Plant / 80 to 100 t rotary bored & CFA piling rig
Piling Rig (Rotary Bored / CFA)
The heavy multi-application foundation drilling rig for large-diameter bored piles, deep continuous flight auger (CFA) columns, and cased secant walls across Australian civil infrastructure.
- Rotary headGround and tooling affect penetration and cleaning time.
- MastVerify the pile position and alignment at setup.
- Crawler baseInclude travel and repositioning between pile locations.
- Rotary torque
- 282kNm
- Max drill depth
- 65.7m
AUD ex GST. *Unquoted placeholder. In accordance with Vaultix estimating principles, hire rates are never invented or extrapolated. Obtain current supplier quotations.
Choosing this class of piling rig
An 80 to 100 t class multipurpose hydraulic piling rig (such as the Bauer BG 28 H on BT 85 carrier) is the primary heavy production platform for Australian deep foundations, bridge abutments, elevated viaduct caissons, and basement retention walls. Powered by a 405 kW (543 hp) Volvo TAD 13 Stage V diesel engine delivering 1,420 L/min hydraulic flow at 350 bar, it features the KDK 280 S rotary drive (282 kNm casing torque, 250 kNm drilling torque, up to 55 rpm spin-off speed), a 330 kN effective crowd winch system (expandable to 530 kN with Crowd Plus), a 200 kN main hoist winch, and extendable crawler track frames (3.00 m transport width to 4.40 m operating gauge). The rig executes uncased Kelly drilling up to 2,500 mm diameter and 65.7 m depth, cased Kelly drilling up to 2,200 mm diameter, and continuous flight auger (CFA) piling up to 1,200 mm diameter and 27.6 m depth with 730 kN combined extraction pull. Productivity is modeled by penetration rate (m/hr), cycle times for tool excavation, cage placement, and tremie/pump concrete pours governed by geotechnical ground conditions.
The heavy multi-application foundation drilling rig for large-diameter bored piles, deep continuous flight auger (CFA) columns, and cased secant walls across Australian civil infrastructure.
80 to 100 t class / 282 kNm casing torque / Rotary bored & CFA rig / Bauer BG 28 H / BT 85
- Uncased and cased large-diameter rotary bored foundation piles (up to 2,500 mm diameter and 65.7 m depth) for bridge abutments, viaduct piers, and high-rise tower caissons
- High-speed continuous flight auger (CFA) piles (up to 1,200 mm diameter and 27.6 m depth) for industrial warehouses, commercial basements, and rail infrastructure
- Cased CFA (CCFA / front-of-wall) and double-rotary head (DKS) secant and contiguous retaining walls adjacent to sensitive existing structures and utilities
- Temporary steel casing installation (up to 2,200 mm diameter) rotated directly via the 282 kNm KDK rotary drive through collapsible gravels and water-bearing alluvial sands
- High-torque coring and rock socket excavation in high-strength rock (UCS >60 MPa) including Hawkesbury Sandstone, basalt, and granodiorite using core barrels and rock augers
- Permanent steel liner caisson installation and drill-and-drive socketing for heavy marine and river bridge foundations
- Deep foundation pile cut-offs, tension piles, and transmission tower anchor piles under AS 2159
Class planning guide
Published manufacturer specifications for the Bauer BG 28 H / 80 to 100 t class rotary bored and CFA piling rig. Use supplier specifications for exact procurement.
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 01.01 | Operating mass | 83.7 t to 103.0 t | 83.7 t basic Kelly configuration on UW 65; up to 103.0 t in heavy expansion stage on UW 80. |
| 01.02 | Rotary torque | 282 kNm casing / 250 kNm drilling | KDK 280 S rotary drive at 350 bar; expandable to 400 kNm with BTM 720 torque multiplier. |
| 01.03 | Engine output | 405 kW (543 hp) @ 1,850 rpm | Volvo TAD 1385VE turbocharged 6-cylinder diesel (EU Stage V / EPA Tier 4 Final). |
| 01.04 | Drilling dimensions | Up to 2,500 mm dia / 65.7 m depth | 2.5 m uncased / 2.2 m cased Kelly diameter; up to 65.7 m depth with 4-part Kelly bar. |
| 01.05 | CFA piling capacity | 1,200 mm dia / 27.6 m depth | Continuous flight auger tooling up to 1.2 m dia; 730 kN combined extraction pull. |
| 01.06 | Shipping mass | 59,800 kg bare / 69,700 kg w/ ballast | Carrier and folded mast without rotary drive (5.5 t) and without 9.9 t counterweight. |
| 01.07 | Fuel burn allowance | 22 to 58 L/hr (38.0 L/hr civil likely) | Derived from Volvo TAD 1385VE (405 kW) load factor profiling on BT 85 carrier with EEP. |
| 01.08 | Ground bearing pressure | 108.0 kPa to 131.2 kPa (derived) | Derived: 83.7 t on 7.602 m² contact (UW 65) = 108.0 kPa; spikes >250 kPa under crowd pull. Certified working pad required per BRE 470 / CIRIA C791. |
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 02.01 | Rotary bored caissons | Telescoping Kelly bar & bucket | Large-diameter bored piles for bridge abutments, elevated viaducts, and tower caissons. |
| 02.02 | Continuous flight auger | Single-pass CFA auger & tremie | Fast vibration-free cast-in-place piling in urban environments with hollow-stem concrete pump. |
| 02.03 | Cased secant walls | Double-rotary head (DKS) | Interlocking primary/secondary piles for watertight basement perimeter retention walls. |
| 02.04 | Hard rock sockets | High crowd pull & roller core barrels | Cores into high-strength bedrock (>60 MPa UCS) using 250 kNm continuous torque and 330 kN crowd. |
| 02.05 | Transport & access | 3.00 m retracted width, 3.40 m height | Exceeds 2.5 m general access; moves as OSOM Class 1 load across 3 to 4 float loads. |
Dimensions and transport planning
Machine dimensions exclude transport float trailers. Complete piling rig moves in modular configuration across 3 to 4 heavy haulage float loads under NHVR OSOM regulations. Obtain verified deck height, loaded envelope, axle group weights, route clearance and restraint plans from haulier before mobilisation.
| Code | Dimension | Published value | Planning note |
|---|---|---|---|
| A | Overall operating height (basic Kelly version) | 21,830 mm | Dimension 21,830 mm in OEM brochure: ground line to peak of mast head in vertical Kelly drilling configuration. |
| B | Overall operating height (with 3 m mast extension) | 24,890 mm | Dimension 24,890 mm: elevated mast height for deep 4-part Kelly bars. |
| C | Maximum operating height in CFA mode (with 10.5 m Kelly extension) | 34,600 mm | Dimension 34,600 mm: maximum vertical reach in continuous flight auger deep piling mode. |
| D | Tail swing radius | 4,300 mm | Dimension 4,300 mm: constant rear slew radius on BT 85 carrier irrespective of counterweight stack. |
| E | Drilling axis radius (center of hole to mast front) | 1,000 mm | 1,000 mm standard drill axis (1,400 mm in expansion stage for large diameter piles up to 2,500 mm). |
| F | Operating drilling reach from center of slew ring | 3,510 mm to 4,710 mm | Dimension 3,510 mm to 4,710 mm: variable operating radius on UW 65 undercarriage. |
| G | Crawler track overall ground length | 5,430 mm | Dimension 5,430 mm on UW 65 (5,500 mm on UW 80) providing stable base under heavy crowd reactions. |
| H | Undercarriage overall width (retracted) | 3,000 mm | Dimension 3,000 mm with 700 mm track shoes: retracted profile for road float transport. |
| I | Undercarriage overall width (extended) | 4,400 mm | Dimension 4,400 mm with 700 mm track shoes (4,500 mm with 800 mm; 4,600 mm with 900 mm). |
| J | Crowd sledge stroke (basic version) | 9,260 mm | Dimension 9,260 mm: basic mast carriage crowd travel stroke. |
| K | Crowd sledge stroke (with 3 m mast extension) | 18,700 mm | Dimension 18,700 mm: extended crowd travel stroke along mast guide rail. |
| L | Overall transport length (without mast extension) | 19,220 mm | Dimension 19,220 mm: bumper to folded mast head with lower mast segment and folded mast head. |
| M | Overall transport length (with 3 m folded mast extension) | 20,810 mm | Dimension 20,810 mm: shipping length with hydraulically folded 3 m mast extension. |
| N | Overall transport height (mast folded horizontal) | 3,400 mm | Dimension 3,400 mm to 3,430 mm on UW 65 (3,500 mm on UW 80): low-profile mast folded height. |
| O | Standard track shoe width | 700 mm | Dimension 700 mm: standard 3-grouser steel track pads. |
Working range & kinematics
Kinematic capabilities and geometric drilling limits for the Bauer BG 28 H piling rig across rotary bored and CFA operations. Allow for geotechnical borehole stability, ground bearing capacity, and working platform design.
| Code | Kinematic range item | Published value |
|---|---|---|
| 1 | Maximum uncased Kelly drilling diameter | 2,500 mm (2.50 m with 1,400 mm drill axis; 1,700 mm standard) |
| 2 | Maximum cased Kelly drilling diameter | 2,200 mm (2.20 m driven via KDK head; 1,400 mm standard) |
| 3 | Maximum Kelly drilling depth | 65.7 m (with 4-part Kelly BK 250/394/4/64 & 3 m mast extension) |
| 4 | Maximum continuous flight auger (CFA) diameter | 1,200 mm (1.20 m continuous flight auger tooling) |
| 5 | Maximum CFA drilling depth | 17.3 m single-pass / 27.6 m with 10.5 m Kelly extension |
| 6 | Cased CFA (CCFA / DKS) capacity | 610 mm to 750 mm dia, up to 18.3 m depth (double-rotary head) |
| 7 | Maximum crowd extraction pull capacity | 730 kN (74.4 tonnes combined main & crowd winch pull) |
| 8 | Nominal rotary torque output | 250 kNm drilling / 282 kNm casing / 400 kNm with BTM 720 |
| 9 | Mast inclination range (batter piling) | 5° forward / 15° backward / ±8° lateral |
| 10 | Operating drilling reach radius | 3,510 mm to 4,710 mm (center of slew ring to drill axis) |
Direct cost and market hire prices
Never invent hire rates. In strict accordance with Vaultix estimating governance, all hire rate figures for this 80 to 100 t piling rig class are recorded as not-yet-quoted placeholders. Enter verified project supplier quotes in the calculator below.
Metro and Remote direct costs
| Basis / AUD ex GST | Metro | Remote |
|---|---|---|
| Direct dry / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Direct wet / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Piling rig operator and dogman crew / paid site hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Delivered diesel / L | 1.94 (reference proxy) | 2.23 (reference proxy) |
| Maintenance, parts and freight | Base allowance | Base plus 25% |
| Roster and camp | Metro working-week roster | 14/7 FIFO, 12-hour days, camp and flights |
Standing decision: Rates for this class have not yet been quoted or audited for vaultix.com.au. To ensure estimating integrity, rates are never estimated from other classes without supplier evidence. Estimators can input their project quotes directly in the instrument below.
Mobilisation, separate one-off cost
| Purchased transport / AUD ex GST | Metro | Remote |
|---|---|---|
| One delivery event | To be quoted by haulier | To be quoted by haulier |
Mobilisation requires modular transport across 3 to 4 heavy low-loader and semi-trailer loads (base machine at 59.8 t and 3.00 m width, 9.9 t counterweights, 5.5 t KDK 280 rotary drive, and Kelly bars / auger tooling), NHVR Class 1 OSOM permits, route clearance, and escort vehicles. Allow separate return demobilisation event.
| Source / date | Hire basis | Per hour | Per day | Per week | Conditions |
|---|---|---|---|---|---|
| Awaiting supplier tender verification Status: Unquoted placeholder |
Dry / Wet pending quotes | Not yet quoted | Not yet quoted | Not yet quoted | All hire rate values are unquoted placeholders. When procuring 80 t to 100 t rotary bored and CFA piling rigs in Australia, solicit 3 dated project rate cards covering wet/dry basis, minimum hire tenure, heavy haulage float mobilization across 3 to 4 loads, counterweight packages, Kelly bar configuration, CFA tooling kits, and fuel inclusion/levies. |
First-principles direct hourly cost
| Component | Direct dry AUD/hr | Direct wet AUD/hr |
|---|---|---|
| Ownership: depreciation and interest | Not yet quoted | Not yet quoted |
| Insurance and registration | Not yet quoted | Not yet quoted |
| Maintenance, servicing, undercarriage and wear parts | Not yet quoted | Not yet quoted |
| Fuel and operating lubricants (38.0 L/hr piling proxy) | 0.00 | Not yet quoted |
| Piling rig operator and dogman crew per paid site hour | 0.00 | Not yet quoted |
| Direct cost per operating hour | Not yet quoted | Not yet quoted |
Placeholder. Replace with a current supplier quote; no hire rates are invented or assumed.
Productivity and calculator
Vaultix estimate: Penetration / drilling rate (m/hr) by methodology; Piles per day = (Shift hours × Efficiency) / (Drill time + Borehole cleanout + Cage installation + Concrete pour cycle h), where Drill time (h) = Pile depth / Drilling rate; Concrete volume per pile (m³) = (π × (Diameter / 2)² × Depth) × (1 + Overbreak allowance, typically 1.10 to 1.18). All factors are Vaultix civil estimating assumptions.
Activity estimating guides
Vaultix estimating standards, 10 November 2026. Joint planning scenarios, not statistical confidence limits.
Low scenario: drilling penetration rate × 0.80, auxiliary cycle times (clean, cage, pour) × 1.20, efficiency × 0.85. High scenario: drilling penetration rate × 1.15, auxiliary cycle times × 0.85, efficiency × 1.10 (capped at 1.00).
01Rotary bored piles
Deep large-diameter rotary bored piling using telescoping Kelly bar with drilling bucket or rock auger for bridge abutments, viaduct piers, and high-rise tower caissons.
Vaultix assumptions: Drilling penetration rate 12 m/hr; pile diameter 1.2 m; pile depth 22 m; cleanout 0.34 h; cage install 0.40 h; pour 0.70 h; efficiency 72%.
Worked example: Drilling duration 1.83 hr; cycle time 3.27 hr; output 2.2 piles per 10-hour shift (48.4 linear m, 62.4 m³ concrete volume at 28.4 m³/pile with 14% overbreak).
Allow for: Tool changes (soil bucket to cleanout bucket), spoil mucking with support excavator, Kelly bar extension/retraction cycles, casing alignment checks, reinforcement cage placement, and tremie concrete pouring.
Pitfalls: Borehole wall collapse in loose saturated sands; overbreak volume in soft strata; delayed concrete delivery causing cold joints or necking in the pile shaft.
02CFA piles
High-speed continuous flight auger (CFA) piling: continuous rotary penetration followed by simultaneous extraction with positive-pressure concrete delivery pumped through the hollow stem, followed by reinforcement cage plunge.
Vaultix assumptions: Auger drilling rate 25 m/hr; pile diameter 0.6 m; pile depth 16 m; cleanout 0.05 h; cage plunge 0.15 h; hollow-stem pour 0.10 h; efficiency 75%.
Worked example: Drilling duration 0.64 hr (38.4 min); cycle time 0.94 hr (56.4 min); output 8.0 piles per 10-hour shift (128 linear m, 41.3 m³ concrete volume at 5.2 m³/pile with 14% overbreak).
Allow for: Continuous concrete pump agitator coordination, auger cleaner spoil scraping, mast swan-neck hose positioning, cage vibrator plunge assist, and pile cut-off trimming.
Pitfalls: Pumping interruption during extraction leading to pile flighting necking or voids; over-rotation causing flighting ground decompression and surface settlement; cage plunge refusal in stiff concrete.
03Cased (temporary casing) piles
Rotary installation and extraction of sectional temporary steel casings using the KDK 280 rotary head or casing oscillator to seal off water-bearing gravels and unstable overburden.
Vaultix assumptions: Casing drive & boring rate 8.0 m/hr; casing diameter 1.3 m; total pile depth 22 m; cleanout 0.30 h; cage install 0.35 h; pour & casing extract 0.60 h; efficiency 68%.
Worked example: Drilling & casing duration 2.75 hr; cycle time 4.00 hr; output 1.7 piles per 10-hour shift (37.4 linear m, 56.6 m³ concrete volume at 33.3 m³/pile with 14% overbreak).
Allow for: Casing joint pinning/bolting, casing shoe cutting friction, high-torque rotary oscillation, internal grab/bucket mucking, and synchronized casing extraction during concrete pour.
Pitfalls: Casing binding or seizure due to prolonged concrete setup time or friction build-up; excessive casing torque damaging rig mast; lifting casing too fast causing concrete lift-up.
04Secant / contiguous pile walls
Construction of perimeter retaining walls consisting of interlocking primary (unreinforced or soft concrete) and secondary (reinforced structural concrete) bored or CCFA piles.
Vaultix assumptions: Wall pile boring rate 16 m/hr; wall pile diameter 0.75 m; wall depth 18 m; cleanout 0.125 h; cage install 0.20 h; pour 0.30 h; efficiency 70%.
Worked example: Drilling duration 1.125 hr; cycle time 1.75 hr; output 4.0 piles per 10-hour shift (72 linear m, 36.3 m³ concrete volume at 9.1 m³/pile; 2.6 m linear wall advance at 0.65 m pile pitch).
Allow for: Guide-wall construction, precise verticality survey monitoring (plumb within 1:150), over-coring into primary piles, and heavy support crane handling of full-depth reinforcement cages.
Pitfalls: Verticality deviation causing gap opening at depth and loss of basement waterproofing; primary concrete curing too hard before secondary coring resulting in drill head wandering.
05Pile cage installation
Handling, hoisting, vertical alignment, multi-section splicing, spacer attachment, and lowering of prefabricated reinforcing steel cages into open or cased boreholes.
Vaultix assumptions: Borehole re-check rate 50 m/hr; pile diameter 1.2 m; pile depth 20 m; cleanout 0.10 h; cage splicing & lowering 0.70 h; pour prep 0.40 h; efficiency 80%.
Worked example: Tool check duration 0.40 hr; cage handling 0.70 hr; cycle time 1.60 hr; output 5.0 cage installations per 10-hour shift (100 linear m, 128.9 m³ concrete equivalent at 25.8 m³/pile).
Allow for: 35t–50t crawler crane or piling rig auxiliary winch, certified spreader bar, cage stiffener rings, NMB mechanical splices or certified lap welding, concrete roller spacers, and cage suspension hanging beams.
Pitfalls: Cage distortion or collapse during upending; cage buoyancy/floating during concrete pour; snagging on borehole sidewall or temporary casing joint.
06Rock sockets
Precision coring and excavation of structural load-bearing sockets into medium- to high-strength competent bedrock (UCS 25 to 120+ MPa) using core barrels and rock augers.
Vaultix assumptions: Rock coring penetration rate 1.8 m/hr; socket diameter 1.05 m; socket depth 3.5 m in 60 MPa bedrock; cleanout 0.25 h; cage stub 0.20 h; plug pour 0.30 h; efficiency 65%.
Worked example: Coring duration 1.94 hr; cycle time 2.69 hr; output 2.4 rock sockets per 10-hour shift (8.4 linear m socket depth, 8.3 m³ high-strength concrete at 3.5 m³/socket; approx. 6 tungsten carbide pick replacements per socket).
Allow for: Round-shank tungsten carbide picks and roller-cone cutter wear, core extraction lifting rings, high crowd thrust (up to 423 kN), high rotary torque (250 kNm), and rock socket roughness logging per AS 2159.
Pitfalls: Excessive pick wear and thermal damage in abrasive sandstone/granite; core barrel jamming in fractured rock mass; core stub breakout failure requiring reverse circulation or breaker intervention.
07Cased CFA (CCFA) piles
Double-rotary cased continuous flight auger (CCFA) installation using twin counter-rotating heads (e.g. Bauer DKS 100/200) advancing outer casing and inner auger simultaneously for vibration-free perimeter retention piles adjacent to sensitive structures.
Vaultix assumptions: Double-rotary penetration rate 14 m/hr; casing diameter 0.75 m; pile depth 17 m; cleanout & seating 0.10 h; cage plunge 0.25 h; pumping & casing extraction 0.44 h; efficiency 70%.
Worked example: Simultaneous drilling duration 1.21 hr; cycle time 2.00 hr; output 3.5 piles per 10-hour shift (59.5 linear m, 30.0 m³ concrete volume at 8.6 m³/pile with 14% overbreak).
Allow for: Counter-rotating drive synchronization, continuous agitator flow to hollow stem, outer casing torque monitoring (up to 200 kNm), and mechanical cage vibrator insertion.
Pitfalls: Differential torque stall between casing and inner auger in gravel lenses; concrete bleed-water escaping through casing joints; premature concrete set prior to full casing extraction.
Estimator checks
- Working platform certification: With an operating weight of 83.7 t to 103.0 t and static ground bearing pressures of 108 kPa to 132 kPa (spiking over 250 kPa under dynamic crowd extraction or sudden tool breakout), a certified piling platform designed per BRE 470 / CIRIA C791 and AS 5100 is strictly mandatory before mobilization.
- Borehole stability and temporary casing: In unstable sands, alluvial silts, or high groundwater tables, specify full-depth temporary steel casing or polymer/bentonite drilling slurries. Ensure KDK casing drive adapter (up to 2,200 mm) or casing oscillator (Bauer BV 1500) is priced.
- Auxiliary support equipment: Piling production strictly requires coordinated support plant: a 35t–50t crawler crane or 30t excavator for reinforcement cage placement, casing handling, and spoil mucking, plus concrete agitators and positive-displacement trailer pump for CFA or tremie pour operations.
- Rock sockets: Penetration rates slow dramatically from 8–16 m/hr in cohesive soils to 0.8–3.0 m/hr in hard rock sockets (UCS 25–120 MPa). Budget tungsten carbide roller-cone core barrels, rock augers, and tool wear replacements.
- Transport and mobilization: Base machine moves as an Oversize/Overmass (OSOM) Class 1 load at 3.00 m width and 3.40 m height (~59.8 t) on an 8-line or 10-line low-loader. Requires 2 to 3 additional semi-trailers for counterweights (9.9 t), KDK 280 rotary head (5.5 t), Kelly bars, and auger strings.
- Overbreak allowance: Allow 10% to 18% concrete overbreak volume above theoretical borehole cylinder geometry due to shaft bulging in soft strata and ground loss.
- All hire rate schedules are unquoted placeholders. In accordance with Vaultix estimating principles, never invent hire rates without formal supplier tenders.
- Output is penetration-governed (m/hr) and cycle-governed (piles/shift), not earthmoving volume. Balance drilling output with concrete batch plant delivery and cage fabrication pacing.
- National civil plant competency / VOC (RIIMPO323E) required for rig operator; High Risk Work Licence Dogging (CPCCLDG3001A) and Support Crane (C6/CO) mandatory for piling crew.
Data basis. Independent check 10 November 2026 against the Bauer BG 28 H BT 85 sheet: all 10 key values matched. The maximum Kelly depth of 65.7 m applies to the BK 250/394/4/64 with a 3 m mast extension. Other rig models and derived values were not checked. Reference model: Bauer BG 28 H Rotary Drilling Rig (Base Carrier BT 85 / UW 65). Technical specifications sourced from official BAUER Maschinen GmbH technical brochure 905.815.2 and BT 75 brochure 905.789.2. Verified 10 November 2026. Fuel burn derived from Volvo TAD 1385VE engine telematics load factor mapping (38.0 L/hr civil foundation likely). Productivity uses Vaultix deep foundation cycle formulas. Hire rates remain unquoted placeholders pending verified tenders. Sources and assumptions.
Entry / piling-rig Issue / 2026-11-10
Library navigation
Plant and method index · Discipline work packages · Survey conformance and lot release