Water and wastewater

Release alignment and connection points, install the selected reticulation or trenchless crossing, then hand over pump and network test sections.

Water and wastewater
  1. Wet wellCheck the structure and connection levels before mechanical installation.
  2. Pump setPlan the lift and assembly against available access.
  3. Discharge mainTrack pressure or functional test records for the completed connection.
Illustrative workfront within Water and wastewater.

Construction and release sequence

  1. Confirm isolations, pipe alignment and receiving interfaces
  2. Lay open-cut or trenchless sections and construct structures
  3. Complete joints, thrust restraint, fittings and pump installation
  4. Reconcile pressure tests, survey and connection approval

Work packages and conformance checks

Production and measurement

Separate pipe lengths by diameter and depth, connections, bypasses and commissioning attendances.

View the discipline reference figureWater and wastewater reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.SV.001Conduit trench & install - single 1-way (<=100 mm)m/day60120180S-061
PRD.SV.002Conduit trench & install - multi-way 2-4 way bankm/day3570110S-061
PRD.SV.004Cable hauling into installed conduit (LV/HV/comms)m/day200500900S-061
PRD.SV.005Electrical/comms pit - small (e.g. Energex P-series / NBN P1-P4)per day369S-061
PRD.SV.006Electrical/comms manhole - large (HV cable / comms joint bay)per day0.51.53S-061
PRD.SV.007Water main lay - DN100 (PVC-O / DICL)m/day60110150S-061
PRD.SV.008Water main lay - DN150 (PVC-O / DICL)m/day4080110S-061
PRD.SV.009Water main lay - DN200-DN300 (DICL / PVC-O)m/day306090S-061
PRD.SV.011Water fittings - valves / hydrants / scour (each, installed)per day258S-061
PRD.SV.012Thrust / anchor block (cast in-situ, at bends/tees)per day3610S-061
PRD.SV.013Sewer gravity main lay - DN150-DN225 (PVC/uPVC)m/day306085S-061
PRD.SV.014Sewer gravity main lay - DN300-DN450 (PVC / VC / RC)m/day204570S-061
PRD.SV.015Sewer maintenance hole (MH) - precast, <=2.5 m deepper day1.534S-061
PRD.SV.017Sewer rising main lay - DN100-DN200 (PE100 / DICL)m/day4075110S-061
PRD.SV.018Service connection - water/sewer property tie-in (each)per day258S-061
PRD.SV.019Bend / junction / tapping band (each, installed)per day4812S-061
PRD.SV.020Pressure / hydrostatic & leak test (per section)sections/day135S-061
PRD.SV.021Swab / chlorinate / bacteriological clearance (water main)sections/day124S-061
PRD.SV.022CCTV inspection & proof (gravity sewer / drainage)m/day300600900S-061
PRD.SV.023Potholing / non-destructive digging (NDD) of existing serviceholes/day61422S-061
PRD.SV.025Service crossing / protection (existing service in the dig)per day146S-061