Discipline library

Dams, levees and water-retaining works

Release diversion and foundation treatment, record each embankment zone and spillway interface, then baseline instrumentation before staged filling.

Dams, levees and water-retaining works
  1. Compaction spreadKeep placement, conditioning and rolling within the released work zone.
  2. Core and filtersSurvey zone boundaries and inspect interfaces before concealment.
  3. Slope protectionReconcile the completed rock profile to the design surface.
Illustrative workfront within Dams, levees and water-retaining works.

Construction and release sequence

  1. Release diversion, care-of-water arrangements and founding surface
  2. Place and verify embankment zones or concrete lifts
  3. Complete outlet works, filters, protection and instrumentation
  4. Reconcile lift records and obtain staged first-fill approval

Work packages and conformance checks

Technique rates and labour allowances

The source records typical values. Its hourly allowances, output rates and shift quantities each retain their published basis.

Component activityPublished basisLowTypicalHighLibrary source
Establishment & disestablishment of siteDLW.01.010.01hr (direct)—90—PROD-DAM-001
Dam Safety Mgmt Plan, CEMP & quality documentationDLW.01.020.01hr (direct)—90—PROD-DAM-001
Geotechnical site investigation - boreholes, test pitsDLW.01.030.01hr/unit (labour-hours)—9—PROD-DAM-001
River/creek diversion works - temporary diversion channel/cuDLW.01.040.01hr (direct)—270—PROD-DAM-001
Cofferdam construction & removal (upstream/downstream)DLW.01.050.01hr/unit (labour-hours)—270—PROD-DAM-001
Care of water - dewatering of foundation & works area (per wDLW.01.060.01hr (direct)—45—PROD-DAM-001
Survey set-out, as-constructed & instrumentation surveyDLW.01.070.01hr (direct)—90—PROD-DAM-001
Clearing, grubbing & topsoil stripping of dam footprintDLW.02.010.01m2/day—3000—PROD-DAM-001
Foundation excavation in common (soil/weathered) materialDLW.02.020.01m3/hr (ref PRD.EW.002)—120—PROD-DAM-001
Foundation excavation in rock (rippable to hard rock)DLW.02.030.01m3/hr (rock strength dependent) (ref PRD.EW.011)—80—PROD-DAM-001
Foundation surface preparation, cleaning & dental concreteDLW.02.040.01m2/day—120—PROD-DAM-001
Foundation consolidation/curtain grouting - drilling & groutDLW.02.050.01m/hr—5—PROD-DAM-001
Cut-off wall - plastic-concrete / bentonite-cementDLW.02.060.01m2/day—60—PROD-DAM-001
Disposal of unsuitable foundation material to designated areDLW.02.070.01m3/hr—90—PROD-DAM-001
Win, process & place zoned earthfill core (low-permeability)DLW.03.010.01m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015)—300—PROD-DAM-001
Win, process & place general embankment shoulder/zone fillDLW.03.020.01m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015)—300—PROD-DAM-001
Supply, place & compact granular filter & transition zoneDLW.03.030.01m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015)—300—PROD-DAM-001
Supply, place & compact drainage zone materialDLW.03.040.01m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015)—300—PROD-DAM-001
Construct levee embankment (homogeneous) - imported/won fillDLW.03.050.01m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015)—300—PROD-DAM-001
Supply & haul imported select fill from off-site borrowDLW.03.060.01m3/hr (ref PRD.EW.014)—300—PROD-DAM-001
Final trimming, shaping & topsoiling of embankment/leveeDLW.03.070.01m2/hr (ref PRD.EW.017)—600—PROD-DAM-001
Supply, place, vibrate & cure mass/structural concreteDLW.04.010.01m3/hr (ref PRD.TL.013)—30—PROD-DAM-001
Supply, place & cure liquid-retaining concrete (AS 3735)DLW.04.020.01m3/crew-day (ref PRD.BS.016)—15—PROD-DAM-001
Roller-compacted concrete (RCC) gravity dam/spillway liftDLW.04.030.01m3/hr—60—PROD-DAM-001
Supply, cut, bend & fix reinforcing steel (AS/NZS 4671)DLW.04.040.01t/hr—1.5—PROD-DAM-001
Supply & install PVC/hydrophilic water-stops to jointsDLW.04.050.01m/day—40—PROD-DAM-001
Supply & apply protective/waterproofing coating systemDLW.04.060.01m2/crew-day (ref PRD.BS.030)—80—PROD-DAM-001
Concrete parapet, crest wall & wave wall incl formworkDLW.04.070.01m/day—25—PROD-DAM-001
Supply & install geomembrane liner (HDPE/LLDPE) to reservoirDLW.05.010.01m2/day—350—PROD-DAM-001
Supply & install geosynthetic clay liner (GCL)DLW.05.020.01m2/day—600—PROD-DAM-001
Supply & install geotextile separation/cushion/filterDLW.05.030.01m2/day—800—PROD-DAM-001
Supply, place & grade rock rip-rap/armour to upstream faceDLW.05.040.01m3/hr (ref PRD.EW.014)—300—PROD-DAM-001
Supply & install articulated concrete block mattressDLW.05.050.01m2/day—150—PROD-DAM-001
Supply, place & compact compacted clay liner (CCL)DLW.05.060.01m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015)—300—PROD-DAM-001
Topsoil, hydromulch/turf & erosion-control mattingDLW.05.070.01m2/day—1200—PROD-DAM-001
Supply & install outlet conduit/pipework (DICL/steel)DLW.06.010.01m/day—30—PROD-DAM-001
Intake tower/screen, trash rack & gates - supply & installDLW.06.020.01hr/unit (labour-hours)—180—PROD-DAM-001
Penstock, guard/regulating valves & pipework - supply & instDLW.06.030.01hr/unit (labour-hours)—135—PROD-DAM-001
Spillway crest gate / radial (Tainter) - supply & installDLW.06.040.01hr/unit (labour-hours)—270—PROD-DAM-001
Energy-dissipation works - stilling basin / baffle blocksDLW.06.050.01hr/unit (labour-hours)—180—PROD-DAM-001
Low-level / scour outlet & environmental flow valveDLW.06.060.01hr/unit (labour-hours)—90—PROD-DAM-001
Supply & install handrails, access platforms, laddersDLW.06.070.01m/day—12—PROD-DAM-001
Supply & install piezometers (vibrating-wire/standpipe)DLW.07.010.01no/day—3—PROD-DAM-001
Supply & install survey/settlement monitoring pointsDLW.07.020.01no/day—8—PROD-DAM-001
Supply & install seepage measurement weirs (V-notch)DLW.07.030.01no/day—1.5—PROD-DAM-001
Compaction & materials testing - field density, moistureDLW.07.040.01no/day—10—PROD-DAM-001
Liquid-retaining structure hydrostatic/water-tightness testDLW.07.050.01hr/unit (labour-hours)—27—PROD-DAM-001
First-fill surveillance, commissioning & dam-safety reviewDLW.07.060.01hr (direct)—135—PROD-DAM-001
O&M manual, as-constructed dossier & surveillance planDLW.07.070.01hr (direct)—72—PROD-DAM-001
Mobilisation of plant, crews and facilities to site (establiDLW.90.010.01hr (direct)—90—PROD-DAM-001
Demobilisation and site restoration on completionDLW.90.020.01hr (direct)—45—PROD-DAM-001
Time-related site costs (supervision, facilities, plant stanDLW.90.030.01hr (direct)—45—PROD-DAM-001
Standing time / standby due to Principal-caused delay (per hDLW.90.040.01hr (direct)—1—PROD-DAM-001

Production and measurement

Distinguish material zones, filters, treatment quantities and monitoring through first fill.

View the discipline reference figureDams, levees and water-retaining works reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

Use the linked discipline record and measured project outputs to establish the planning basis.