Plant / 40 to 80 m³/h stationary / trailer concrete line pump
Trailer Concrete Line Pump
High-pressure concrete placement workhorse for civil foundations, ground slabs, tunnel shotcrete, and restricted-access pours throughout Queensland and Australia.
- HopperPlan mixer access and a continuous feed.
- Pump bodyAdopt achievable delivery for the specified mix and pipeline.
- Delivery lineAllow for routing, handling and cleaning the line.
- Max pump output
- 71m³/hr
- Max line pressure
- 106bar
AUD ex GST. *Unquoted placeholder. In accordance with Vaultix estimating principles, hire rates are never invented or extrapolated. Obtain current supplier quotations.
Choosing this class of trailer concrete line pump
A heavy-duty trailer-mounted stationary concrete line pump (such as the Putzmeister BSA 1407 D powered by a 115 kW Deutz diesel) is the core high-pressure concrete delivery system for civil engineering works, ground slabs, foundation footings, vertical formwork, tunnel shotcreting, and long-distance restricted access pours where boom pumps cannot access or set up. Equipped with twin Ø 200 mm x 1,400 mm material cylinders, S 2015 D S-transfer tube valve, and 600 L RS 909 receiving hopper, it delivers up to 71 m³/hr output at 71 bar on the rod side, or 47 m³/hr at up to 106 bar on the piston side for pumping through DN 125 pipeline runs exceeding 300 to 500 metres. Productivity is modeled by effective placement rate (m³/hr) governed by rated pump displacement, pipeline length and friction head, transit mixer turnaround, formwork capacity, and fixed allowances for pipe coupling assembly and sponge-ball washout.
High-pressure concrete placement workhorse for civil foundations, ground slabs, tunnel shotcrete, and restricted-access pours throughout Queensland and Australia.
40-80 m³/h class / Putzmeister BSA 1407 D / 106 bar max pressure / Civil estimating guide
- Civil foundation placement for continuous strip footings, pad footings, crane bases, and ground beam infrastructure
- Large-format warehouse ground slabs, industrial hardstands, apron pavements, and residential raft foundations via ground pipeline
- Controlled vertical placement into slender retaining walls, core walls, shear walls, and structural columns
- Remote or restricted-access pours exceeding 100 to 300+ metres into steep gullies, rear properties, or interior cores where boom pumps cannot set up
- Continuous supply of low-slump sprayed concrete or fiber-reinforced shotcrete to tunneling nozzles, soil nail stabilization faces, and rock batters
- High-volume structural void backfilling, micropile grout injection, precast panel grout beds, and mass concrete blinding pours
Class planning guide
Published manufacturer specifications for the Putzmeister BSA 1407 D / 40 to 80 m³/h stationary trailer concrete line pump. Use supplier specifications for exact procurement.
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 01.01 | Max pump output (rod-side) | 71 m³/h | Theoretical maximum delivery rate on cylinder rod side. |
| 01.02 | Max pump output (piston-side) | 47 m³/h | Delivery rate in high-pressure piston-side mode. |
| 01.03 | Max delivery pressure | 106 bar (10.6 MPa) | High concrete pressure for long-distance or high-vertical lines. |
| 01.04 | Engine power | 115 kW (~154 HP) | Deutz turbocharged industrial diesel engine. |
| 01.05 | Cylinder dimensions | Ø 200 mm x 1,400 mm | Twin hard-chromed delivery cylinders. |
| 01.06 | Hopper capacity | Approx. 600 L | RS 909 low-profile hopper with agitator (1.3 m filling height). |
| 01.07 | Operating weight | 4,300 kg (4.30 t) | Complete operating mass on single-axle F8 trailer chassis. |
| 01.08 | Fuel burn allowance | 11.0 to 28.0 L/hr | 17.0 L/hr likely civil duty used in planning; line pressure matters. |
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 02.01 | Restricted access | Ground pipeline delivery | Delivers concrete over 100 to 500+ metres where boom trucks cannot set up. |
| 02.02 | High-pressure capability | 106 bar piston-side | Pushes low-slump mixes and high vertical risers without booster pumps. |
| 02.03 | Long-stroke pumping | 1,400 mm stroke length | Reduces valve reversal cycles, pipe shock, and mechanical wear. |
| 02.04 | Integrated wash system | 50 L/min @ 20 bar pump | Hydraulically driven onboard water pump enables rapid sponge-ball line cleanout. |
| 02.05 | Site transport | F8 trailer chassis | Compact 5.75 m x 2.02 m footprint easily transported on tilt-tray truck. |
Dimensions and transport planning
Machine dimensions on single-axle F8 site trailer chassis. For public highway transit, transport via flatbed tilt-tray truck or drop-deck trailer complies with standard legal dimensions without NHVR oversize permits.
| Code | Dimension | Published value | Planning note |
|---|---|---|---|
| L | Overall transport length | Not verified | Measured from tip of drawbar tow ring to rear hopper step bumper. |
| W | Overall transport width | Not verified | Maximum width across trailer mudguards and tyres. |
| H | Overall transport height | Not verified | Height to highest point of engine hood and exhaust rain cap. |
| Hf | Hopper charging / filling height | 1,300 mm | Top lip of RS 909 hopper allowing gravity discharge from standard transit agitator chute. |
| Wb | Wheelbase (Tow eye to axle center) | 3,850 mm | Distance from coupling eye to trailer axle centerline. |
| Tw | Track width (outer tyre edges) | 1,850 mm | Transverse tyre stance ensuring lateral stability during site towing. |
| Gc | Ground clearance under axle | 320 mm | Clearance under lowest trailer chassis / axle component. |
| Hd | Discharge outlet centerline height | 540 mm | Centerline elevation of SK 125 concrete pressure discharge connection. |
Working range & pumping limits
Pumping performance envelope, hydraulic pressures, and delivery reach capabilities for the Putzmeister BSA 1407 D trailer concrete line pump. Allow for pipeline friction loss, concrete mix slump, vertical hydrostatic head, and coupling resistance.
| Code | Performance / range item | Published value |
|---|---|---|
| 1 | Maximum theoretical concrete output (rod-side) | 71 m³/h (High-volume setting for large industrial ground slabs and bulk footings) |
| 2 | Maximum theoretical concrete output (piston-side) | 47 m³/h (High-pressure setting for long-distance lines or steep vertical rises) |
| 3 | Maximum delivery pressure on concrete (piston-side) | 106 bar (10.6 MPa / 1,537 psi for pipeline runs exceeding 300 to 500 m) |
| 4 | Maximum delivery pressure on concrete (rod-side) | 71 bar (7.1 MPa / 1,030 psi for medium pipeline setups up to 150 to 200 m) |
| 5 | Theoretical maximum horizontal pumping distance | 500 m+ (Achievable through DN 125 pipeline with low friction and slump >120 mm) |
| 6 | Theoretical maximum vertical pumping distance | 150 m+ (Equivalent vertical lift for high-rise or deep shaft construction) |
| 7 | Maximum aggregate size | 40 mm (1.5" civil concrete passes freely through Ø 200 mm cylinders and S-tube) |
| 8 | Concrete slump capability range | 60 mm to 220 mm (Low-slump mixes up to self-compacting concrete and shotcrete) |
| 9 | Hopper volumetric capacity | approx. 600 L (RS 909 receiving hopper with integrated agitator paddles) |
| 10 | Delivery line diameter | DN 125 (5.5" grooved clamp coupling pipeline and heavy-duty placement hose) |
Direct cost and market hire prices
Never invent hire rates. In strict accordance with Vaultix estimating governance, all hire rate figures for this stationary trailer concrete line pump class are recorded as not-yet-quoted placeholders. Enter verified project supplier quotes in the calculator below.
Metro and Remote direct costs
| Basis / AUD ex GST | Metro | Remote |
|---|---|---|
| Direct dry / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Direct wet / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Line pump operator and line hand crew / paid site hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Delivered diesel / L | 1.94 (reference proxy) | 2.23 (reference proxy) |
| Maintenance, parts and freight | Base allowance | Base plus 25% |
| Roster and camp | Metro working-week roster | 14/7 FIFO, 12-hour days, camp and flights |
Standing decision: Rates for this class have not yet been quoted or audited for vaultix.com.au. To ensure estimating integrity, rates are never estimated from other classes without supplier evidence. Estimators can input their project quotes directly in the instrument below.
Mobilisation, separate one-off cost
| Purchased transport / AUD ex GST | Metro | Remote |
|---|---|---|
| One delivery event | To be quoted by haulier | To be quoted by haulier |
Purchased tilt-tray transport or site-towing mobilisation depends on transit distance, road permits, and carrier availability. No NHVR oversize permit required for legal freight dimensions. Allow separate return demobilisation event.
| Source / date | Hire basis | Per hour | Per day | Per week | Conditions |
|---|---|---|---|---|---|
| Awaiting supplier tender verification Status: Unquoted placeholder |
Dry / Wet pending quotes | Not yet quoted | Not yet quoted | Not yet quoted | All hire rate values are unquoted placeholders. When procuring trailer concrete line pumps in Australia, solicit formal quotations covering wet/dry basis, minimum hire hours (typically 4 hrs), pipeline length included, delivery/towing charges, priming slurry supply, and line hand / offsider crew. |
First-principles direct hourly cost
| Component | Direct dry AUD/hr | Direct wet AUD/hr |
|---|---|---|
| Ownership: depreciation, finance and capital return | Not yet quoted | Not yet quoted |
| Insurance and registration | Not yet quoted | Not yet quoted |
| Maintenance, pipeline wear, valve servicing and seals | Not yet quoted | Not yet quoted |
| Fuel and operating lubricants (17.0 L/hr proxy) | 0.00 | Not yet quoted |
| Line pump operator and line hand crew per site hour | 0.00 | Not yet quoted |
| Direct cost per operating hour | Not yet quoted | Not yet quoted |
Placeholder. Replace with a current supplier quote; no hire rates are invented or assumed.
Productivity and calculator
Effective Placement Rate (m³/hr) = Rated Pump Output (m³/hr) × Operational Efficiency, hydraulically limited by pipeline length and vertical static head back-pressure. Pipeline Setup Time (hr) = Base Pump Setup (0.50 hr) + [Setup Rate (1.0 to 1.5 min/m) × Pipeline Length (m) / 60]. Total Pour Duration (hr) = [Net Pour Volume (m³) / Effective Placement Rate (m³/hr)] + Pipeline Setup Time (hr) + Wash-Out Time (hr). Efficiency factor accounts for transit mixer turnaround (4–8 min), rebar congestion, testing hold points, vibrator consolidation pacing, and manual line relocation. All factors are Vaultix estimating assumptions.
Activity estimating guides
Vaultix estimating standards, 10 November 2026. Joint planning scenarios, not statistical confidence limits.
Low: rated output × 0.85, efficiency × 0.80, setup/washout × 1.25. High: rated output × 1.15 (cap 71 m³/h), efficiency × 1.10 (cap 1.00), setup/washout × 0.85.
01Footing and strip pours
Civil foundation concrete placement for continuous strip footings, pad footings, crane bases, and ground beam infrastructure where the trailer pump discharges through 30–80 m of ground pipeline.
Vaultix assumptions: Rated output 50 m³/hr; efficiency 58%; pipeline length 50 m; setup time 45 min; wash-out time 45 min.
Worked example: 50 m³/hr × 0.58 efficiency = 29.0 m³/hr effective placement rate. A 100 m³ footing pour requires (100 / 29.0) + 1.5 hr setup/washout = 4.9 hours.
Allow for: Trench access, concrete vibrator consolidation rate, moving the flexible delivery hose along the trench line, and priming slurry pump-through.
Pitfalls: Trench edge instability from pipeline weight; pipe coupling blowouts if safety pins omitted; hose kink restrictions at trench bends.
02Slab on ground via pipeline
Large-format warehouse ground slabs, industrial hardstands, apron pavements, and residential raft foundations placed using 40–120 m of DN 125 ground pipeline.
Vaultix assumptions: Rated output 60 m³/hr; efficiency 68%; pipeline length 75 m; setup time 55 min; wash-out time 50 min.
Worked example: 60 m³/hr × 0.68 efficiency = 40.8 m³/hr effective placement rate. A 200 m³ ground slab pour requires (200 / 40.8) + 1.75 hr setup/washout = 6.7 hours.
Allow for: Paced by laser screed progression, agitator swap intervals, and progressive pipe disassembly (breaking back 3 m pipes as the pour retreats).
Pitfalls: Agitator truck delivery delays causing line stall; joint delamination if pour pace falls behind laser screeding; slurry spillage during pipe disconnects.
03Wall and column pours
Controlled vertical concrete placement into slender retaining walls, core walls, shear walls, and structural columns.
Vaultix assumptions: Rated output 32 m³/hr; efficiency 48%; pipeline length 60 m; setup time 50 min; wash-out time 50 min.
Worked example: 32 m³/hr × 0.48 efficiency = 15.4 m³/hr effective placement rate. An 80 m³ core wall pour requires (80 / 15.4) + 1.67 hr setup/washout = 6.9 hours.
Allow for: Throttle reduced to control hydrostatic concrete head inside formwork; controlled 500–800 mm lift layers; intensive immersion needle vibration.
Pitfalls: Formwork hydrostatic bursting blowout from rapid vertical pour rates; honeycombing around dense reinforcement; pipe coupling movement on scaffolding.
04Remote or restricted-access pours
Long-distance concrete delivery over 100 to 300+ metres into steep gullies, rear properties, pedestrian laneways, or interior building cores where boom pumps cannot set up.
Vaultix assumptions: Rated output 38 m³/hr; efficiency 52%; pipeline length 180 m; setup time 100 min; wash-out time 80 min.
Worked example: 38 m³/hr × 0.52 efficiency = 19.8 m³/hr effective placement rate. A 60 m³ remote gully pour requires (60 / 19.8) + 3.0 hr setup/washout = 6.0 hours.
Allow for: High-pressure piston-side connection utilized (up to 106 bar) to overcome high line friction; manual line handling across rough terrain; coordinated two-way radio signalling.
Pitfalls: Severe line blockage from aggregate pack-off over long distances; extreme line kick on unanchored bends; extended cleanout cycle.
05Shotcrete feed
Continuous supply of low-slump sprayed concrete or fiber-reinforced shotcrete to underground tunneling nozzles, soil nail stabilization faces, and rock batters.
Vaultix assumptions: Rated output 18 m³/hr; efficiency 60%; pipeline length 80 m; setup time 45 min; wash-out time 45 min.
Worked example: 18 m³/hr × 0.60 efficiency = 10.8 m³/hr effective placement rate. A 40 m³ slope stabilization shift requires (40 / 10.8) + 1.5 hr setup/washout = 5.2 hours.
Allow for: Synchronized with robotic manipulator arm or manual nozzleman spraying pace and accelerator dosing; continuous hopper agitation.
Pitfalls: Rapid flash-setting chemical accelerators backing into line; pulsation disrupting uniform spray pattern; rebound accumulation around pipe couplings.
06Grout and mass fill
High-volume structural void backfilling, micropile grout injection, precast panel grout beds, and mass concrete blinding pours.
Vaultix assumptions: Rated output 48 m³/hr; efficiency 65%; pipeline length 60 m; setup time 40 min; wash-out time 35 min.
Worked example: 48 m³/hr × 0.65 efficiency = 31.2 m³/hr effective placement rate. A 150 m³ void fill pour requires (150 / 31.2) + 1.25 hr setup/washout = 6.1 hours.
Allow for: Continuous rapid pumping for fluid grouts and mass fill; stationary line feeding directly into void injection ports or tremie pipes.
Pitfalls: Formwork uplift or blowout under fluid grout hydrostatic head; line segregation with highly fluid mixes if flow stops.
07Suspended slab and vertical riser
Elevated structural concrete placement for multi-storey decks, transfer slabs, and podium floors pumped via high-pressure vertical riser pipeline (30–60 m vertical head) and flexible distribution lines.
Vaultix assumptions: Rated output 45 m³/hr; efficiency 55%; pipeline length 100 m; vertical head 35 m; setup time 65 min; wash-out time 55 min.
Worked example: 45 m³/hr × 0.55 efficiency = 24.8 m³/hr effective placement rate. A 120 m³ suspended slab pour requires (120 / 24.8) + 2.0 hr setup/washout = 6.8 hours.
Allow for: Deck distribution line handling, riser anchor bracket inspections, vertical head back-pressure, and sponge-ball catch basket at bottom dump valve.
Pitfalls: Concrete rollback in vertical riser if shutoff valve fails; excessive pressure spike on unanchored elbows; formwork deck overload from line weight.
Estimator checks
- AS 2550.15 Compliance: Equipment must be operated, inspected, and maintained in accordance with AS 2550.15 (Concrete placing equipment) and AS 1418.15. Mandatory daily pre-starts, 6-monthly periodic assessments, and logbook maintenance are required.
- Pipeline Pressure Rating: All delivery pipes, bends, reducers, and couplings must be rated to withstand maximum pump pressure (106 bar / 10.6 MPa). Every clamp coupling must be fitted with an approved safety locking pin or clip.
- Pipeline Setup Allowance: Allow 1.0 to 1.5 minutes per linear metre for carrying 3-metre pipe sections, fitting gaskets, latching SK clamps, and inserting safety pins, plus 30 minutes base pump setup.
- Whip Restraint & Hose Safety: Flexible delivery end hoses must be secured with safety whip-checks at rigid-to-rubber transition joints, and must not exceed manufacturer maximum lengths (typically 4.0 to 5.0 m) to prevent dangerous whipping.
- High-Pressure Blowout Hazards: Water washout via the onboard 50 L/min 20 bar pump and sponge ball is the preferred method. Compressed air blowout carries extreme explosion hazards and must follow CPAA guidelines with approved catchment skips.
- Environmental Washout: Concrete wash water is highly alkaline (pH 11–13). Zero discharge to stormwater drains or waterways; all washout must discharge into an impervious environmental wash skip or lined bin.
- Transport Mobilisation: The standard F8 site trailer has a mass of 4,300 kg (5.75 m L x 2.02 m W x 2.37 m H) and is designed for site towing. Mobilisation on public highways is typically via tilt-tray truck or drop-deck float (no NHVR oversize permit required).
- All hire rate schedules are unquoted placeholders. In accordance with Vaultix estimating principles, never invent hire rates without formal supplier tenders.
- No HRWL class required; operator competency confirmed by verified plant operational qualification (VOC), White Card, and CPAA line pumping certification.
Data basis. Independent check 10 November 2026 against the Putzmeister BSA 1407 D sheet: output, pressure, engine, hopper, weight and outriggers matched. Not verified (not on the sheet, sources have no URL): transport length, width and height, fuel tank (130 L) and hydraulic oil volume (170 L). Reference model: Putzmeister BSA 1407 D trailer-mounted stationary concrete line pump (powered by a 115 kW Deutz diesel engine, mounted on a single-axle F8 site trailer chassis with 4 mechanical outrigger jacks). Technical specifications sourced from official Putzmeister Concrete Pumps GmbH data sheet CT 2142-25 EN (https://www.camfaud.co.uk/wp-content/uploads/2024/04/BSA1407D.pdf). Verified 10 November 2026. Fuel burn derived from Deutz BF4M 1013 engine test curves (17.0 L/hr likely). Productivity uses Vaultix concrete pumping estimating formulas. Hire rates remain unquoted placeholders pending verified tenders. Sources and assumptions.