Foundations and piling

Micropiles — drilled & grouted

Locate each pile head and inclination. Tie socket or bond length to the drilling log and reference level.

Soil Nail Drilling Rig
  1. Feed beamSet the drilling orientation to the released nail location.
  2. Drill rodRecord achieved depth and ground response.
  3. Crawler baseInclude repositioning between nail rows.
Plant reference for Micropiles — drilled & grouted

Work scope and interfaces

What it is & where used

Used for underpinning existing foundations, low-headroom / restricted-access sites (inside buildings, under bridges), foundations in karst/boulders/variable rock, seismic retrofits, tension/tie-down anchorage, and machine foundations. Where a conventional pile rig fits and loads are moderate-high, a bored/driven pile is usually cheaper — micropiles win on access and difficult ground.

Related work packages

Construction sequence

  1. Position compact drill rig (PLANT-DRILL-ANCHOR) in restricted/low-headroom space
  2. Drill cased hole through soil into the competent bond zone
  3. Insert reinforcement (threaded bar / tube, with centralisers + corrosion protection)
  4. Grout (tremie/gravity, then pressure/post-grout the bond zone)
  5. Withdraw temporary casing
  6. Fit bearing plate / connection
  7. PROOF / acceptance load test selected piles
  8. Connect to structure / underpin.

The make-or-break: the bond zone in competent ground (length & grouting govern capacity — and verifying the ground in a small hole is harder), and access/headroom logistics (the reason to use micropiles, and the thing that slows them — many short stages, hand-handling).

Plant, resources and measurement

L.CREW.PILE.MICRO + PLANT-DRILL-ANCHOR (compact anchor/micropile drill); materials M.BAR.THREADED (GEWI/self-drilling bar or tube), M.GROUT.CEMENT, casing, centralisers, bearing plates. Measured: micropile per m (by length) (FN.01.090), integrity / proof-load test per no (FN.01.070 / FN.01.080); grout by volume / deemed. The restricted-access / low-headroom premium, the drill-method-by-ground band and the post-grouting option must show — a flat $/m hides the access reality that defines micropiling.

Separate installed length, socket or treatment extras, testing and rig mobilisation.

View Foundations and piling productivity references

Package productivity

Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.

Component activityPublished basisLowTypicalHighLibrary source
Micropile (drilled & grouted) - by lengthFN.01.090.01m/hr—8—PROD-FND-001

Component duration

Survey conformance and lot release

Observe
Locate each pile head and inclination. Tie socket or bond length to the drilling log and reference level.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Identify the installed pile on the grouting and load-test register before cap release.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations

Drill method/depth, bond-zone verification, bar/grout certs + corrosion protection, grout volume vs theoretical (over-break / loss in karst), proof / acceptance load test (the capacity proof), connection detail. Risks: variable ground / grout take (karst, boulders, fissured rock — quantity & grout blow-out → route to the site conditions geotechnical review); access/headroom productivity; corrosion (aggressive ground → double protection); achieving capacity in poor bond zones. Pairs with rock-socketed piles (Rock-Socketed Piles) and ground anchors/soil nails (Geotechnical discipline, GT.04).

Evidence and related work

Internal record PILE-TYPE-006 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.