Battery energy storage
- Battery enclosureIdentify each unit and its installation release.
- Power conversion systemCoordinate DC and AC interfaces with the electrical work packages.
- TransformerLink installation and test records to the grid connection package.
Construction and release sequence
- Release plinths, cable routes and enclosure access
- Set battery blocks, power conversion and MV equipment
- Install cooling, fire systems, controls and grid interfaces
- Reconcile enclosure checks, test packs and staged commissioning
Work packages and conformance checks
BESS Grid Connection, Control (EMS/SCADA) & CommissioningSurvey collector routes, joint bays, switchgear interfaces and metering asset locations.BESS Fire Safety, Thermal Management & HVAC — detection, suppression, deflagration venting, separation & coolingCheck separation distances, access envelopes, drainage and service penetration locations.Power Conversion (PCS) & MV Reticulation — inverters, step-up transformers, MV switchgear & collection cablingSurvey skid pads, cable entries, earthing connections and equipment clearances.Battery Energy Storage Units — DC blocks, enclosures, modules & string cablingCheck enclosure pad elevations, bolt patterns and unit access clearances before delivery.
Production and measurement
Track enclosure, converter and circuit quantities separately from site-wide commissioning.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.BESS.001 | Battery enclosure / DC block — offload, set on pad & connect | no/crew-day | 1 | 2.5 | 5 | S-302 |
| PRD.BESS.002 | Battery module / rack install & DC string assembly | no/crew-day | 4 | 10 | 20 | S-302 |
| PRD.BESS.003 | DC interconnection & string cabling between enclosures | no/crew-day | 2 | 5 | 10 | S-302 |
| PRD.BESS.004 | PCS inverter / power-station block — set & terminate | no/crew-day | 0.5 | 1 | 2 | S-302 |
| PRD.BESS.005 | MV step-up transformer — set & terminate | no/crew-day | 0.5 | 1 | 2 | S-302 |
| PRD.BESS.006 | MV switchgear / ring-main unit — set & terminate | no/crew-day | 1 | 2 | 4 | S-302 |
| PRD.BESS.007 | MV collection cabling on tray / in trench — supply & lay | m/day per crew | 150 | 300 | 600 | S-302 |
| PRD.BESS.008 | HV connection works / switchbay to the connection point | days/switchbay | 5 | 12 | 25 | S-302 |
| PRD.BESS.009 | Fire detection & alarm to battery enclosures (gas/heat) | no/crew-day | 2 | 4 | 8 | S-302 |
| PRD.BESS.010 | Fire suppression / deluge & deflagration venting (NFPA 855) | no/crew-day | 1 | 2 | 4 | S-302 |
| PRD.BESS.011 | HVAC / thermal-management system — install | no/crew-day | 1 | 2.5 | 5 | S-302 |
| PRD.BESS.012 | EMS / plant controller + SCADA/RTU integration | days/system | 5 | 12 | 25 | S-302 |
| PRD.BESS.013 | Pre-commissioning, FAT/SAT & subsystem testing | days/system | 5 | 15 | 30 | S-302 |
| PRD.BESS.014 | Grid-compliance / GPS hold-point campaign (R1/R2/full-output) + energisation/registration | weeks/campaign | 4 | 12 | 30 | S-302/208 |
Construction references
- Grid-Scale Battery Energy Storage Construction