Piled wharf construction
- Precast deckDeck units span between headstocks. Keep the open bay available for scour placement and inspection.
- Steel pilesThe accepted pile-head group releases the cap and scour crews.
- Crane pontoonVessel access and positioning determine which bay the lifting spread can serve.
Construction and release sequence
- Establish hydrographic control and release the dredge area
- Survey the dredge cut and release the piling footprint
- Install piles and scour protection in the approved bay sequence
- Complete the wharf deck, berth fittings and handover survey
Work packages and conformance checks
Cathodic Protection (CP)Locate anodes, reference electrodes, test points and cables before covering or immersion.CofferdamsSurvey pile-wall corners, top levels and bracing interfaces relative to marine control.Dredging & ReclamationReduce pre- and post-dredge soundings to the agreed vertical datum and compare common survey boundaries.Marine & Raked PilingObserve pile centre and rake at identified elevations, then record cut-off level on the project datum.Scour Protection — rock armour, mattresses & filter to resist erosionSurvey the bed before placement and the finished armour footprint and crest after placement.Wharf & Jetty Superstructure — pile caps, deck units & in-situ toppingCheck deck lines, berth face, fender and bollard positions against marine control.
Production and measurement
Separate floating plant standby, tidal windows, tow and positioning, disposal and accepted in-situ volume.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.MAR.001 | Drive large-dia steel tubular pile (<=914 mm) to set, jack-up, good ground | no/shift | 2 | 4 | 6 | S-065 |
| PRD.MAR.002 | Drive large-dia steel tubular pile, floating barge (swell-limited) | no/shift | 1 | 2.5 | 4 | S-065 |
| PRD.MAR.003 | Drive PSC pile, marine, from barge/jack-up | no/shift | 2 | 4 | 7 | S-065 |
| PRD.MAR.004 | Pitch & vibrate steel sheet pile (combi/anchored wall) | m2/shift | 40 | 80 | 140 | S-065 |
| PRD.MAR.005 | Tremie/pump concrete plug to driven tubular | m3/hr | 8 | 15 | 25 | S-065 |
| PRD.MAR.006 | Bored marine pile in soil, 1200-1500 mm dia (drill+cage+tremie) | no/shift | 0.5 | 1 | 2 | S-065 |
| PRD.MAR.007 | Rock-socket advance (medium-strong rock) | m/hr | 0.3 | 0.8 | 1.5 | S-065 |
| PRD.MAR.008 | Tremie concrete placement, marine bored pile | m3/hr | 10 | 18 | 30 | S-065 |
| PRD.MAR.009 | In-situ pile cap / headstock concrete over water (form, fix, pour) | m3/day | 8 | 20 | 40 | S-065 |
| PRD.MAR.010 | Place precast deck planks / soffit units | no/day | 8 | 20 | 35 | S-065 |
| PRD.MAR.011 | In-situ topping deck pour (pump from deck) | m2/day | 60 | 150 | 300 | S-065 |
| PRD.MAR.012 | Reinforcement fixing, marine deck/cap | t/day per gang | 1 | 2.5 | 4 | S-065 |
| PRD.MAR.013 | CSD in soft-medium material (in-situ m3) | m3/week | 30000 | 80000 | 200000 | S-065 |
| PRD.MAR.014 | TSHD loose sand/silt (in-situ m3) | m3/week | 50000 | 150000 | 400000 | S-065 |
| PRD.MAR.015 | Backhoe dredger, stiff clay / soft rock (in-situ m3) | m3/day | 1500 | 4000 | 8000 | S-065 |
| PRD.MAR.016 | Maintenance dredge silt (in-situ m3), TSHD | m3/hr | 300 | 800 | 1500 | S-065 |
| PRD.MAR.017 | Hydraulic fill placement (pumped from CSD) | m3/week | 30000 | 90000 | 250000 | S-065 |
| PRD.MAR.018 | Rock bund construction | m3/day | 300 | 800 | 1500 | S-065 |
| PRD.MAR.019 | PVD installation | lm/rig/day | 3000 | 6000 | 10000 | S-065 |
| PRD.MAR.020 | Dynamic compaction | m2/day | 800 | 2000 | 4000 | S-065 |
| PRD.MAR.021 | Offshore S-lay welded steel line (firing-line) | joints/day | 60 | 120 | 250 | S-065 |
| PRD.MAR.022 | Offshore lay pipe length (12 m joints) | km/day | 0.7 | 1.5 | 3 | S-065 |
| PRD.MAR.023 | Nearshore float-and-sink / bottom-pull HDPE outfall string | m/day | 100 | 300 | 600 | S-065 |
| PRD.MAR.024 | Jet-sled trenching / lowering (soft seabed) | m/hr | 50 | 200 | 500 | S-065 |
| PRD.MAR.025 | Rock-dump cover (fall-pipe vessel) | t/hr | 200 | 500 | 1000 | S-065 |
| PRD.MAR.026 | Place graded rock armour (land-based, long-reach exc) | t/day | 400 | 1000 | 2000 | S-065 |
| PRD.MAR.027 | Place rock armour from barge (marine) | t/day | 200 | 600 | 1200 | S-065 |
| PRD.MAR.028 | Pattern-place single-layer concrete armour units (Accropode/Core-Loc) | no/day | 30 | 80 | 150 | S-065 |
| PRD.MAR.029 | Place geotextile sand containers (geobags) | no/day | 20 | 60 | 120 | S-065 |
| PRD.MAR.030 | Place geotextile filter / bedding | m2/day | 300 | 800 | 1500 | S-065 |
| PRD.MAR.031 | Core rock placement (haul-road advance / end-tip) | t/day | 1500 | 4000 | 8000 | S-065 |
| PRD.MAR.032 | Primary rock armour placement (land/marine) | t/day | 400 | 1000 | 2000 | S-065 |
| PRD.MAR.033 | Pattern-place concrete armour units | no/day | 30 | 70 | 130 | S-065 |
| PRD.MAR.034 | Caisson float-in and sink (vertical breakwater) | no/week | 0.5 | 1.5 | 3 | S-065 |
| PRD.MAR.035 | Place rock rip-rap scour protection (land-based) | t/day | 300 | 700 | 1500 | S-065 |
| PRD.MAR.036 | Place rip-rap from barge (around piles) | t/day | 150 | 400 | 800 | S-065 |
| PRD.MAR.037 | Place articulated concrete mattress | m2/day | 100 | 300 | 600 | S-065 |
| PRD.MAR.038 | Grout-bag / fabric-form mattress around piles (diver-assisted) | m2/day | 30 | 80 | 150 | S-065 |
| PRD.MAR.039 | Install fender system (cone/cell + panel + chains), per set | set/day | 0.5 | 1.5 | 3 | S-065 |
| PRD.MAR.040 | Install bollard / QRH (set out, anchor, set, torque) | no/day | 1 | 3 | 6 | S-065 |
| PRD.MAR.041 | Install chemical/mechanical anchor set for fittings | no/day | 8 | 16 | 30 | S-065 |
| PRD.MAR.042 | Abrasive blast + coat marine steel (multi-coat system) | m2/day per crew | 60 | 150 | 300 | S-065 |
| PRD.MAR.043 | Install HDPE/concrete pile jacket + grout (splash zone) | no/day | 2 | 5 | 10 | S-065 |
| PRD.MAR.044 | Install sacrificial anodes (bolt-on/stand-off) | no/day | 6 | 15 | 30 | S-065 |
| PRD.MAR.045 | Pitch & vibrate marine sheet-pile cofferdam wall | m2/shift | 40 | 90 | 150 | S-065 |
| PRD.MAR.046 | Install bracing frame / waling level | frame/day | 0.5 | 1 | 2 | S-065 |
| PRD.MAR.047 | Tremie base seal | m3/hr | 8 | 15 | 25 | S-065 |
Construction references
- Marine Piling and Wharf
- Breakwater Revetment and Rock Armour
- Quay Walls and Sheet Pile Bulkheads