Discipline library

Marine and ports

Establish marine datum and bathymetry. Release dredge, piling, quay and wharf fronts by berth or reach. Verify finished bed, deck and protection surfaces.

Piled wharf construction
  1. Precast deckDeck units span between headstocks. Keep the open bay available for scour placement and inspection.
  2. Steel pilesThe accepted pile-head group releases the cap and scour crews.
  3. Crane pontoonVessel access and positioning determine which bay the lifting spread can serve.
Illustrative workfront within Marine and ports.
Open the marine lot programme and handover register
Open the Wharf piling from a floating work platform calculator

Construction and release sequence

  1. Establish hydrographic control and release the dredge area
  2. Survey the dredge cut and release the piling footprint
  3. Install piles and scour protection in the approved bay sequence
  4. Complete the wharf deck, berth fittings and handover survey

Work packages and conformance checks

Production and measurement

Separate floating plant standby, tidal windows, tow and positioning, disposal and accepted in-situ volume.

View the discipline reference figureMarine and ports reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.MAR.001Drive large-dia steel tubular pile (<=914 mm) to set, jack-up, good groundno/shift246S-065
PRD.MAR.002Drive large-dia steel tubular pile, floating barge (swell-limited)no/shift12.54S-065
PRD.MAR.003Drive PSC pile, marine, from barge/jack-upno/shift247S-065
PRD.MAR.004Pitch & vibrate steel sheet pile (combi/anchored wall)m2/shift4080140S-065
PRD.MAR.005Tremie/pump concrete plug to driven tubularm3/hr81525S-065
PRD.MAR.006Bored marine pile in soil, 1200-1500 mm dia (drill+cage+tremie)no/shift0.512S-065
PRD.MAR.007Rock-socket advance (medium-strong rock)m/hr0.30.81.5S-065
PRD.MAR.008Tremie concrete placement, marine bored pilem3/hr101830S-065
PRD.MAR.009In-situ pile cap / headstock concrete over water (form, fix, pour)m3/day82040S-065
PRD.MAR.010Place precast deck planks / soffit unitsno/day82035S-065
PRD.MAR.011In-situ topping deck pour (pump from deck)m2/day60150300S-065
PRD.MAR.012Reinforcement fixing, marine deck/capt/day per gang12.54S-065
PRD.MAR.013CSD in soft-medium material (in-situ m3)m3/week3000080000200000S-065
PRD.MAR.014TSHD loose sand/silt (in-situ m3)m3/week50000150000400000S-065
PRD.MAR.015Backhoe dredger, stiff clay / soft rock (in-situ m3)m3/day150040008000S-065
PRD.MAR.016Maintenance dredge silt (in-situ m3), TSHDm3/hr3008001500S-065
PRD.MAR.017Hydraulic fill placement (pumped from CSD)m3/week3000090000250000S-065
PRD.MAR.018Rock bund constructionm3/day3008001500S-065
PRD.MAR.019PVD installationlm/rig/day3000600010000S-065
PRD.MAR.020Dynamic compactionm2/day80020004000S-065
PRD.MAR.021Offshore S-lay welded steel line (firing-line)joints/day60120250S-065
PRD.MAR.022Offshore lay pipe length (12 m joints)km/day0.71.53S-065
PRD.MAR.023Nearshore float-and-sink / bottom-pull HDPE outfall stringm/day100300600S-065
PRD.MAR.024Jet-sled trenching / lowering (soft seabed)m/hr50200500S-065
PRD.MAR.025Rock-dump cover (fall-pipe vessel)t/hr2005001000S-065
PRD.MAR.026Place graded rock armour (land-based, long-reach exc)t/day40010002000S-065
PRD.MAR.027Place rock armour from barge (marine)t/day2006001200S-065
PRD.MAR.028Pattern-place single-layer concrete armour units (Accropode/Core-Loc)no/day3080150S-065
PRD.MAR.029Place geotextile sand containers (geobags)no/day2060120S-065
PRD.MAR.030Place geotextile filter / beddingm2/day3008001500S-065
PRD.MAR.031Core rock placement (haul-road advance / end-tip)t/day150040008000S-065
PRD.MAR.032Primary rock armour placement (land/marine)t/day40010002000S-065
PRD.MAR.033Pattern-place concrete armour unitsno/day3070130S-065
PRD.MAR.034Caisson float-in and sink (vertical breakwater)no/week0.51.53S-065
PRD.MAR.035Place rock rip-rap scour protection (land-based)t/day3007001500S-065
PRD.MAR.036Place rip-rap from barge (around piles)t/day150400800S-065
PRD.MAR.037Place articulated concrete mattressm2/day100300600S-065
PRD.MAR.038Grout-bag / fabric-form mattress around piles (diver-assisted)m2/day3080150S-065
PRD.MAR.039Install fender system (cone/cell + panel + chains), per setset/day0.51.53S-065
PRD.MAR.040Install bollard / QRH (set out, anchor, set, torque)no/day136S-065
PRD.MAR.041Install chemical/mechanical anchor set for fittingsno/day81630S-065
PRD.MAR.042Abrasive blast + coat marine steel (multi-coat system)m2/day per crew60150300S-065
PRD.MAR.043Install HDPE/concrete pile jacket + grout (splash zone)no/day2510S-065
PRD.MAR.044Install sacrificial anodes (bolt-on/stand-off)no/day61530S-065
PRD.MAR.045Pitch & vibrate marine sheet-pile cofferdam wallm2/shift4090150S-065
PRD.MAR.046Install bracing frame / waling levelframe/day0.512S-065
PRD.MAR.047Tremie base sealm3/hr81525S-065

Construction references

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.