Discipline library

Earthworks and bulk civil

Release clearing and environmental limits, then segregate cut, place fill in accepted lifts and hand over formation by zone.

Earthworks and bulk civil
  1. Cut faceMeasure excavation on the agreed bank-volume basis.
  2. Articulated truckThe return and loading cycle limits the haul spread.
  3. Placed liftSurvey the compacted fill before releasing the next lift.
Illustrative workfront within Earthworks and bulk civil.

Construction and release sequence

  1. Release clearing limits and erosion controls
  2. Strip and survey the cut and fill zones
  3. Haul classified material and compact by lift
  4. Release the surveyed formation with density results

Work packages and conformance checks

Production and measurement

Distinguish bank, loose and compacted volume. Measure haul and rehandling where the site balance requires them.

View the discipline reference figureEarthworks and bulk civil reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.EW.001Strip & stockpile topsoilm3/hr120200320S-061
PRD.EW.002Bulk excavation cut-to-fill (30t excavator + truck fleet)m3/hr80120160S-061
PRD.EW.003Cut-to-spoil (excavator load-out, no on-site reuse)m3/hr (loading limited)90130170S-061
PRD.EW.004Dozer push (short haul, cut-to-fill <100 m)m3/hr (falls sharply >70 m and uphill)150300500S-061
PRD.EW.005Scraper cut / haul / spread (self-loading or push-loaded)m3/hr per scraper (haul-distance dependent)150300600S-061
PRD.EW.006Load & haul - 0.5 km one-way (exc + tippers)m3/hr90130170S-061
PRD.EW.007Load & haul - 1 km one-waym3/hr70110150S-061
PRD.EW.008Load & haul - 2 km one-waym3/hr5590130S-061
PRD.EW.009Load & haul - 5 km one-waym3/hr4065100S-061
PRD.EW.010Import select fill (supply + place + compact)m3/hr (placing crew)60100150S-061
PRD.EW.011Rock excavation - rippable (D8/D10 ripping)m3/hr (rock strength dependent)4080130S-061
PRD.EW.012Rock excavation - hydraulic hammer / rock-breakerm3/hr82045S-061
PRD.EW.014Spread & level fill (place dumped material to grade)m3/hr150300500S-061
PRD.EW.015Compact fill - by layer (roller passes)m3/hr at 200 mm lift (slower at 300 mm / 6-8 passes)150300500S-061
PRD.EW.016Moisture condition / water fill (OMC ±2%)m3/hr200400700S-061
PRD.EW.017Trim & batter to design (final shaping)m2/hr3006001000S-061
PRD.EW.018Proof roll formation/subgradem2/hr150030005000S-061
PRD.EW.019Subgrade preparation / CBR conditioningm2/hr200400700S-061
PRD.EW.020Borrow pit operation (win + process + load)m3/hr (winning rate)100200400S-061
PRD.CLR.001Clear & grub - light grass / sparse scrub (<1 tree per 100 m2, <150 mm girth)ha/hr0.81.21.5S-061
PRD.CLR.002Clear & grub - light grass / sparse scrubm2/hr80001100015000S-061
PRD.CLR.003Clear & grub - medium scrub / regrowth (scattered trees 150-300 mm girth, dense low scrub)ha/hr0.350.550.8S-061
PRD.CLR.004Clear & grub - heavy timber / closed forest (continuous canopy, frequent trees >300 mm)ha/hr0.080.150.3S-061
PRD.CLR.005Individual tree removal - small (<300 mm girth/diameter at 1.4 m)trees/hr81420S-061
PRD.CLR.006Individual tree removal - medium (300-600 mm girth)trees/hr358S-061
PRD.CLR.007Individual tree removal - large (600-900 mm girth)trees/hr123S-061
PRD.CLR.008Individual tree removal - very large (>900 mm girth)trees/hr0.30.71.2S-061
PRD.CLR.009Stump grinding (in-situ, root system left)Small -/hr · Med -/hr · Large -/hr1510S-061
PRD.CLR.010Stump / root ball removal (excavate & extract)Small -/hr · Med -/hr · Large -/hr0.548S-061
PRD.CLR.011Grub roots / remove organic material (strip area, post-clearing)m2/hr150025004000S-061
PRD.CLR.012Topsoil strip & stockpile - shallow (<=150 mm)m2/hr120020003000S-061
PRD.CLR.013Topsoil strip & stockpile - medium (150-300 mm)m2/hr90014002200S-061
PRD.CLR.014Topsoil strip & stockpile - deep (>300 mm)m3/hr (load & short haul)6090140S-061
PRD.CLR.015Mulch / chip arisings in-situ (forestry/horizontal mulcher or chipper)ha/hr0.150.30.55S-061
PRD.CLR.016Chip individual fell material (mobile chipper)m3/hr (loose)81422S-061
PRD.CLR.017Windrow & burn (where permitted)ha/hr (push only)0.40.71.2S-061
PRD.CLR.018Load & cart mulch / cleared spoil off-site to disposalLoad - m3/hr; cart governed by cycle60110110S-061
PRD.CLR.020Demolish & remove fencing (rural/chainmesh/timber)m/hr3060100S-061
PRD.CLR.021Remove signs / posts / small roadside furnitureea/hr4814S-061
PRD.CLR.022Demolish & remove minor structure (shed / slab / hardstand, <=50 m2)m2/hr153060S-061