Mining conveyor systems
- Erection craneInclude repositioning and rigging between lift zones.
- Trestle and gallerySurvey supports and connections before installing the belt.
- Belt and idlersComplete alignment and inspection before commissioning.
Construction and release sequence
- Release foundations, corridor access and component delivery
- Erect trestles, galleries, drives and transfer stations
- Install belt, idlers, splices and guarding by section
- Reconcile alignment, tracking and commissioned transfer interfaces
Work packages and conformance checks
Production and measurement
Measure structure tonnage, installed conveyor length, splices and commissioning separately.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.CV.001 | Conveyor structure / gantry erect — stringers, trusses, trestles | m/day | 20 | 40 | 60 | S-072 |
| PRD.CV.002 | Carry / return idler set + pulley — supply & install | idlers/shift | 100 | 200 | 300 | S-072 |
| PRD.CV.003 | Drive / take-up / tension station — supply & install | no/week | 0.5 | 1.5 | 3 | S-072 |
| PRD.CV.004 | Belt supply & pull-on install (steel-cord / fabric) | m/day | 100 | 250 | 400 | S-072 |
| PRD.CV.005 | Belt splice — hot-vulcanised (steel-cord / heavy) | splices/shift | 0.5 | 1 | 2 | S-072 |
| PRD.CV.006 | Transfer chute install (skirting + wear liners) | no/week | 1 | 3 | 6 | S-072 |
| PRD.CV.007 | Guarding & walkway — supply & install (AS 1755/4024) | m/crew-day | 20 | 40 | 70 | S-072 |
| PRD.CV.008 | Belt scraper / cleaner system (primary + secondary) — install | no/shift | 1 | 2 | 4 | S-072 |
| PRD.CV.009 | Belt weigher (weightometer) / sampling station — install & calibrate | no/week | 0.5 | 1.5 | 3 | S-072 |
| PRD.CV.010 | Drive motor + gearbox + VSD — install & terminate | no/week | 1 | 2 | 4 | S-072 |
| PRD.CV.011 | Dust suppression / extraction at transfer point — install | no/week | 1 | 3 | 6 | S-072 |
Construction references
- Conveyor System Installation