Drainage and stormwater

Verify outfall and receiving levels first. Release pipe, channel and subsurface works before cover, then check the connected flow path and treatment areas.

Drainage and stormwater
  1. ExcavatorExcavation and lifting access govern the installation front.
  2. Pipe beddingVerify support and invert before the pipe is covered.
  3. Pit connectionSurvey the inlet and outlet levels against the design.
Illustrative workfront within Drainage and stormwater.

Construction and release sequence

  1. Survey outlets, crossings and existing connections
  2. Prepare excavation, founding level and bedding
  3. Install pipes, pits, filters and surface drainage assets
  4. Record inverts, connection inspections and accepted backfill

Work packages and conformance checks

Production and measurement

Include pits, headwalls, dewatering, filter media and reinstatement separately from pipe length.

View the discipline reference figureDrainage and stormwater reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.DR.001Trench excavation 0-1.5 m depthm3/day180260340S-061
PRD.DR.002Trench excavation 1.5-3.0 m depthm3/day120190260S-061
PRD.DR.003Trench excavation 3.0-4.5 m depthm3/day70130190S-061
PRD.DR.004RCP pipe lay DN300m/day457090S-061
PRD.DR.005RCP pipe lay DN375-DN450m/day406080S-061
PRD.DR.006RCP pipe lay DN600m/day305065S-061
PRD.DR.007RCP pipe lay DN750-DN900m/day224055S-061
PRD.DR.008RCP pipe lay DN1050-DN1200m/day153045S-061
PRD.DR.010Bedding & haunch (Type 1 / Type 2)m3/day placed204060S-061
PRD.DR.011Backfill & compact (select / in-situ)m3/day150250350S-061
PRD.DR.012Precast pit/manhole 1050-1200 dia, <=2.5 m deepper day1.534S-061
PRD.DR.014Field inlet / gully (kerb) pitper day246S-061
PRD.DR.015Headwall / wingwall (precast or in-situ)per day0.523S-061
PRD.DR.016RCBC box culvert lay (per cell, <=1200x600)m/day per cell81828S-061
PRD.DR.017RCBC box culvert lay (per cell, >=1800x1200)m/day per cell51220S-061
PRD.DR.018Subsoil / agi drain (slotted + filter)m/day120250400S-061
PRD.DR.019Geotextile (separation / filter fabric)m2/day4008001200S-061
PRD.DR.020Scour protection / rock pitching (placed)m2/day3070120S-061
PRD.DR.021Connect to existing drainageper day0.523S-061
PRD.DR.022CCTV inspection & proof (post-lay)m/day300600900S-061