- Compaction spreadKeep placement, conditioning and rolling within the released work zone.
- Core and filtersSurvey zone boundaries and inspect interfaces before concealment.
- Slope protectionReconcile the completed rock profile to the design surface.
Construction and release sequence
- Release diversion, care-of-water arrangements and founding surface
- Place and verify embankment zones or concrete lifts
- Complete outlet works, filters, protection and instrumentation
- Reconcile lift records and obtain staged first-fill approval
Work packages and conformance checks
Technique rates and labour allowances
The source records typical values. Its hourly allowances, output rates and shift quantities each retain their published basis.
| Component activity | Published basis | Low | Typical | High | Library source |
|---|---|---|---|---|---|
| Establishment & disestablishment of siteDLW.01.010.01 | hr (direct) | — | 90 | — | PROD-DAM-001 |
| Dam Safety Mgmt Plan, CEMP & quality documentationDLW.01.020.01 | hr (direct) | — | 90 | — | PROD-DAM-001 |
| Geotechnical site investigation - boreholes, test pitsDLW.01.030.01 | hr/unit (labour-hours) | — | 9 | — | PROD-DAM-001 |
| River/creek diversion works - temporary diversion channel/cuDLW.01.040.01 | hr (direct) | — | 270 | — | PROD-DAM-001 |
| Cofferdam construction & removal (upstream/downstream)DLW.01.050.01 | hr/unit (labour-hours) | — | 270 | — | PROD-DAM-001 |
| Care of water - dewatering of foundation & works area (per wDLW.01.060.01 | hr (direct) | — | 45 | — | PROD-DAM-001 |
| Survey set-out, as-constructed & instrumentation surveyDLW.01.070.01 | hr (direct) | — | 90 | — | PROD-DAM-001 |
| Clearing, grubbing & topsoil stripping of dam footprintDLW.02.010.01 | m2/day | — | 3000 | — | PROD-DAM-001 |
| Foundation excavation in common (soil/weathered) materialDLW.02.020.01 | m3/hr (ref PRD.EW.002) | — | 120 | — | PROD-DAM-001 |
| Foundation excavation in rock (rippable to hard rock)DLW.02.030.01 | m3/hr (rock strength dependent) (ref PRD.EW.011) | — | 80 | — | PROD-DAM-001 |
| Foundation surface preparation, cleaning & dental concreteDLW.02.040.01 | m2/day | — | 120 | — | PROD-DAM-001 |
| Foundation consolidation/curtain grouting - drilling & groutDLW.02.050.01 | m/hr | — | 5 | — | PROD-DAM-001 |
| Cut-off wall - plastic-concrete / bentonite-cementDLW.02.060.01 | m2/day | — | 60 | — | PROD-DAM-001 |
| Disposal of unsuitable foundation material to designated areDLW.02.070.01 | m3/hr | — | 90 | — | PROD-DAM-001 |
| Win, process & place zoned earthfill core (low-permeability)DLW.03.010.01 | m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015) | — | 300 | — | PROD-DAM-001 |
| Win, process & place general embankment shoulder/zone fillDLW.03.020.01 | m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015) | — | 300 | — | PROD-DAM-001 |
| Supply, place & compact granular filter & transition zoneDLW.03.030.01 | m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015) | — | 300 | — | PROD-DAM-001 |
| Supply, place & compact drainage zone materialDLW.03.040.01 | m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015) | — | 300 | — | PROD-DAM-001 |
| Construct levee embankment (homogeneous) - imported/won fillDLW.03.050.01 | m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015) | — | 300 | — | PROD-DAM-001 |
| Supply & haul imported select fill from off-site borrowDLW.03.060.01 | m3/hr (ref PRD.EW.014) | — | 300 | — | PROD-DAM-001 |
| Final trimming, shaping & topsoiling of embankment/leveeDLW.03.070.01 | m2/hr (ref PRD.EW.017) | — | 600 | — | PROD-DAM-001 |
| Supply, place, vibrate & cure mass/structural concreteDLW.04.010.01 | m3/hr (ref PRD.TL.013) | — | 30 | — | PROD-DAM-001 |
| Supply, place & cure liquid-retaining concrete (AS 3735)DLW.04.020.01 | m3/crew-day (ref PRD.BS.016) | — | 15 | — | PROD-DAM-001 |
| Roller-compacted concrete (RCC) gravity dam/spillway liftDLW.04.030.01 | m3/hr | — | 60 | — | PROD-DAM-001 |
| Supply, cut, bend & fix reinforcing steel (AS/NZS 4671)DLW.04.040.01 | t/hr | — | 1.5 | — | PROD-DAM-001 |
| Supply & install PVC/hydrophilic water-stops to jointsDLW.04.050.01 | m/day | — | 40 | — | PROD-DAM-001 |
| Supply & apply protective/waterproofing coating systemDLW.04.060.01 | m2/crew-day (ref PRD.BS.030) | — | 80 | — | PROD-DAM-001 |
| Concrete parapet, crest wall & wave wall incl formworkDLW.04.070.01 | m/day | — | 25 | — | PROD-DAM-001 |
| Supply & install geomembrane liner (HDPE/LLDPE) to reservoirDLW.05.010.01 | m2/day | — | 350 | — | PROD-DAM-001 |
| Supply & install geosynthetic clay liner (GCL)DLW.05.020.01 | m2/day | — | 600 | — | PROD-DAM-001 |
| Supply & install geotextile separation/cushion/filterDLW.05.030.01 | m2/day | — | 800 | — | PROD-DAM-001 |
| Supply, place & grade rock rip-rap/armour to upstream faceDLW.05.040.01 | m3/hr (ref PRD.EW.014) | — | 300 | — | PROD-DAM-001 |
| Supply & install articulated concrete block mattressDLW.05.050.01 | m2/day | — | 150 | — | PROD-DAM-001 |
| Supply, place & compact compacted clay liner (CCL)DLW.05.060.01 | m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) (ref PRD.EW.015) | — | 300 | — | PROD-DAM-001 |
| Topsoil, hydromulch/turf & erosion-control mattingDLW.05.070.01 | m2/day | — | 1200 | — | PROD-DAM-001 |
| Supply & install outlet conduit/pipework (DICL/steel)DLW.06.010.01 | m/day | — | 30 | — | PROD-DAM-001 |
| Intake tower/screen, trash rack & gates - supply & installDLW.06.020.01 | hr/unit (labour-hours) | — | 180 | — | PROD-DAM-001 |
| Penstock, guard/regulating valves & pipework - supply & instDLW.06.030.01 | hr/unit (labour-hours) | — | 135 | — | PROD-DAM-001 |
| Spillway crest gate / radial (Tainter) - supply & installDLW.06.040.01 | hr/unit (labour-hours) | — | 270 | — | PROD-DAM-001 |
| Energy-dissipation works - stilling basin / baffle blocksDLW.06.050.01 | hr/unit (labour-hours) | — | 180 | — | PROD-DAM-001 |
| Low-level / scour outlet & environmental flow valveDLW.06.060.01 | hr/unit (labour-hours) | — | 90 | — | PROD-DAM-001 |
| Supply & install handrails, access platforms, laddersDLW.06.070.01 | m/day | — | 12 | — | PROD-DAM-001 |
| Supply & install piezometers (vibrating-wire/standpipe)DLW.07.010.01 | no/day | — | 3 | — | PROD-DAM-001 |
| Supply & install survey/settlement monitoring pointsDLW.07.020.01 | no/day | — | 8 | — | PROD-DAM-001 |
| Supply & install seepage measurement weirs (V-notch)DLW.07.030.01 | no/day | — | 1.5 | — | PROD-DAM-001 |
| Compaction & materials testing - field density, moistureDLW.07.040.01 | no/day | — | 10 | — | PROD-DAM-001 |
| Liquid-retaining structure hydrostatic/water-tightness testDLW.07.050.01 | hr/unit (labour-hours) | — | 27 | — | PROD-DAM-001 |
| First-fill surveillance, commissioning & dam-safety reviewDLW.07.060.01 | hr (direct) | — | 135 | — | PROD-DAM-001 |
| O&M manual, as-constructed dossier & surveillance planDLW.07.070.01 | hr (direct) | — | 72 | — | PROD-DAM-001 |
| Mobilisation of plant, crews and facilities to site (establiDLW.90.010.01 | hr (direct) | — | 90 | — | PROD-DAM-001 |
| Demobilisation and site restoration on completionDLW.90.020.01 | hr (direct) | — | 45 | — | PROD-DAM-001 |
| Time-related site costs (supervision, facilities, plant stanDLW.90.030.01 | hr (direct) | — | 45 | — | PROD-DAM-001 |
| Standing time / standby due to Principal-caused delay (per hDLW.90.040.01 | hr (direct) | — | 1 | — | PROD-DAM-001 |
Production and measurement
Distinguish material zones, filters, treatment quantities and monitoring through first fill.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
Use the linked discipline record and measured project outputs to establish the planning basis.