- Working platformConfirm the released platform and rig setup for the pile location.
- Temporary casingCasing installation and recovery affect cycle time.
- Reinforcement cageLink the cage inspection and concrete records to the pile ID.
Construction and release sequence
- Confirm ground model, platform and trial requirements
- Install the selected pile family or excavate shallow foundations
- Inspect founding conditions, test and survey completed elements
- Release pile cut-offs, caps and ground beams to the frame
Work packages and conformance checks
Technique rates and labour allowances
The source records typical values. Its hourly allowances, output rates and shift quantities each retain their published basis.
| Component activity | Published basis | Low | Typical | High | Library source |
|---|---|---|---|---|---|
| Bored cast-in-situ pile, 600 mm dia - supply & install (exclFN.01.010.01 | m/hr | — | 8.9 | — | PROD-FND-001 |
| Bored cast-in-situ pile, 750 mm diaFN.01.010.02 | m/hr | — | 7 | — | PROD-FND-001 |
| Bored cast-in-situ pile, 900 mm diaFN.01.010.03 | m/hr | — | 5.6 | — | PROD-FND-001 |
| Bored cast-in-situ pile, 1200 mm diaFN.01.010.04 | m/hr | — | 3.2 | — | PROD-FND-001 |
| CFA pile, 450 mm dia - supply & install (excl. reo)FN.01.020.01 | m/hr | — | 39 | — | PROD-FND-001 |
| CFA pile, 600 mm dia - supply & install (excl. reo)FN.01.020.02 | m/hr | — | 25 | — | PROD-FND-001 |
| Extra-over bored/CFA pile for rock socket (drilling in rock)FN.01.030.01 | m/hr | — | 2 | — | PROD-FND-001 |
| Permanent steel casing - supply & leave in placeFN.01.040.01 | m/hr | — | 12 | — | PROD-FND-001 |
| Pile reinforcement cage - supply, fabricate, placeFN.01.050.01 | t/hr | — | 1.2 | — | PROD-FND-001 |
| Static / dynamic pile load testingFN.01.080.01 | hr/unit (labour-hours) | — | 36 | — | PROD-FND-001 |
| Micropile (drilled & grouted) - by lengthFN.01.090.01 | m/hr | — | 8 | — | PROD-FND-001 |
| Driven precast prestressed concrete pile, 450x450 - supply &FN.02.010.01 | m/hr | — | 30 | — | PROD-FND-001 |
| Driven steel tube pile - supply & driveFN.02.020.01 | m/hr | — | 25 | — | PROD-FND-001 |
| Excavate for pile cap / footing incl. trim, dewater allowancFN.03.010.01 | m3/hr | — | 25 | — | PROD-FND-001 |
| Pile cap / footing concrete (special-class) - supply, place,FN.03.020.01 | m3/hr | — | 18 | — | PROD-FND-001 |
| Pile cap / footing reinforcementFN.03.030.01 | t/hr | — | 1.5 | — | PROD-FND-001 |
| Formwork to pile cap / footingFN.03.040.01 | m2/hr | — | 8 | — | PROD-FND-001 |
| Blinding concrete under cap / footingFN.03.050.01 | m3/hr | — | 25 | — | PROD-FND-001 |
| Mobilisation of plant, crews and facilities to site (establiFN.90.010.01 | hr (direct) | — | 72 | — | PROD-FND-001 |
| Demobilisation and site restoration on completionFN.90.020.01 | hr (direct) | — | 36 | — | PROD-FND-001 |
| Time-related site costs (supervision, facilities, plant stanFN.90.030.01 | hr (direct) | — | 45 | — | PROD-FND-001 |
| Standing time / standby due to Principal-caused delay (per hFN.90.040.01 | hr (direct) | — | 1 | — | PROD-FND-001 |
Production and measurement
Separate installed length, socket or treatment extras, testing and rig mobilisation.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
Use the linked discipline record and measured project outputs to establish the planning basis.
Construction references
- Bored Pile Construction
- CFA Pile Construction
- Driven Pile Construction