Rail and track systems
- Track machineMachine access and possession windows govern the productive shift.
- Sleepers and railTrack geometry and installation records identify the work lot.
- BallastConfirm support and formation before accepting the track.
Construction and release sequence
- Secure possessions, survey control and formation access
- Place ballast, sleepers and rails by track section
- Weld, stress, tamp and coordinate signalling and overhead interfaces
- Release geometry, test records and possession handback
Work packages and conformance checks
Rail Welding, CWR De-stressing & Special TrackworkSurvey switch and crossing geometry, reference marks and track tie-in levels.Overhead Wiring & Traction (OHW / OLE)Check mast position, contact-wire height and stagger against the accepted track geometry.Signalling, Train Control, Level Crossings & PossessionLocate signals, equipment cases and cable crossings against asset and track references.Track Formation & StructureMeasure alignment, gauge, crosslevel and longitudinal level by track chainage.
Production and measurement
Possession time, setup and handback can govern productive hours for every trade.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.RL.001 | Trackbed formation prep & proof-roll | m2/day | 2000 | 3000 | 4000 | S-076 |
| PRD.RL.002 | Capping / blanket structural-fill place | m3/day | 200 | 400 | 700 | S-076 |
| PRD.RL.003 | Bottom ballast place & profile | m3/day | 150 | 300 | 500 | S-076 |
| PRD.RL.004 | Concrete sleeper lay on ballast | no/day | 200 | 400 | 700 | S-076 |
| PRD.RL.005 | Thread / lay rail to sleepers | m/day | 200 | 500 | 1000 | S-076 |
| PRD.RL.006 | Top ballast place, box & shoulder | m3/day | 200 | 400 | 600 | S-076 |
| PRD.RL.007 | Tamp, line, level & regulate plain line | m/day | 800 | 2000 | 4000 | S-076 |
| PRD.RL.008 | Turnout (points & crossing) install | no/week | 0.5 | 1 | 2 | S-076 |
| PRD.RL.009 | Flash-butt rail weld | no/shift | 40 | 70 | 100 | S-076 |
| PRD.RL.010 | CWR stressing / destress to neutral | m/shift | 200 | 500 | 1000 | S-076 |
| PRD.RL.011 | Road/rail level crossing panels | m/day | 5 | 15 | 30 | S-076 |
Construction references
- Track Formation Plain-Line Construction
- Overhead Wiring Electrification and Energisation
- Signalling Train Control and Commissioning