Airfields and airports
- Paving trainSequence plant access within the agreed airside work window.
- Pavement stripControl the joint, profile and accepted paving area.
- Edge lightingCheck the lighting interface before handing the strip back.
Construction and release sequence
- Agree airside staging and operational handback boundaries
- Release subgrade, drainage and lighting ducts
- Construct pavement, then fit lights, markings and signs
- Reconcile surface survey and applicable operational acceptance
Work packages and conformance checks
Airfield Ground Lighting (AGL) & Airside ElectricalSurvey light centres, elevations and duct crossings relative to runway or taxiway control.Airside Operations, Live-Airport Staging & Acceptance TestingMap the approved work limits, temporary markings and reopening boundaries.Airfield Drainage, Markings, Signage, Wildlife & SecurityCheck outfall levels, marking geometry and sign positions against the airfield layout.Airfield Pavement — flexible (asphalt) & rigid (PQC)Measure finished levels, grades and transitions at runway or taxiway interfaces.
Production and measurement
Allow separately for short closures, lighting tests and inspection before reopening.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.AP.001 | Slipform PQC placement (continuous taxiway/runway lane) | m3/day | 400 | 600 | 800 | S-065 |
| PRD.AP.002 | Fixed-form PQC apron slabs (irregular, pits/edges) | m3/day | 120 | 220 | 350 | S-065 |
| PRD.AP.003 | DLC/cement-treated subbase placement & trim | m3/day | 600 | 1000 | 1500 | S-065 |
| PRD.AP.004 | Green-saw contraction joints | m/day | 800 | 1500 | 2500 | S-065 |
| PRD.AP.005 | Airfield asphalt place & compact (night-window resurfacing) | t/hr | 120 | 170 | 250 | S-065 |
| PRD.AP.006 | Echelon paving area output (two-paver new works) | m2/shift | 6000 | 9000 | 13000 | S-065 |
| PRD.AP.007 | Cold-mill existing asphalt (profiling for overlay) | m2/shift | 2500 | 5000 | 9000 | S-065 |
| PRD.AP.008 | Inset light install (saw-cut slot, deep-base, transformer, fitting set-to-level) | no/day | 4 | 8 | 14 | S-065 |
| PRD.AP.009 | Elevated edge light install (frangible base, transformer, fitting) | no/day | 15 | 30 | 50 | S-065 |
| PRD.AP.010 | Primary series cable pull-in (slot/duct) | m/day | 300 | 700 | 1500 | S-065 |
| PRD.AP.011 | Saw-cut cable slot in pavement | m/day | 200 | 400 | 800 | S-065 |
| PRD.AP.012 | Saw-cut transverse grooving (asphalt wearing course) | m2/shift | 2000 | 4000 | 7000 | S-065 |
| PRD.AP.013 | Saw-cut transverse grooving (PCC surface) | m2/shift | 1200 | 2500 | 4500 | S-065 |
| PRD.AP.014 | Continuous friction survey (CFME run) | km/hr | 30 | 60 | 95 | S-065 |
| PRD.AP.015 | Strip/RESA bulk earthworks (cut/fill, graded area) | m3/day | 800 | 2000 | 5000 | S-065 |
| PRD.AP.016 | Graded-area trim to MOS slope/smoothness (grader) | m2/day | 4000 | 9000 | 16000 | S-065 |
| PRD.AP.017 | Sealed shoulder - sprayed seal | m2/day | 6000 | 12000 | 20000 | S-065 |
| PRD.AP.018 | Navaid/visual-aid concrete footings (excavate, cast, cure) | no/day | 2 | 4 | 8 | S-065 |
| PRD.AP.019 | Guidance/mandatory sign install (frangible, set & connect) | no/day | 3 | 6 | 12 | S-065 |
| PRD.AP.020 | PAPI unit install & align (excl. flight check) | no/day | 1 | 2 | 4 | S-065 |
| PRD.AP.021 | Stormwater pipe lay (RC/HDPE, <1.5 m depth) | m/day | 30 | 60 | 100 | S-065 |
| PRD.AP.022 | Subsoil/edge drain install | m/day | 80 | 150 | 300 | S-065 |
| PRD.AP.023 | Field-inlet/junction pit construct | no/day | 1 | 2 | 4 | S-065 |
| PRD.AP.024 | Saw-cut joint reservoir (reservoir saw) | m/day | 600 | 1200 | 2000 | S-065 |
| PRD.AP.025 | Clean, backer-rod & seal (silicone, gun) | m/day | 300 | 600 | 1000 | S-065 |
| PRD.AP.026 | Asphalt crack/joint seal (hot-pour) | m/day | 500 | 1200 | 2500 | S-065 |
| PRD.AP.027 | Linear markings apply (machine, incl. beads) | m2/day | 1500 | 3500 | 6000 | S-065 |
| PRD.AP.028 | Designations/symbols apply (template/hand) | m2/day | 200 | 500 | 900 | S-065 |
| PRD.AP.029 | Marking removal (high-pressure waterblast) | m2/day | 400 | 1000 | 2500 | S-065 |