Earthworks and bulk civil
- Cut faceMeasure excavation on the agreed bank-volume basis.
- Articulated truckThe return and loading cycle limits the haul spread.
- Placed liftSurvey the compacted fill before releasing the next lift.
Construction and release sequence
- Release clearing limits and erosion controls
- Strip and survey the cut and fill zones
- Haul classified material and compact by lift
- Release the surveyed formation with density results
Work packages and conformance checks
Bulk Cut-to-Fill Earthworks & Engineered FillCompare stripped and finished surfaces by cut or fill zone and common boundary.Erosion & Sediment Control & Environmental ManagementPick up diversion crest, basin invert and spillway levels before runoff is diverted.Subgrade / Formation, Ground Treatment & Earthworks DrainageSurvey treatment limits, top of treated formation and drain outlets before covering.Site Clearing, Grubbing & Topsoil StrippingStake the disturbance boundary and survey the original and stripped surfaces.
Production and measurement
Distinguish bank, loose and compacted volume. Measure haul and rehandling where the site balance requires them.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.EW.001 | Strip & stockpile topsoil | m3/hr | 120 | 200 | 320 | S-061 |
| PRD.EW.002 | Bulk excavation cut-to-fill (30t excavator + truck fleet) | m3/hr | 80 | 120 | 160 | S-061 |
| PRD.EW.003 | Cut-to-spoil (excavator load-out, no on-site reuse) | m3/hr (loading limited) | 90 | 130 | 170 | S-061 |
| PRD.EW.004 | Dozer push (short haul, cut-to-fill <100 m) | m3/hr (falls sharply >70 m and uphill) | 150 | 300 | 500 | S-061 |
| PRD.EW.005 | Scraper cut / haul / spread (self-loading or push-loaded) | m3/hr per scraper (haul-distance dependent) | 150 | 300 | 600 | S-061 |
| PRD.EW.006 | Load & haul - 0.5 km one-way (exc + tippers) | m3/hr | 90 | 130 | 170 | S-061 |
| PRD.EW.007 | Load & haul - 1 km one-way | m3/hr | 70 | 110 | 150 | S-061 |
| PRD.EW.008 | Load & haul - 2 km one-way | m3/hr | 55 | 90 | 130 | S-061 |
| PRD.EW.009 | Load & haul - 5 km one-way | m3/hr | 40 | 65 | 100 | S-061 |
| PRD.EW.010 | Import select fill (supply + place + compact) | m3/hr (placing crew) | 60 | 100 | 150 | S-061 |
| PRD.EW.011 | Rock excavation - rippable (D8/D10 ripping) | m3/hr (rock strength dependent) | 40 | 80 | 130 | S-061 |
| PRD.EW.012 | Rock excavation - hydraulic hammer / rock-breaker | m3/hr | 8 | 20 | 45 | S-061 |
| PRD.EW.014 | Spread & level fill (place dumped material to grade) | m3/hr | 150 | 300 | 500 | S-061 |
| PRD.EW.015 | Compact fill - by layer (roller passes) | m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes) | 150 | 300 | 500 | S-061 |
| PRD.EW.016 | Moisture condition / water fill (OMC ±2%) | m3/hr | 200 | 400 | 700 | S-061 |
| PRD.EW.017 | Trim & batter to design (final shaping) | m2/hr | 300 | 600 | 1000 | S-061 |
| PRD.EW.018 | Proof roll formation/subgrade | m2/hr | 1500 | 3000 | 5000 | S-061 |
| PRD.EW.019 | Subgrade preparation / CBR conditioning | m2/hr | 200 | 400 | 700 | S-061 |
| PRD.EW.020 | Borrow pit operation (win + process + load) | m3/hr (winning rate) | 100 | 200 | 400 | S-061 |
| PRD.CLR.001 | Clear & grub - light grass / sparse scrub (<1 tree per 100 m2, <150 mm girth) | ha/hr | 0.8 | 1.2 | 1.5 | S-061 |
| PRD.CLR.002 | Clear & grub - light grass / sparse scrub | m2/hr | 8000 | 11000 | 15000 | S-061 |
| PRD.CLR.003 | Clear & grub - medium scrub / regrowth (scattered trees 150-300 mm girth, dense low scrub) | ha/hr | 0.35 | 0.55 | 0.8 | S-061 |
| PRD.CLR.004 | Clear & grub - heavy timber / closed forest (continuous canopy, frequent trees >300 mm) | ha/hr | 0.08 | 0.15 | 0.3 | S-061 |
| PRD.CLR.005 | Individual tree removal - small (<300 mm girth/diameter at 1.4 m) | trees/hr | 8 | 14 | 20 | S-061 |
| PRD.CLR.006 | Individual tree removal - medium (300-600 mm girth) | trees/hr | 3 | 5 | 8 | S-061 |
| PRD.CLR.007 | Individual tree removal - large (600-900 mm girth) | trees/hr | 1 | 2 | 3 | S-061 |
| PRD.CLR.008 | Individual tree removal - very large (>900 mm girth) | trees/hr | 0.3 | 0.7 | 1.2 | S-061 |
| PRD.CLR.009 | Stump grinding (in-situ, root system left) | Small -/hr · Med -/hr · Large -/hr | 1 | 5 | 10 | S-061 |
| PRD.CLR.010 | Stump / root ball removal (excavate & extract) | Small -/hr · Med -/hr · Large -/hr | 0.5 | 4 | 8 | S-061 |
| PRD.CLR.011 | Grub roots / remove organic material (strip area, post-clearing) | m2/hr | 1500 | 2500 | 4000 | S-061 |
| PRD.CLR.012 | Topsoil strip & stockpile - shallow (<=150 mm) | m2/hr | 1200 | 2000 | 3000 | S-061 |
| PRD.CLR.013 | Topsoil strip & stockpile - medium (150-300 mm) | m2/hr | 900 | 1400 | 2200 | S-061 |
| PRD.CLR.014 | Topsoil strip & stockpile - deep (>300 mm) | m3/hr (load & short haul) | 60 | 90 | 140 | S-061 |
| PRD.CLR.015 | Mulch / chip arisings in-situ (forestry/horizontal mulcher or chipper) | ha/hr | 0.15 | 0.3 | 0.55 | S-061 |
| PRD.CLR.016 | Chip individual fell material (mobile chipper) | m3/hr (loose) | 8 | 14 | 22 | S-061 |
| PRD.CLR.017 | Windrow & burn (where permitted) | ha/hr (push only) | 0.4 | 0.7 | 1.2 | S-061 |
| PRD.CLR.018 | Load & cart mulch / cleared spoil off-site to disposal | Load - m3/hr; cart governed by cycle | 60 | 110 | 110 | S-061 |
| PRD.CLR.020 | Demolish & remove fencing (rural/chainmesh/timber) | m/hr | 30 | 60 | 100 | S-061 |
| PRD.CLR.021 | Remove signs / posts / small roadside furniture | ea/hr | 4 | 8 | 14 | S-061 |
| PRD.CLR.022 | Demolish & remove minor structure (shed / slab / hardstand, <=50 m2) | m2/hr | 15 | 30 | 60 | S-061 |
Construction references
- Bulk Earthworks Formation
- Soft Ground Embankment and Staged Filling
- Rock Excavation Ripping Hammer and Drill and Blast