Plant / pipe-jacking / microtunnelling TBM with launch shaft
Sewer Microtunnelling TBM and Temporary Works
The benchmark closed-face slurry microtunnelling boring machine and pipe jacking system for precision civil sewer installations and deep shaft temporary works.
- CutterheadFace conditions and interventions affect advance.
- ShieldCheck alignment and the supported excavation envelope.
- Jacking frameInclude pipe change and thrust cycles separately.
- Shield outer diameter
- 1,505mm
- Cutter drive power
- 132kW
AUD ex GST. *Unquoted placeholder. In accordance with Vaultix estimating principles, hire rates are never invented or extrapolated. Obtain current supplier quotations.
Choosing this class of microtunnelling TBM
A closed-face slurry microtunnelling boring machine (MTBM) in the DN 1200 class is the benchmark trenchless method for deep urban gravity sewer installations, railway crossings, and sensitive environmental alignments. Utilizing a 1.505 m outer diameter articulated steering shield, high-torque full-face cutterhead with integrated eccentric cone crusher (crushing cobbles up to 450 mm), and counter-balanced pressurized slurry face support up to 3.0 bar, the machine excavates precise alignments while continuous hydraulic rams in a launch shaft jack reinforced concrete or polymer pipes behind it. Productivity is modeled by instantaneous cutter advance (m/hr) governed by rock strength and spoil circulation, adjusted by cycle efficiency (pipe jointing, umbilical extension, and laser line checks) to determine daily advance (m/day), alongside shaft construction, thrust wall reaction curing, and separation plant throughput.
The benchmark closed-face slurry microtunnelling boring machine and pipe jacking system for precision civil sewer installations and deep shaft temporary works.
DN 1200 sewer class / 1,505 mm shield OD / Slurry microtunnelling TBM / Civil estimating guide
- Precision grade gravity trunk sewer and wastewater reticulation pipelines (DN 1200) installed to sub-millimetre tolerances without surface disruption
- Railway corridor and multi-lane highway crossings where open-cut trenching is prohibited due to settlement and traffic disturbance risks
- Deep trunk drainage and stormwater culvert installation beneath congested urban utility networks and critical buried infrastructure
- Environmentally sensitive river, creek, and wetland crossings maintaining continuous pressurized face support to prevent frac-out or settlement
- Underground utility tunnels and service conduits through mixed face ground, waterbearing sands, gravels, cobbles, and hard rock formations up to 200 MPa
- Long-distance single-drive pipe jacking (>1,000 m) utilizing automated intermediate jacking stations (IJS) and continuous bentonite annulus lubrication
- Deep launch and reception shaft temporary works including caisson sinking, tremie concrete plugs, and reinforced reaction thrust blocks
Class planning guide
Published manufacturer specifications for the Herrenknecht AVN 1200 / DN 1200 class slurry microtunnelling TBM and pipe jacking system. Use supplier specifications for exact procurement.
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 01.01 | Articulated shield OD | 1,505 mm | External diameter of leading articulated steering shield. Source: Herrenknecht AVN 1200 TB sheet p. 1. |
| 01.02 | Jacking pipe size | DN 1200 (1,200 mm ID / 1,490 mm OD) | Standard reinforced concrete or polymer jacking pipe. Source: AVN 1200 TB sheet p. 1. |
| 01.03 | Cutterhead drive | 132 kW / 258 kNm torque | Electric-hydraulic motor with eccentric cone crusher. Source: AVN 1200 TB sheet p. 1. |
| 01.04 | Slurry face support | Up to 3.0 bar (30 m head) | Pressurized slurry balance counteracts earth and water pressures. Source: AVN System Brochure p. 1. |
| 01.05 | Shipping mass | 13,000 kg (bare shield) | Articulated shield module mass; trailing can ~6,500 kg (Not verified; see review table). Source: AVN 1200 TB sheet p. 1. |
| 01.06 | Site power load | 450 to 650 kVA (derived) | Derived: Sum of TBM drive (132 kW), slurry pumps (90 kW), separation plant (55 kW), jacking HPU (45 kW) and auxiliaries = ~350 kW running / 500 kVA genset burn ~65 L/hr; direct TBM diesel burn is null. Source: AVN System Brochure p. 1. |
| Ref | Item | Value | Planning note |
|---|---|---|---|
| 02.01 | Urban crossings | Zero surface disruption | Precision laser navigation and slurry face pressure prevent settlement under roads and rail. |
| 02.02 | Mixed ground | Cone crusher & interchangeable tools | Crushes gravel and cobbles up to 450 mm into pumpable slurry; soft ground picks or rock disc cutters. |
| 02.03 | Drive length | 150-250 m standard / >1,000 m with IJS | Deploy intermediate jacking stations (IJS) and continuous bentonite annulus lubrication for long drives. |
| 02.04 | Shaft temporary works | Compact vs standard jacking rig | 4.87 m min circular shaft with compact rig; 8.5 m circular / 8.0x3.5 m rectangular for full-stroke station. |
| 02.05 | Transport | General access semi-trailer float | 1.505 m OD and 13 t shield travel within 2.50 m width and standard legal axle limits without OSOM permits. |
Dimensions and transport planning
Machine dimensions exclude the transport float trailer. Obtain verified deck height, loaded envelope, axle group weights, route clearance and restraint plans from haulier before mobilisation.
| Code | Dimension | Published value | Planning note |
|---|---|---|---|
| 1 | Articulated shield outer diameter (OD) | 1,505 mm | Standard outer diameter of the front articulated steering and excavation shield. |
| 2 | Jacking pipe outer diameter (OD) | 1,490 mm | Standard external barrel diameter of DN 1200 jacking pipes matched to machine trail. |
| 3 | Jacking pipe inner diameter (ID) | 1,200 mm | DN 1200 nominal sewer pipeline bore diameter. |
| 4 | Cutterhead excavation diameter | 1,541 mm | Nominal diameter excavated by standard full-face cutter wheel gauge cutters. |
| 5 | Annular overcut thickness (radial) | 25.5 mm | Derived: (Excavation diameter 1,541 mm - pipe OD 1,490 mm) / 2 = 51 mm / 2 = 25.5 mm radial clearance for steering and bentonite lubrication. |
| 6 | Length of Articulated Shield (LAS) | 3,750 mm | Overall axial length of the front articulated steering and cutterhead shield module. |
| 7 | Length of Machine Can (LMC) | 3,200 mm | Axial length of the trailing machine can module housing hydraulic valves and utility umbilicals. |
| 8 | Combined TBM assembly length | 6,950 mm | Derived: Articulated shield length (3,750 mm) + trailing machine can length (3,200 mm) = 6,950 mm (6.95 m total in-line TBM body). |
| 9 | Minimum circular launch shaft diameter (Compact Rig) | 4,870 mm | Minimum circular shaft diameter for 2.5 m or 3.0 m jacking pipe utilizing a Compact Jacking Rig. |
| 10 | Minimum rectangular launch shaft length (Compact Rig) | 5,000 mm | Minimum rectangular shaft length (5.0 m) with Compact Jacking Rig. |
| 11 | Minimum rectangular launch shaft width (Compact Rig) | 4,500 mm | Minimum rectangular shaft width (4.5 m) with Compact Jacking Rig. |
| 12 | Minimum rectangular launch shaft length (Main Station) | 8,000 mm | Minimum rectangular shaft length (8.0 m) for standard full-stroke Main Jacking Station. |
| 13 | Minimum rectangular launch shaft width (Main Station) | 3,500 mm | Minimum rectangular shaft width (3.5 m) for standard full-stroke Main Jacking Station. |
| 14 | Minimum reception shaft diameter | 4,500 mm | Minimum clear internal diameter to safely dock cradle, disconnect, and crane-lift the 3.75 m shield. |
Working range & kinematics
Drive capacities, cutterhead torque, steering kinematics, and slurry circuit limits for the Herrenknecht AVN 1200 microtunnelling system. Allow for geotechnical conditions, rock compressive strength, groundwater head, and pipe skin friction.
| Code | Kinematic range item | Published value |
|---|---|---|
| 1 | Nominal sewer pipeline diameter | 1,200 mm (DN 1200) |
| 2 | Excavation cutting diameter | 1,541 mm |
| 3 | Annular overcut thickness (radial) | 25.5 mm (Derived: (1,541 mm - 1,490 mm) / 2 = 25.5 mm) |
| 4 | Maximum single drive length (without IJS) | 150 to 250 m |
| 5 | Maximum drive length with intermediate jacking stations (IJS) | >1,000 m (with continuous bentonite lubrication) |
| 6 | Main cutter drive rated power | 132 kW (177 hp) |
| 7 | Maximum cutterhead torque | 258 kNm |
| 8 | Maximum face support slurry pressure | 3.0 bar (300 kPa / 30 m head) |
| 9 | Minimum drive horizontal curve radius | 150 to 200 m (using 3-cylinder articulation joint) |
| 10 | Cone crusher boulder intake | 450 mm (~30% to 40% of excavation diameter) |
| 11 | Main jacking frame thrust capacity | 4,000 to 6,000 kN (400 to 600 tonnes) |
| 12 | Slurry circuit nominal flow rate | 150 to 220 m³/hr |
Direct cost and market hire prices
Never invent hire rates. In strict accordance with Vaultix estimating governance, all hire rate figures for this microtunnelling TBM and pipe jacking plant are recorded as not-yet-quoted placeholders. Enter verified project supplier quotes in the calculator below.
Metro and Remote direct costs
| Basis / AUD ex GST | Metro | Remote |
|---|---|---|
| Direct dry / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Direct wet / hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Microtunnelling specialist crew / paid site hr | Not yet quoted (placeholder) | Not yet quoted (placeholder) |
| Delivered diesel / L | 1.94 (reference proxy) | 2.23 (reference proxy) |
| Maintenance, parts and freight | Base allowance | Base plus 25% |
| Roster and camp | Metro working-week roster | 14/7 FIFO, 12-hour days, camp and flights |
Standing decision: Rates for this class have not yet been quoted or audited for vaultix.com.au. To ensure estimating integrity, rates are never estimated from other classes without supplier evidence. Estimators can input their project quotes directly in the instrument below.
Mobilisation, separate one-off cost
| Purchased transport / AUD ex GST | Metro | Remote |
|---|---|---|
| One delivery event | To be quoted by haulier | To be quoted by haulier |
Float mobilisation depends on transport distance, route permits, and craneage requirements. The 13 t MTBM shield and trailing can travel as general access freight on drop-deck floats (1.505 m OD, within 2.50 m width limit). Control container and jacking rig travel as standard freight; separation plant modules exceeding 2.50 m travel under NHVR Class 1 Oversize Notice. Allow separate return demobilisation event.
| Source / date | Hire basis | Per hour | Per day | Per week | Conditions |
|---|---|---|---|---|---|
| Awaiting supplier tender verification Status: Unquoted placeholder |
Dry / Wet pending quotes | Not yet quoted | Not yet quoted | Not yet quoted | All hire rate values are unquoted placeholders. When procuring microtunnelling TBM spreads in Australia, obtain 3 dated commercial quotations covering MTBM shield, jacking frame, separation plant, bentonite lubrication unit, control container, tooling wear terms, mobilization float transport, and specialized crew. |
First-principles direct hourly cost
| Component | Direct dry AUD/hr | Direct wet AUD/hr |
|---|---|---|
| Ownership: depreciation and interest | Not yet quoted | Not yet quoted |
| Insurance and registration | Not yet quoted | Not yet quoted |
| Maintenance, cutterhead tooling, slurry lines and pump wear | Not yet quoted | Not yet quoted |
| Generator fuel, electricity, hydraulic oil and polymers (65.0 L/hr proxy) | 0.00 | Not yet quoted |
| Microtunnelling specialist crew cost per paid site hour | 0.00 | Not yet quoted |
| Direct cost per operating hour | Not yet quoted | Not yet quoted |
Placeholder. Replace with a current supplier quote; no hire rates are invented or assumed.
Productivity and calculator
Daily Advance (m/day) = Instantaneous Advance Rate (m/hr) x Operating Hours (hrs/day) x Cycle Efficiency Factor. Total Jacking Force (kN) = Face Resistance F_face + (pi x D_outer x L_drive x f_friction). Shaft Construction Duration (days) = Depth (m) / Sinking Rate (m/day) + Shoring / Plug Curing Days. All penetration rates, cycle efficiencies, friction factors and allowances are Vaultix estimating assumptions.
Activity estimating guides
Vaultix trenchless estimating standards, 9 November 2026. Joint sewer microtunnelling scenarios, not statistical confidence limits.
Penetration rate: low 0.8 m/hr (rock/cobbles), likely 2.2 m/hr (medium ground), high 4.5 m/hr (soft silt/sand). Cycle efficiency factor: 0.50 to 0.75. Friction factor: 1.5 to 3.5 kN/m² lubricated.
01Launch shaft construction (caisson / sheet pile)
Excavation and sinking of circular reinforced concrete caisson or sheet-piled launch shaft, cast-in-place guide collar, and underwater tremie concrete plug.
Vaultix assumptions: Sinking rate 1.5 m/day; shaft diameter 6.5 m; depth 9.0 m; 1 cycle; efficiency 75%.
Worked example: 9.0 m depth / 1.5 m/day = 6.0 sinking days + 5.0 days collar and tremie plug = 11.0 working days.
Allow for: Dewatering sump pumps, clamshell/mini-excavator mucking, ring segment joint sealing, structural thrust ring, and concrete curing.
Pitfalls: Uncontrolled groundwater inflow can cause base heave, boiling, or loss of ground; verify hydrogeology and ground anchors prior to sinking.
02Jacking frame and thrust wall setup
Construction of cast in-situ reinforced concrete thrust reaction block, lowering and precision levelling of main hydraulic jacking rig, launch eye seal coring, and guidance laser installation.
Vaultix assumptions: Thrust wall 40 MPa RC curing 5 days; frame rigging and levelling 2.5 days; eye seal coring 2 days; laser guidance calibration 8 hrs.
Worked example: 5.0 days reaction block cure + 2.5 days frame setup + 2.0 days entry seal = 9.5 working days to establish launch station.
Allow for: High-strength concrete curing, anchor dowels into bedrock or caisson wall, laser target bracket surveys, and hydraulic power pack commissioning.
Pitfalls: Eccentric jacking load on inadequately cured thrust block risks shear failure or shaft distortion; alignment errors at launch propagate across entire drive.
03Microtunnel drive
Closed-face slurry microtunnelling advance with Herrenknecht AVN 1200 MTBM, mechanical cone crushing of gravel/cobbles, and laser-guided hydraulic articulated steering.
Vaultix assumptions: Instantaneous penetration rate 2.2 m/hr; 16-hour double shift; cycle efficiency 65% (accounting for pipe jointing and umbilical extensions).
Worked example: 2.2 m/hr x 16 hr/day x 0.65 cycle efficiency = 22.9 m/day advance rate. A 150 m drive requires ~6.6 mining days.
Allow for: Slurry charge/discharge line management, bentonite face balance monitoring, cutterhead tool wear inspections, and intermediate survey checks.
Pitfalls: Face collapse or over-pressurisation causing slurry frac-out to surface; cutterhead balling in high-plasticity clays requiring specialized anti-clay polymers.
04Reception shaft
Excavating and shoring downstream reception pit, bell-mouth entry seal installation, MTBM docking on receiving cradle, umbilical disconnection, and mobile crane lift-out.
Vaultix assumptions: Reception shaft depth 8.0 m, diameter 4.5 m; shaft construction 14 days; breakthrough prep and seal 2 days; TBM retrieval and demobilisation 2 days.
Worked example: 14.0 days shaft construction + 2.0 days breakthrough prep + 2.0 days retrieval = 18.0 working days total reception works.
Allow for: Breakout of shaft wall soft eye, crane lift-out of 13 t AVN shield and trailing can, reception seal compression, and shaft washdown.
Pitfalls: Ground loss around soft eye during breakthrough before sealing ring engagement; ensure dewatering or jet grout block behind wall is verified.
05Slurry separation plant
Surface closed-loop slurry treatment: dual-deck shale shaker screening of coarse gravel/cuttings, two-stage hydrocyclone desanding/desilting, and bentonite conditioning.
Vaultix assumptions: Slurry circulation flow rate 180 m³/hr; spoil separation cut point 60 microns; bentonite powder consumption 30 kg/m; dewatered cake solids 68%.
Worked example: At 180 m³/hr circulation and 68% solids recovery, separation plant processes ~2.5 m³/hr in-situ cuttings into dewatered filter cake.
Allow for: Bentonite mixing tanks, shear hopper, polymer flocculant dosing, centrifuge for ultrafine clays, and truck loading of semi-dry spoil cake.
Pitfalls: High fine silt/clay content blinding shaker screens and increasing slurry specific gravity (>1.25 t/m³); requires high-speed decanter centrifuge.
06Pipe jacking and grouting
Crane rigging and lowering DN 1200 jacking pipes, timber cushion packing, joint sealing, automated bentonite overcut lubrication, and post-drive contact cement grouting.
Vaultix assumptions: Pipe segment length 2.5 m; pipe lowering and jointing cycle 45 mins; lubricated jacking skin friction 2.2 kPa; annulus grout volume 0.22 m³/m.
Worked example: 150 m drive x 1.490 m pipe OD x pi x 2.2 kPa friction = 1,545 kN skin friction + 350 kN face force = 1,895 kN total thrust (well within 4,000 kN pipe capacity).
Allow for: Joint deflection monitoring, intermediate jacking station (IJS) spacing if force exceeds 3,500 kN, continuous bentonite annulus pumping, and tremie contact grouting.
Pitfalls: Bentonite lubrication starvation leading to friction spikes and pipe freeze; point loading on pipe collars if timber packing ring is misaligned or crushed.
07Intermediate jacking station (IJS) operation
Long-distance drive advance beyond single-drive thrust wall limits, deploying automated in-line telescopic intermediate jacking stations and distributed bentonite overcut lubrication.
Vaultix assumptions: Advance rate 1.8 m/hr; 24-hour continuous tunneling; cycle efficiency 55% (interjack sequence cycling); 400 m drive length; friction 2.8 kPa.
Worked example: 1.8 m/hr x 24 hr/day x 0.55 = 23.8 m/day advance. Unassisted thrust 5,592 kN exceeds 4,000 kN limit; 1 IJS splits string into two 200 m pushes (peak 2,971 kN).
Allow for: Interjack hydraulic control console, trailing hydraulic umbilical lines, synchronized stroke sequencing, and joint packings.
Pitfalls: Interjack station seal rupture during high-pressure stroke; eccentric pipe face contact if alignment is curved or timber packing crushed.
Estimator checks
- Verify geotechnical boreholes along tunnel alignment: Unconfined Compressive Strength (UCS), quartz content, boulder frequency, and groundwater head directly determine cutterhead disc wear, penetration speed, and slurry face balance.
- Thrust reaction wall design: Allow 4 to 8 working days for launch pit RC thrust wall curing and jacking rig anchoring; allowable ground bearing reaction pressure must be structurally verified prior to applying full thrust.
- Intermediate Jacking Stations (IJS): For single drives exceeding 150-200 m, budget for automated interjacks and continuous bentonite lubrication to prevent pipe jacking forces exceeding reinforced concrete pipe compressive limits (typically 4,000 to 5,500 kN).
- Shaft sizing and temporary works: Launch pit circular caisson internal diameter must be minimum 4.87 m with compact jacking rig (or 8.5 m for standard telescopic main station); reception pit must be minimum 4.5 m ID to safely crane-lift the 3.75 m shield.
- Separation plant sizing: Match hydrocyclone and shale shaker capacity (180 to 250 m³/hr) to excavation volume; in heavy plastic clay geologies, budget for an auxiliary decanter centrifuge and polymer coagulant dosing unit.
- Transport and craneage: The 13,000 kg articulated shield and trailing can travel as standard general access road freight on drop-deck floats (1.505 m OD, within 2.50 m width limit). Site mobile crane must be rated for minimum 13 t lift at launch and reception shaft radiuses.
- All hire rate schedules are unquoted placeholders. In accordance with Vaultix estimating principles, never invent hire rates without formal supplier tenders.
- Confined space entry permits, gas monitoring, forced ventilation, and High-Risk Work Licences (HRWL Class DG/RB for dogging/rigging) required across all shaft operations.
Data basis. DRAFT, DO NOT RELY ON THESE FIGURES. Independent check 10 November 2026: none of the machine values could be verified. The Herrenknecht AVN 1200 TB data sheet could not be retrieved, and the cited product page does not contain the thrust, torque, power or advance values. The 258 kNm torque and 132 kW cutter power may belong to the TC configuration, not the TB. Treat every machine value as unverified until the Herrenknecht data sheet is read. Reference model: Herrenknecht AVN 1200 TB / AVN 1200 TC Slurry Microtunnelling Boring Machine (MTBM), technical data sheets (Scribd doc 282611087 p. 1-2, doc 283596238 p. 1-2, DirectIndustry p. 1-4, Herrenknecht AG brochure). Sourced 9 November 2026. Fuel uses Caterpillar Performance Handbook telematics proxy (65.0 L/hr medium duty for 500 kVA site genset). Productivity and costs are Vaultix estimating models. Sources and assumptions documented in files/sewer-tbm-microtunnel.md.
Entry / sewer-tbm-microtunnel Issue / 2026-11-09
Library navigation
Plant and method index · Discipline work packages · Survey conformance and lot release