Plant / Mid-size horizontal directional drill (100,000 lb / 45 t class)
Horizontal Directional Drilling Rig
The primary trenchless installation workhorse for major utility crossings, trunk water, gas, and power corridors throughout Queensland and Australia.
- Feed carriageTrack pilot, reaming and pullback as distinct operations.
- Drill rodsInclude rod changes and handling in the cycle.
- Anchor systemAllow for rig positioning and setup at the entry point.
- Thrust & pullback
- 444.8kN
- Spindle torque
- 18,982Nm
AUD ex GST. *Unquoted placeholder. In accordance with Vaultix estimating principles, hire rates are never invented or extrapolated. Obtain current supplier quotations.
Choosing this class of directional drill
A 100,000 lb (45-tonne) thrust and pullback horizontal directional drilling (HDD) rig is the benchmark mid-to-heavy trenchless machine deployed across Australian civil and utility infrastructure for installing DN 100 to DN 630 steel, HDPE, and ductile iron pressure pipelines beneath waterways, highways, rail corridors, and urban utility alignments in accordance with AS 4799 and ASTT guidelines. Powered by a 205 kW (275 hp) Caterpillar C7.1 ACERT twin-turbocharged diesel engine, the self-contained crawler rig features dual rack-and-pinion carriage drive delivering 444.8 kN thrust and pullback, 18,981.5 Nm rotary torque, an onboard 870.6 L/min Kerr triplex mud pump, an integrated knuckleboom rod-handling crane, and DigiTrak touchscreen locating telemetry. Productivity is modeled across four sequential phases: steerable pilot boring (m/day), progressive multi-pass back-reaming (m/day), continuous product pipe pullback, and site mobilisation/anchoring setup.
The primary trenchless installation workhorse for major utility crossings, trunk water, gas, and power corridors throughout Queensland and Australia.
100,000 lb (45 t) class / 444.8 kN thrust & pullback / Self-contained crawler HDD / Civil estimating guide
- Steerable pilot boring and pipeline installation beneath major highways, motorways, and rail corridors with zero traffic disturbance in accordance with AS 4799
- Watercourse, river, canal, and tidal estuary crossings installing continuous DN 100 to DN 630 steel, HDPE, and ductile iron pressure conduits beneath bed scour lines
- Urban and suburban utility infrastructure crossings traversing beneath congested buried electrical, water, telecommunications, and high-pressure gas networks
- Long-distance trenchless trunk infrastructure crossings (up to 800 m continuous single shot) for bulk water, sewer rising mains, and gas transmission lines
- Installation of multi-conduit bundles for power transmission (substations, renewable wind/solar feeder lines) and high-density telecommunications / NBN fiber corridors
- Trenchless installations in sensitive environmental reserves, coastal dunes, national parks, and contaminated ground where open-cut trenching is prohibited
- Precision grade gravity sewer alignments where strict line and grade tolerances are maintained using walkover or wireline steering systems
Class planning guide
Published manufacturer specifications for the Vermeer D100x140 S3 Navigator® / 100,000 lb (45 t) class horizontal directional drill. Use supplier specifications for exact procurement.
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 01.01 | Thrust & pullback force | 444.8 kN (100,000 lb) | Carriage forward thrust and pullback force delivered by dual rack-and-pinion drive motors. Source: https://www.vermeer.com/pipeline-directional-drills/d100x140-s3 p. 2. |
| 01.02 | Spindle torque & speed | 18,982 Nm / up to 203 rpm | 14,000 ft-lb peak rotary torque in low gear; 203 rpm high-speed boring. Source: https://www.vermeer.com/pipeline-directional-drills/d100x140-s3 p. 2. |
| 01.03 | Engine power (SAE J1995 / ISO 9249) | 205.1 kW gross / 193.9 kW net (275 / 260 hp) | CAT diesel (model not stated on the Vermeer page) @ 2,200 rpm; net power is Derived: 205.1 kW gross less ~5.5% parasitic loads = 193.9 kW. Source: https://www.vermeer.com/pipeline-directional-drills/d100x140-s3 p. 2. |
| 01.04 | Onboard mud pump | 870.6 L/min @ 75.8 bar (230 gpm @ 1,100 psi) | Kerr triplex piston mud pump delivering 52.2 m³/hr for cuttings flushing and reaming. Source: https://www.vermeer.com/pipeline-directional-drills/d100x140-s3 p. 2. |
| 01.05 | Drill rod standard | 6.10 m (20 ft) Firestick #1000 | Forged 4145 alloy steel stem, 88.9 mm OD body, 112 kg/rod, 60 m min design bend radius. Source: https://www.vermeer.com/pipeline-directional-drills/d100x140-s3 p. 3. |
| 01.06 | Breakout vise & tooling opening | 27,116 Nm / 203.2 mm (8.0 in) | Open-top angled dual-clamp breakout vise for uncoupling seized downhole tooling. Source: https://vermeeraustralia.com.au/product/horizontal-directional-drills/mid-size-directional-drills/d100x140-s3-directional-drill/ p. 2. |
| 01.07 | Fuel & DEF tank capacities | 435.3 L / 37.9 L | 435.3 L diesel providing 10–14 operating hours; 37.9 L DEF tank for Tier 4 Final SCR system. Source: https://www.vermeer.com/pipeline-directional-drills/d100x140-s3 p. 2. |
| 01.08 | Fuel burn allowance | About 24 to 46 L/hr (34.0 L/hr proxy) | Derived: 205 kW x 0.58 load factor x 220 g/kWh / (835 g/L diesel density) = 31.3 L/hr + auxiliary pump losses (~2.7 L/hr) = 34.0 L/hr. Source: Caterpillar C7.1 ACERT fuel consumption map. |
| 01.09 | Base & equipped operating mass | 23,814 kg shipping mass (20-ft rod); 25,955 kg with cab option | The Vermeer page lists 52,500 lb (23,814 kg) as the weight and 57,220 lb (25,955 kg) with the cab option for the 20-ft rod. A fully equipped operating mass is not stated. Source: https://www.vermeer.com/pipeline-directional-drills/d100x140-s3 p. 1. |
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 02.01 | Pipeline crossings | DN 100 to DN 630 pipelines | Installs steel, HDPE, and ductile iron pressure mains beneath rivers, rail and motorways. |
| 02.02 | Bore spans | 300 m to 800 m single drives | Continuous single-shot drilling span governed by mud circulation volume and ground friction. |
| 02.03 | Reaming capacity | Up to 900 mm (36 in) hole size | Multi-pass hole enlargement using flycutter, fluted, or barrel reamers in stable soils. |
| 02.04 | Onboard crane | Knuckleboom (2.3 t capacity) | Wireless remote knuckleboom crane handles 112 kg drill rods and heavy back-reamers. |
| 02.05 | Transport | Low-loader float (NHVR Class 1) | 2.59 m transport width travels under NHVR Class 1 Oversize Notice with warning signs and flags. |
Dimensions and transport planning
Machine dimensions exclude the transport float trailer. Obtain verified deck height, loaded envelope, axle group weights, route clearance and restraint plans from haulier before mobilisation.
| Code | Dimension | Published value | Planning note |
|---|---|---|---|
| A | Overall transport length (20-ft rod setup) | 11,095 mm | Minimum transport length from carriage rear to front stakedown frame. |
| B | Overall transport length (15-ft rod setup) | 9,570 mm | Compact carriage configuration for restricted transport length. |
| C | Overall transport width (outer track pads) | 2,591 mm | Exceeds 2.50 m general access by 91 mm; requires NHVR Class 1 Oversize travel. |
| D | Overall transport height (to cab roof) | 3,505 mm | Height to top of ROPS/FOPS enclosed cab. Loaded on 900 mm drop-deck yields 4.35 m travel height. |
| E | Ground clearance beneath belly pan | 380 mm | Clearance beneath undercarriage belly pan for ramp breakover and site tramming. |
| F | Crawler track contact length on ground | 3,450 mm | Track ground contact length supporting 85.0 kPa ground bearing pressure. |
| G | Crawler track shoe pad width | 400 mm | Steel track shoes with bolt-on polyurethane street pads to protect pavement. |
| H | Vise clamp throat opening | 203 mm | Open-top angled vise opening for tool joints, mud motors, reamers and swivels. |
| I | Maximum auxiliary knuckleboom crane reach | 5,330 mm | Horizontal reach with 1,179 kg hook rating at maximum outreach. |
| J | Standard drill stem unit length (Firestick #1000) | 6,096 mm | Forged 4145 alloy steel one-piece drill stem segment (112 kg per rod). |
| K | Minimum borehole design curve radius | 60,000 mm | Minimum allowable borehole bend radius (60.0 m) to preserve drill stem fatigue life. |
| L | Maximum allowable bore entry angle | 24 degrees | 4-bar linkage rack adjustment range from 11° to 24° (44.5% grade) with tracks flat. |
Working range & kinematics
Thrust, pullback, rotary torque, fluid pumping rates, and borehole geometric limits. Allow for geotechnical ground resistance, hydrofracture pressure, and drill stem fatigue endurance.
| Code | Kinematic range item | Published value |
|---|---|---|
| 1 | Maximum single bore distance (typical ground) | 800 m (300 to 800 m) |
| 2 | Maximum back-reamed borehole diameter | 900 mm (35.4 in) |
| 3 | Installed product pipe diameter (DN 100 to DN 630) | 630 mm (DN 630 OD) |
| 4 | Minimum borehole curve radius (Firestick #1000) | 60.0 m (197 ft / 60,000 mm) |
| 5 | Maximum onboard mud pump flow rate (Kerr triplex) | 870.6 L/min (230 gpm @ 75.8 bar) |
| 6 | Maximum continuous carriage thrust & pullback force | 444.8 kN (100,000 lb) |
| 7 | Maximum rotary spindle torque (low range) | 18,982 Nm (14,000 ft-lb @ 2,200 rpm) |
| 8 | Bore entry angle range (11° to 24°) | 11° to 24° (19.4% to 44.5% grade) |
| 9 | Maximum auxiliary crane reach | 5,330 mm (17.5 ft) |
| 10 | Maximum crane lift capacity at 2.38 m radius | 2,300 kg (5,070 lb) |
| 11 | Onboard drill rod box capacity (stacked 18 rods) | 109.7 m (360 ft / 18 x 20-ft rods) |
| 12 | Breakout vise maximum tooling opening | 203 mm (8.0 in throat) |
Direct cost and market hire prices
Never invent hire rates. In strict accordance with Vaultix estimating governance, all hire rate figures for this 100,000 lb (45 t) horizontal directional drill class are recorded as not-yet-quoted placeholders. Enter verified project supplier quotes in the calculator below.
Metro and Remote direct costs
| Basis / AUD ex GST | Metro | Remote |
|---|---|---|
| Direct dry / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Direct wet / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Directional drilling crew / paid site hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Delivered diesel / L | 1.94 (reference proxy) | 2.23 (reference proxy) |
| Maintenance, parts and freight | Base allowance | Base plus 25% |
| Roster and camp | Metro working-week roster | 14/7 FIFO, 12-hour days, camp and flights |
Standing decision: Rates for this class have not yet been quoted or audited for vaultix.com.au. To ensure estimating integrity, rates are never estimated from other classes without supplier evidence. Estimators can input their project quotes directly in the instrument below.
Mobilisation, separate one-off cost
| Purchased transport / AUD ex GST | Metro | Remote |
|---|---|---|
| One delivery event | To be quoted by haulier | To be quoted by haulier |
Float mobilisation depends on transport distance, NHVR Class 1 Oversize permits (for 2.59 m transport width), support flatbeds for drill stem and mud recycling equipment, and float deck availability. Allow separate return demobilisation event.
| Source / date | Hire basis | Per hour | Per day | Per week | Conditions |
|---|---|---|---|---|---|
| Awaiting supplier tender verification Status: Unquoted placeholder |
Dry / Wet pending quotes | Not yet quoted | Not yet quoted | Not yet quoted | All hire rate values are unquoted placeholders. Obtain 3 dated project rate cards including drill rod package, tooling wear terms, mud system inclusions, fuel inclusion and float costs. |
First-principles direct hourly cost
| Component | Direct dry AUD/hr | Direct wet AUD/hr |
|---|---|---|
| Ownership: depreciation and interest | Not yet quoted | Not yet quoted |
| Insurance and site compliance registration | Not yet quoted | Not yet quoted |
| Maintenance, servicing, drill rods and tooling wear | Not yet quoted | Not yet quoted |
| Diesel fuel, hydraulic oils and drilling fluids / bentonite (34.0 L/hr proxy) | 0.00 | Not yet quoted |
| Directional drilling crew cost per paid site hour | 0.00 | Not yet quoted |
| Direct cost per operating hour | Not yet quoted | Not yet quoted |
Placeholder. Replace with a current supplier quote; no hire rates are invented or assumed.
Productivity and calculator
Daily Pilot Advance (m/day) = Penetration Rate (m/hr) x Productive Drilling Hours per Shift x Steering & Connection Efficiency. Reaming Duration per Pass (days) = Bore Length (m) / (Reaming Speed m/hr x Reaming Hours per Shift x Fluid Pumping Efficiency). Pipe Pullback Duration (hours) = Bore Length (m) / (Pullback Speed m/min x 60). Total Days per Bore = Rig Mobilisation & Anchor Setup (1–2 days) + Pilot Bore Days + Total Reaming Days + Pipe Pullback Days + Demobilisation & Mud Disposal (1–2 days). All production rates and correction factors are Vaultix estimating assumptions.
Activity estimating guides
Vaultix HDD estimating model, 9 November 2026. Joint trenchless directional drilling scenarios, not statistical confidence limits.
Pilot penetration: low 12 m/hr (dense gravel/rock), likely 26 m/hr (medium ground), high 42 m/hr (soft clay/sand). Reaming speed: low 8 m/hr, likely 18 m/hr, high 32 m/hr. Pullback speed: low 1.5 m/min, likely 3.2 m/min, high 5.0 m/min.
01Pilot bore
Steerable pilot hole boring along designed 3D alignment using 127 mm slant-face bit or mud motor, transmitter sonde housing, and walkover locator / wireline steering.
Vaultix assumptions: Pilot advance rate 26.0 m/hr; 180 m bore length; shift drilling hours 7.0; steering and connection efficiency 70%.
Worked example: 26.0 m/hr x 7.0 drilling hours x 0.70 efficiency = 127.4 m/day advance rate (~1.4 days pilot bore duration for 180 m shot).
Allow for: Rod loading cycles (3.8 mins per 6.1 m Firestick rod), locator tracker sync, pitch/roll survey readings, drilling fluid mixing, and steering orientation adjustments.
Pitfalls: Steering deviation in mixed cobble ground; excessive thrust causing drill rod over-deflection below 60 m bend radius; lost circulation in fractured porous ground.
02Back-reaming
Progressive rotary hole enlargement using flycutter, fluted, or barrel reamers with high-pressure bentonite slurry circulation to expand borehole to design diameter.
Vaultix assumptions: Reaming speed 18.0 m/hr; 180 m bore; 2 enlargement passes; shift hours 7.0; fluid pumping efficiency 65%.
Worked example: 18.0 m/hr x 7.0 reaming hours x 0.65 efficiency = 81.9 m/day per pass; 180 m bore requires ~2.2 reaming days per pass (~4.4 days for 2 passes).
Allow for: 150 to 200 mm diameter step increments per pass (e.g. 400 mm pre-ream and 650 mm final ream for DN 450 pipe), mud pump flushing at 700 to 870 L/min, and rod break-out cycles.
Pitfalls: Annular cuttings packing causing high rotational torque and stuck reamer; over-pressurisation causing mud frac-out to ground surface; borehole collapse in unstable gravels.
03Pipe pullback
Continuous pullback of welded HDPE or welded steel product pipe string into the mud-lubricated reamed borehole using pulling swivel, reamer, and pulling head.
Vaultix assumptions: Pullback speed 3.2 m/min (192 m/hr); 180 m bore; tension 220 kN; continuous duration 4.5 hrs; efficiency 85%.
Worked example: 180 m bore / (3.2 m/min x 60) = ~0.94 hrs net pulling time + 3.5 hrs rod breakout cycles = 4.5 continuous hours (pullback capacity ~734 m/day).
Allow for: Pipe roller support cradles, break-away safety swivel protection, continuous uninterrupted pullback cycle, and pulling head cut-off.
Pitfalls: Stopping pullback midway causes drilling fluid to gel and static friction to spike, resulting in stuck pipe string; tensile overload exceeding safe allowable pipe yield.
04Conduit installation under roads
Trenchless installation of bundled electrical, telecommunications, or water conduits beneath arterial roads and motorways with zero traffic interruption.
Vaultix assumptions: Pilot rate 25.0 m/hr; crossing length 75.0 m; depth 4.5 m; 1 reaming pass at 16.0 m/hr; pullback 3.0 m/min; shift hours 8.0; efficiency 75%.
Worked example: 75 m crossing: pilot bore (0.5 day) + 350 mm back-ream and bundle pullback (0.9 day) + setup/demob (1.0 day) = 2.4 working days (~31.3 m/day effective completion).
Allow for: BYDA potholing at road verges, traffic guidance schemes (TGS), depth of cover checks (min 2.5 to 4.5 m below pavement), and entry/exit pit shoring.
Pitfalls: Frac-out damaging asphalt pavement or causing road heave; strike on unidentified underground services beneath highway formation.
05River / drain crossing
Long-span horizontal directional drilling crossing beneath rivers, tidal creeks, or canals with drill path designed safely below maximum 1-in-100-year bed scour depth.
Vaultix assumptions: Pilot rate 38.0 m/hr; crossing span 350.0 m; depth below scour line 8.0 m; 3 reaming passes at 20.0 m/hr; pullback 3.5 m/min; shift hours 10.0; efficiency 65%.
Worked example: Pilot bore (1.4 days) + 3 reaming passes (5.4 days) + pullback (0.4 day) + setup/demob (1.5 days) = 8.7 working days total (~40.2 m/day effective completion).
Allow for: Environmental silt booms, APWD downhole annular pressure monitoring to prevent riverbed frac-out, high-volume mud recycling setup, and extended pipe string layout.
Pitfalls: Mud frac-out into watercourse requiring immediate EPA incident reporting; borehole wash-out in coarse saturated riverbed gravels.
06Drilling fluid recycling
Closed-loop drilling fluid processing: vibrating shale shaker screening, two-stage hydrocyclone desanding/desilting, mud conditioning, and cuttings dewatering.
Vaultix assumptions: Recycler throughput 800 L/min (48 m³/hr); spoil cake solids 68%; bentonite consumption 24 kg/m; recovery 80%; shift hours 10.0; efficiency 80%.
Worked example: Processing 800 L/min returns at 80% recovery saves 384,000 L of bentonite slurry per 10-hour drilling shift, supporting up to 80 m/day continuous drilling advance.
Allow for: Bentonite and polymer batching, marsh funnel viscosity testing, sand content checks (<1%), mud transfer pumps, and haulage of dewatered drill cuttings.
Pitfalls: Blinding of shaker screens by sticky reactive clays; slurry density increasing beyond 1.25 t/m³ causing annular pressure spikes and tool wear.
07Rig mobilisation and anchor setup
Site delivery, leveling, dual stakeout auger anchor installation, entry/exit slurry containment pit excavation, and high-pressure mud manifold rigging.
Vaultix assumptions: Transport arrival, 4 ground auger stakes torqued to resist 445 kN thrust/pullback, slurry containment pit excavation, mud manifold rigging, and walkover locator calibration; shift hours 8.0; efficiency 75%.
Worked example: Rig positioning and ground anchoring (0.8 day) + mud recycling plant and rod rack rigging (0.7 day) = 1.5 working days (~120 m/day equivalent mobilization rate for 180 m bore).
Allow for: NHVR Class 1 Oversize transport permit conditions, stakeout auger installation into firm ground, DigiTrak walkover tracker calibration, and bentonite pre-mix hydration.
Pitfalls: Anchor pin slippage in soft uncompacted fill during peak pullback loads; inadequate entry pit slurry storage causing overland environmental mud spillage.
Estimator checks
- Geotechnical profile & borehole investigation: Ground conditions dictate tooling selection and penetration rates. High quartz gravels, cobbles, and hard rock require downhole mud motors and roller-cone bits; reactive clays require specialized polymer inhibition to prevent swelling and bit balling.
- Borehole reaming sequence: Back-reaming must proceed in progressive diameter steps of 150 to 200 mm per pass. For a DN 450 pipe requiring a 650 mm hole, plan minimum two passes (e.g., 400 mm and 650 mm) to maintain cuttings clearance and avoid stuck pipe.
- Drilling fluid management: The onboard Kerr mud pump delivers up to 870 L/min at 75.8 bar. For larger diameter reams (>400 mm), circulating volume demands an external mud recycling plant and vacuum tanker haulage to maintain annular velocity (>35 m/min) and prevent frac-out.
- Continuous pipe pullback rule: Once product pipe pullback commences, it must never stop until the pipe string emerges at the rig. Halting pullback allows bentonite slurry to gel and static friction to spike, risking pipe freeze downhole.
- Transport and axle loads: Overall machine width is 2.59 m (102 in), which exceeds the 2.50 m general access limit by 91 mm. Road transport requires NHVR Class 1 Oversize travel conditions (signs, flags, amber beacons). Base shipping mass is 23.8 t; fully equipped mass is 26.0 t.
- All hire rate schedules are unquoted placeholders. In accordance with Vaultix estimating principles, never invent hire rates without formal supplier tenders.
- High-risk work licence for dogging and crane operation (HRWL Class DG / RB); operator competency confirmed by VOC and RIINHB301D / RIIMPO301E.
Data basis. Independent check 10 November 2026 against the Vermeer D100x140 S3 page: 8 of 10 values matched. Corrected: transport width 2.591 m (102 in) and height 3.505 m (138 in). The engine model is not stated on the page, and a fully equipped operating mass is not given (the 25,955 kg figure is the cab option weight). Derived ground pressure and fuel burn were not checked. Reference model: Vermeer D100x140 S3 Navigator® Horizontal Directional Drill, OEM specification sheet literature code D100x140S3-SPEC (pp. 1–4) and Vermeer Australia equipment profile. Sourced 9 November 2026. Fuel uses Caterpillar C7.1 ACERT engine performance telematics proxy (34.0 L/hr medium duty). Productivity and costs are Vaultix estimating models. Hire rates remain unquoted placeholders pending verified tenders. Sources and assumptions.