Drainage and stormwater
- ExcavatorExcavation and lifting access govern the installation front.
- Pipe beddingVerify support and invert before the pipe is covered.
- Pit connectionSurvey the inlet and outlet levels against the design.
Construction and release sequence
- Survey outlets, crossings and existing connections
- Prepare excavation, founding level and bedding
- Install pipes, pits, filters and surface drainage assets
- Record inverts, connection inspections and accepted backfill
Work packages and conformance checks
Subsoil & Subsurface DrainageSurvey invert and outlet levels before closing trenches and record observed drainage direction.Surface DrainageCheck channel profiles, pit inverts, pipe gradients and outfall tie-ins along the drainage path.Water-Sensitive Urban Design (WSUD)Survey filter surface, underdrain level, overflow crest and basin storage limits.
Production and measurement
Include pits, headwalls, dewatering, filter media and reinstatement separately from pipe length.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.DR.001 | Trench excavation 0-1.5 m depth | m3/day | 180 | 260 | 340 | S-061 |
| PRD.DR.002 | Trench excavation 1.5-3.0 m depth | m3/day | 120 | 190 | 260 | S-061 |
| PRD.DR.003 | Trench excavation 3.0-4.5 m depth | m3/day | 70 | 130 | 190 | S-061 |
| PRD.DR.004 | RCP pipe lay DN300 | m/day | 45 | 70 | 90 | S-061 |
| PRD.DR.005 | RCP pipe lay DN375-DN450 | m/day | 40 | 60 | 80 | S-061 |
| PRD.DR.006 | RCP pipe lay DN600 | m/day | 30 | 50 | 65 | S-061 |
| PRD.DR.007 | RCP pipe lay DN750-DN900 | m/day | 22 | 40 | 55 | S-061 |
| PRD.DR.008 | RCP pipe lay DN1050-DN1200 | m/day | 15 | 30 | 45 | S-061 |
| PRD.DR.010 | Bedding & haunch (Type 1 / Type 2) | m3/day placed | 20 | 40 | 60 | S-061 |
| PRD.DR.011 | Backfill & compact (select / in-situ) | m3/day | 150 | 250 | 350 | S-061 |
| PRD.DR.012 | Precast pit/manhole 1050-1200 dia, <=2.5 m deep | per day | 1.5 | 3 | 4 | S-061 |
| PRD.DR.014 | Field inlet / gully (kerb) pit | per day | 2 | 4 | 6 | S-061 |
| PRD.DR.015 | Headwall / wingwall (precast or in-situ) | per day | 0.5 | 2 | 3 | S-061 |
| PRD.DR.016 | RCBC box culvert lay (per cell, <=1200x600) | m/day per cell | 8 | 18 | 28 | S-061 |
| PRD.DR.017 | RCBC box culvert lay (per cell, >=1800x1200) | m/day per cell | 5 | 12 | 20 | S-061 |
| PRD.DR.018 | Subsoil / agi drain (slotted + filter) | m/day | 120 | 250 | 400 | S-061 |
| PRD.DR.019 | Geotextile (separation / filter fabric) | m2/day | 400 | 800 | 1200 | S-061 |
| PRD.DR.020 | Scour protection / rock pitching (placed) | m2/day | 30 | 70 | 120 | S-061 |
| PRD.DR.021 | Connect to existing drainage | per day | 0.5 | 2 | 3 | S-061 |
| PRD.DR.022 | CCTV inspection & proof (post-lay) | m/day | 300 | 600 | 900 | S-061 |
Construction references
- Pipe Culvert Drainage
- WSUD and Stormwater Treatment Train
- Open Channel Floodway and Waterway Drainage