Discipline library

Battery energy storage

Release unit pads and access, set battery and converter packages, inspect thermal and fire systems, then turn over connection and control systems.

Battery energy storage
  1. Battery enclosureIdentify each unit and its installation release.
  2. Power conversion systemCoordinate DC and AC interfaces with the electrical work packages.
  3. TransformerLink installation and test records to the grid connection package.
Illustrative workfront within Battery energy storage.

Construction and release sequence

  1. Release plinths, cable routes and enclosure access
  2. Set battery blocks, power conversion and MV equipment
  3. Install cooling, fire systems, controls and grid interfaces
  4. Reconcile enclosure checks, test packs and staged commissioning

Work packages and conformance checks

Production and measurement

Track enclosure, converter and circuit quantities separately from site-wide commissioning.

View the discipline reference figureBattery energy storage reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.BESS.001Battery enclosure / DC block — offload, set on pad & connectno/crew-day12.55S-302
PRD.BESS.002Battery module / rack install & DC string assemblyno/crew-day41020S-302
PRD.BESS.003DC interconnection & string cabling between enclosuresno/crew-day2510S-302
PRD.BESS.004PCS inverter / power-station block — set & terminateno/crew-day0.512S-302
PRD.BESS.005MV step-up transformer — set & terminateno/crew-day0.512S-302
PRD.BESS.006MV switchgear / ring-main unit — set & terminateno/crew-day124S-302
PRD.BESS.007MV collection cabling on tray / in trench — supply & laym/day per crew150300600S-302
PRD.BESS.008HV connection works / switchbay to the connection pointdays/switchbay51225S-302
PRD.BESS.009Fire detection & alarm to battery enclosures (gas/heat)no/crew-day248S-302
PRD.BESS.010Fire suppression / deluge & deflagration venting (NFPA 855)no/crew-day124S-302
PRD.BESS.011HVAC / thermal-management system — installno/crew-day12.55S-302
PRD.BESS.012EMS / plant controller + SCADA/RTU integrationdays/system51225S-302
PRD.BESS.013Pre-commissioning, FAT/SAT & subsystem testingdays/system51530S-302
PRD.BESS.014Grid-compliance / GPS hold-point campaign (R1/R2/full-output) + energisation/registrationweeks/campaign41230S-302/208

Construction references

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.