Foundations and piling

Select the foundation system from the issued design. Release the platform, verify founding or termination, then cut off and hand over to the cap crew.

Foundations and piling
  1. Working platformConfirm the released platform and rig setup for the pile location.
  2. Temporary casingCasing installation and recovery affect cycle time.
  3. Reinforcement cageLink the cage inspection and concrete records to the pile ID.
Illustrative workfront within Foundations and piling.

Construction and release sequence

  1. Confirm ground model, platform and trial requirements
  2. Install the selected pile family or excavate shallow foundations
  3. Inspect founding conditions, test and survey completed elements
  4. Release pile cut-offs, caps and ground beams to the frame

Work packages and conformance checks

Technique rates and labour allowances

The source records typical values. Its hourly allowances, output rates and shift quantities each retain their published basis.

Component activityPublished basisLowTypicalHighLibrary source
Bored cast-in-situ pile, 600 mm dia - supply & install (exclFN.01.010.01m/hr—8.9—PROD-FND-001
Bored cast-in-situ pile, 750 mm diaFN.01.010.02m/hr—7—PROD-FND-001
Bored cast-in-situ pile, 900 mm diaFN.01.010.03m/hr—5.6—PROD-FND-001
Bored cast-in-situ pile, 1200 mm diaFN.01.010.04m/hr—3.2—PROD-FND-001
CFA pile, 450 mm dia - supply & install (excl. reo)FN.01.020.01m/hr—39—PROD-FND-001
CFA pile, 600 mm dia - supply & install (excl. reo)FN.01.020.02m/hr—25—PROD-FND-001
Extra-over bored/CFA pile for rock socket (drilling in rock)FN.01.030.01m/hr—2—PROD-FND-001
Permanent steel casing - supply & leave in placeFN.01.040.01m/hr—12—PROD-FND-001
Pile reinforcement cage - supply, fabricate, placeFN.01.050.01t/hr—1.2—PROD-FND-001
Static / dynamic pile load testingFN.01.080.01hr/unit (labour-hours)—36—PROD-FND-001
Micropile (drilled & grouted) - by lengthFN.01.090.01m/hr—8—PROD-FND-001
Driven precast prestressed concrete pile, 450x450 - supply &FN.02.010.01m/hr—30—PROD-FND-001
Driven steel tube pile - supply & driveFN.02.020.01m/hr—25—PROD-FND-001
Excavate for pile cap / footing incl. trim, dewater allowancFN.03.010.01m3/hr—25—PROD-FND-001
Pile cap / footing concrete (special-class) - supply, place,FN.03.020.01m3/hr—18—PROD-FND-001
Pile cap / footing reinforcementFN.03.030.01t/hr—1.5—PROD-FND-001
Formwork to pile cap / footingFN.03.040.01m2/hr—8—PROD-FND-001
Blinding concrete under cap / footingFN.03.050.01m3/hr—25—PROD-FND-001
Mobilisation of plant, crews and facilities to site (establiFN.90.010.01hr (direct)—72—PROD-FND-001
Demobilisation and site restoration on completionFN.90.020.01hr (direct)—36—PROD-FND-001
Time-related site costs (supervision, facilities, plant stanFN.90.030.01hr (direct)—45—PROD-FND-001
Standing time / standby due to Principal-caused delay (per hFN.90.040.01hr (direct)—1—PROD-FND-001

Production and measurement

Separate installed length, socket or treatment extras, testing and rig mobilisation.

View the discipline reference figureFoundations and piling reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

Use the linked discipline record and measured project outputs to establish the planning basis.