Water and wastewater
- Wet wellCheck the structure and connection levels before mechanical installation.
- Pump setPlan the lift and assembly against available access.
- Discharge mainTrack pressure or functional test records for the completed connection.
Construction and release sequence
- Confirm isolations, pipe alignment and receiving interfaces
- Lay open-cut or trenchless sections and construct structures
- Complete joints, thrust restraint, fittings and pump installation
- Reconcile pressure tests, survey and connection approval
Work packages and conformance checks
Pump Stations — Sewage & WaterCheck wet-well invert, pipe penetrations, pump guides and discharge connection levels.Pressure Reticulation — Valves, Hydrants, Fittings & ConnectionsPick up joints, valves, bends and cover at crossings before trench closure.Trenchless Pipe InstallationTie entry and exit points and the verified bore trajectory to a common control network.
Production and measurement
Separate pipe lengths by diameter and depth, connections, bypasses and commissioning attendances.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.SV.001 | Conduit trench & install - single 1-way (<=100 mm) | m/day | 60 | 120 | 180 | S-061 |
| PRD.SV.002 | Conduit trench & install - multi-way 2-4 way bank | m/day | 35 | 70 | 110 | S-061 |
| PRD.SV.004 | Cable hauling into installed conduit (LV/HV/comms) | m/day | 200 | 500 | 900 | S-061 |
| PRD.SV.005 | Electrical/comms pit - small (e.g. Energex P-series / NBN P1-P4) | per day | 3 | 6 | 9 | S-061 |
| PRD.SV.006 | Electrical/comms manhole - large (HV cable / comms joint bay) | per day | 0.5 | 1.5 | 3 | S-061 |
| PRD.SV.007 | Water main lay - DN100 (PVC-O / DICL) | m/day | 60 | 110 | 150 | S-061 |
| PRD.SV.008 | Water main lay - DN150 (PVC-O / DICL) | m/day | 40 | 80 | 110 | S-061 |
| PRD.SV.009 | Water main lay - DN200-DN300 (DICL / PVC-O) | m/day | 30 | 60 | 90 | S-061 |
| PRD.SV.011 | Water fittings - valves / hydrants / scour (each, installed) | per day | 2 | 5 | 8 | S-061 |
| PRD.SV.012 | Thrust / anchor block (cast in-situ, at bends/tees) | per day | 3 | 6 | 10 | S-061 |
| PRD.SV.013 | Sewer gravity main lay - DN150-DN225 (PVC/uPVC) | m/day | 30 | 60 | 85 | S-061 |
| PRD.SV.014 | Sewer gravity main lay - DN300-DN450 (PVC / VC / RC) | m/day | 20 | 45 | 70 | S-061 |
| PRD.SV.015 | Sewer maintenance hole (MH) - precast, <=2.5 m deep | per day | 1.5 | 3 | 4 | S-061 |
| PRD.SV.017 | Sewer rising main lay - DN100-DN200 (PE100 / DICL) | m/day | 40 | 75 | 110 | S-061 |
| PRD.SV.018 | Service connection - water/sewer property tie-in (each) | per day | 2 | 5 | 8 | S-061 |
| PRD.SV.019 | Bend / junction / tapping band (each, installed) | per day | 4 | 8 | 12 | S-061 |
| PRD.SV.020 | Pressure / hydrostatic & leak test (per section) | sections/day | 1 | 3 | 5 | S-061 |
| PRD.SV.021 | Swab / chlorinate / bacteriological clearance (water main) | sections/day | 1 | 2 | 4 | S-061 |
| PRD.SV.022 | CCTV inspection & proof (gravity sewer / drainage) | m/day | 300 | 600 | 900 | S-061 |
| PRD.SV.023 | Potholing / non-destructive digging (NDD) of existing service | holes/day | 6 | 14 | 22 | S-061 |
| PRD.SV.025 | Service crossing / protection (existing service in the dig) | per day | 1 | 4 | 6 | S-061 |