Traffic management and road furniture
- Protection vehicleInclude the setup, moves and standby for the active front.
- Traffic taperCheck the implemented layout against the approved staging plan.
- Safety barrierInspect the completed run and terminal before opening the lane.
Construction and release sequence
- Approve staging, device locations and lane-closure windows
- Establish the temporary work zone and verify access
- Install permanent barriers, signs, markings and terminals
- Inspect alignment and release each stage to the road operator
Work packages and conformance checks
Road Safety Barriers & TerminalsCheck roadside offset, installed height, transitions and terminal locations by chainage.Pavement Marking & RRPMsSurvey line offsets, taper endpoints, symbols and raised marker positions against the traffic layout.Road Signs & Support StructuresLocate supports and check mounting height, lateral offset and orientation.Worksite Traffic Management — TMP/TGS, devices & maintenance-of-trafficSet out stage limits and check temporary device locations before opening the changed arrangement.
Production and measurement
Track device hire by occupied shift and installation by run or asset.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.TM.001 | TMP / TGS design & approval (standard low-complexity) | days/scheme | 0.5 | 1 | 2 | S-061 |
| PRD.TM.002 | TMP / TGS design & approval (complex, RoadManager/TMR submission) | days/scheme | 1 | 3 | 5 | S-061 |
| PRD.TM.010 | Water-filled barrier - supply, place & remove | m/day place & fill | 150 | 300 | 450 | S-061 |
| PRD.TM.011 | Cones / bollards / temporary signs - daily setup & pack-down | set/take per shift; ~- hr each | 0.5 | 0.5 | 1 | S-061 |
| PRD.TM.017 | Lane / road closure - setup & removal (per closure event) | closures set/removed per day | 1 | 2 | 2 | S-061 |
Construction references
- Temporary Traffic Management
- Permanent Signs Linemarking and Safety Barriers