Airfields and airports

Stage access around operating areas. Release pavement, drainage and lighting circuits by zone, then verify markings and operational handback.

Airfields and airports
  1. Paving trainSequence plant access within the agreed airside work window.
  2. Pavement stripControl the joint, profile and accepted paving area.
  3. Edge lightingCheck the lighting interface before handing the strip back.
Illustrative workfront within Airfields and airports.

Construction and release sequence

  1. Agree airside staging and operational handback boundaries
  2. Release subgrade, drainage and lighting ducts
  3. Construct pavement, then fit lights, markings and signs
  4. Reconcile surface survey and applicable operational acceptance

Work packages and conformance checks

Production and measurement

Allow separately for short closures, lighting tests and inspection before reopening.

View the discipline reference figureAirfields and airports reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.AP.001Slipform PQC placement (continuous taxiway/runway lane)m3/day400600800S-065
PRD.AP.002Fixed-form PQC apron slabs (irregular, pits/edges)m3/day120220350S-065
PRD.AP.003DLC/cement-treated subbase placement & trimm3/day60010001500S-065
PRD.AP.004Green-saw contraction jointsm/day80015002500S-065
PRD.AP.005Airfield asphalt place & compact (night-window resurfacing)t/hr120170250S-065
PRD.AP.006Echelon paving area output (two-paver new works)m2/shift6000900013000S-065
PRD.AP.007Cold-mill existing asphalt (profiling for overlay)m2/shift250050009000S-065
PRD.AP.008Inset light install (saw-cut slot, deep-base, transformer, fitting set-to-level)no/day4814S-065
PRD.AP.009Elevated edge light install (frangible base, transformer, fitting)no/day153050S-065
PRD.AP.010Primary series cable pull-in (slot/duct)m/day3007001500S-065
PRD.AP.011Saw-cut cable slot in pavementm/day200400800S-065
PRD.AP.012Saw-cut transverse grooving (asphalt wearing course)m2/shift200040007000S-065
PRD.AP.013Saw-cut transverse grooving (PCC surface)m2/shift120025004500S-065
PRD.AP.014Continuous friction survey (CFME run)km/hr306095S-065
PRD.AP.015Strip/RESA bulk earthworks (cut/fill, graded area)m3/day80020005000S-065
PRD.AP.016Graded-area trim to MOS slope/smoothness (grader)m2/day4000900016000S-065
PRD.AP.017Sealed shoulder - sprayed sealm2/day60001200020000S-065
PRD.AP.018Navaid/visual-aid concrete footings (excavate, cast, cure)no/day248S-065
PRD.AP.019Guidance/mandatory sign install (frangible, set & connect)no/day3612S-065
PRD.AP.020PAPI unit install & align (excl. flight check)no/day124S-065
PRD.AP.021Stormwater pipe lay (RC/HDPE, <1.5 m depth)m/day3060100S-065
PRD.AP.022Subsoil/edge drain installm/day80150300S-065
PRD.AP.023Field-inlet/junction pit constructno/day124S-065
PRD.AP.024Saw-cut joint reservoir (reservoir saw)m/day60012002000S-065
PRD.AP.025Clean, backer-rod & seal (silicone, gun)m/day3006001000S-065
PRD.AP.026Asphalt crack/joint seal (hot-pour)m/day50012002500S-065
PRD.AP.027Linear markings apply (machine, incl. beads)m2/day150035006000S-065
PRD.AP.028Designations/symbols apply (template/hand)m2/day200500900S-065
PRD.AP.029Marking removal (high-pressure waterblast)m2/day40010002500S-065