour synchronized with rig auger extraction speed.
Pitfalls: Loss of concrete head causing pile necking defects; excessive line pressure spike if auger extraction stalls.
06Tunnel / shaft lining
Deep vertical delivery down access and launch shafts (up to 31 m depth) for shaft bottom plugs, tunnel invert slabs, cross passages, and cavern secondary linings.
Vaultix assumptions: Rated output 50 m³/hr; efficiency 48%; setup time 60 min; wash-out time 60 min.
Worked example: 50 m³/hr x 0.48 efficiency = 24.0 m³/hr effective placement rate. A 120 m³ shaft base plug pour requires (120 / 24.0) + 2.0 hr setup/washout = 7.0 hours.
Allow for: Controlled throttling against vertical gravity head down shaft; tethered drop chains on end hose; two-way radio and video spotters.
Pitfalls: Aggregate segregation from uncontrolled freefall in vertical slickline; line kick and air entrapment during pipeline purging down deep shafts.
07Mass concrete and raft pour
High-volume structural foundation concrete delivery for heavy industrial raft slabs, wind turbine gravity bases, bridge anchor blocks, and crane bases.
Vaultix assumptions: Rated output 120 m³/hr; efficiency 72%; setup time 45 min; wash-out time 45 min.
Worked example: 120 m³/hr x 0.72 efficiency = 86.4 m³/hr effective placement rate. A 500 m³ raft foundation pour requires (500 / 86.4) + 1.5 hr setup/washout = 7.3 hours.
Allow for: Continuous multi-truck agitator discharge; high pump cadence; thermal gradient monitoring; mechanical needle vibrator gangs.
Pitfalls: Cold joints if transit mixer supply slows; thermal cracking in deep sections (>1.5 m thickness); high delivery pipeline wear.
Estimator checks
- AS 2550.15 Compliance: Operation, inspection, and maintenance must adhere strictly to Australian Standard AS 2550.15 (Concrete placing equipment). 6-monthly inspections and 5-yearly major structural tear-down recertifications are mandatory.
- HRWL Requirement: Boom pump operation requires a SafeWork High Risk Work Licence class PB (Concrete Placing Boom). Truck road transit requires an Australian Heavy Rigid (HR) driver licence.
- Ground Bearing & Crane Mats: Maximum outrigger reaction force is 240 kN (~24.5 t). Under bare 350 mm steel swivel feet, bearing pressure is 2.50 MPa (Derived: 240 kN / 0.0962 m² = 2,495 kPa = 2.50 MPa), which will punch through uncompacted subgrade. Spreader crane mats (minimum 1.0 m² area) are mandatory to reduce bearing pressure to 240 kPa (Derived: 240 kN / 1.0 m² = 240 kPa).
- Unfolding Clearance: The 5-section RZ boom requires 8.6 m vertical ceiling clearance to unfold. Check warehouse roof trusses, bridge soffits, and overhead portal cranes.
- Overhead Powerline Exclusion Zones: Observe the Look Up and Live rule. Maintain statutory exclusion zones (minimum 3.0 m up to 132 kV, 6.0 m for 132 to 330 kV, 8.0 m over 330 kV) with dedicated safety spotters and Tiger Tails.
- Hose Whip Hazard: The flexible delivery end hose must never exceed 4.0 m in length per AS 2550.15. Maintain an 8.0 m exclusion zone during priming or when air is trapped in the pipeline.
- Environmental Washout: Concrete wash water is highly alkaline (pH > 12). Mandate watertight washout containment bins or environmental slurry bags; zero discharge to stormwater or waterways.
- Hire Rates: All hire rate figures remain unquoted placeholders pending verified project tenders. Never invent hire rates.
Data basis. Independent check 10 November 2026 against the Putzmeister BSF 42-5.16 H data sheet: reach, output and pressure matched. Not verified: gross vehicle mass (depends on the carrier truck), outrigger point loads of 240 and 220 kN (cited to a Schwing sheet, not Putzmeister), front and rear outrigger spreads, and the derived ground bearing figures that use them. Do not use these for ground-bearing design. Reference model: Putzmeister BSF 42-5.16 H truck-mounted concrete boom pump (5-section RZ-fold M 42-5 placing boom on 8x4 Mercedes-Benz Actros carrier). Technical specifications sourced from official Putzmeister Concrete Pumps GmbH data sheet CT 4381-5 EN (https://tlilleste.se/content/files/pdf/m42_datablad.pdf) and Schwing S 42 SX data sheet 10311060 (https://www.schwing.cz/wp-content/uploads/2019/09/S_42_SX_10311060_low-regulated_EN.pdf). Verified 10 November 2026. Fuel burn derived from Mercedes-Benz OM 501 / OM 470 engine telematics with PTO engaged (35.0 L/hr likely). Productivity uses Vaultix concrete placing formulas. Hire rates remain unquoted placeholders pending verified tenders. Sources and assumptions.
Entry / conc-boom-pump-42m Issue / 2026-11-10