Airfields and airports

Airfield Pavement — flexible (asphalt) & rigid (PQC)

Measure finished levels, grades and transitions at runway or taxiway interfaces.

Airfields and airports
  1. Paving trainSequence plant access within the agreed airside work window.
  2. Pavement stripControl the joint, profile and accepted paving area.
  3. Edge lightingCheck the lighting interface before handing the strip back.
Construction context for Airfield Pavement — flexible (asphalt) & rigid (PQC)

Work scope and interfaces

What it is & where used

Runways, taxiways, taxilanes, holding bays, aprons/hardstands. Flexible suits runways/taxiways; rigid PQC suits aprons/hardstands and heavy-turning/standing areas (better fuel/heat resistance).

Related work packages

Construction sequence

  1. Accept subgrade/formation (bulk earthworks → Earthworks; proof-roll to CBR + lime/cement stab AP.02)
  2. FLEXIBLE: granular subbase
  3. Base (or cement/foamed-bitumen stabilised base)
  4. Prime/primerseal
  5. DGA binder
  6. DGA wearing course
  7. Grooving + friction. RIGID: DLC subbase
  8. Set dowels/tie bars + reo
  9. Place/finish/cure PQC slabs (fixed-form or slip-form)
  10. Saw-cut & seal contraction/expansion joints
  11. Surface texture (broom/tine) + curing compound
  12. Apron fuel-resistant sealer. All staged under live-airport windows (Airside Operations, Live-Airport Staging & Acceptance Testing); acceptance = friction/regularity/FWD (AP.08).

The make-or-break: surface tolerance, ride & friction to MOS 139 (an out-of-tolerance runway fails acceptance — re-grind/re-lay), the PQC joint/dowel detail (slab performance), and paving within operational windows (continuity of asphalt/concrete supply against curfew).

Plant, resources and measurement

L.CREW.ASPHALT / L.CREW.CONCRETE + PLANT-PAVER (asphalt) / PLANT-SLIPFORM-001 (PQC); materials M.ASPH.AIRFIELD, M.CONC.PQC, granular, DLC, dowels/reo, sealer. Measured: granular subbase/base m³, stabilised base m², prime m², asphalt t, mill/profile m², grooving m², construction joint m (flexible AP.03); DLC m³, PQC m³, dowel/tie no, joint saw/seal m, reo t, texture/cure m², fuel-resistant sealer m² (rigid AP.04). Priced items: AP.03.* (flexible) + AP.04.* (rigid); subgrade/earthworks AP.02.* (bulk → EW.*). Asphalt by t, PQC by m³ — to airfield mix/strength spec.

Allow separately for short closures, lighting tests and inspection before reopening.

View Airfields and airports productivity references

Package productivity

Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.

Component activityPublished basisLowTypicalHighLibrary source
Slipform PQC placement (continuous taxiway/runway lane)PRD.AP.001m3/day400600800S-065
Airfield asphalt place & compact (night-window resurfacing)PRD.AP.005t/hr120170250S-065

Component duration

Survey conformance and lot release

Observe
Measure finished levels, grades and transitions at runway or taxiway interfaces.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Link surface profile and specified pavement test results to the operational release lot.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations

Subgrade proof-roll/CBR, granular density/grading, asphalt mix/compaction/temperature, PQC strength/slump/cure, joint saw-timing & seal, dowel alignment, surface regularity/ride + friction + grooving (the acceptance, AP.08). Risks: friction/regularity non-conformance (re-grind/re-do — costly on a runway); PQC joint/dowel defects (slab failure); asphalt/concrete supply continuity within curfew windows; subgrade variability (→ Earthworks/ the site conditions geotechnical review); fuel/heat damage on aprons if rigid not used. Pairs with airside staging (Airside Operations, Live-Airport Staging & Acceptance Testing) and AGL/drainage in the pavement (Airfield Ground Lighting (AGL) & Airside Electrical, Airfield Drainage, Markings, Signage, Wildlife & Security).

Evidence and related work

Internal record AP-PAVEMENT-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.