Marine and ports

Wharf piling from a floating work platform

Piled wharf construction
  1. Precast deckDeck units span between headstocks. Keep the open bay available for scour placement and inspection.
  2. Steel pilesThe accepted pile-head group releases the cap and scour crews.
  3. Crane pontoonVessel access and positioning determine which bay the lifting spread can serve.
Illustrative workfront for Wharf piling from a floating work platform.
Open the marine lot programme and handover register

Modular piling pontoon

Compare a floating spud pontoon with a jack-up platform. Water depth, seabed conditions, exposure, reach and access for supply barges determine which spread can serve each pile group.

Supplier information to obtain

Obtain the deck arrangement, crane reactions, vessel stability assessment, mooring or spud arrangement, tow plan and the operating window from the marine contractor.

Supporting plant and crew

Crane and hammer, pile guides, survey boat, workboat and pile supply barge. Check which vessel is on hire during weather standby.

Damen lists crane work, drilling and piling among the platform applications. Damen modular pontoon 3015

Construction method

Release the workfront

Release the pile grid and marine work area. Deliver piles in installation order and allow a separate tow and initial setup.

Execute the work

Set the guide, pitch and install each pile. Record positioning time separately from driving, splicing and inspection.

Measure and hand over

Reconcile the accepted pile log with survey and installation records before releasing pile caps. Allow for relocations between bents.

Productivity calculator

Use one typical pile as a batch. Separate long or spliced piles by location. Charge a barge move once per group, or apportion it across that group.

Example values demonstrate the arithmetic. Use shift records, supplier programmes or a measured trial for an estimate.

Calculation basis and shift treatment

One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.

Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.

Productivity evidence

Drive large-dia steel tubular pile, floating barge (swell-limited)

Low 1 · Typical 2.5 · High 4   no/shift

The floating-barge row is expressed per shift. Match its ground and marine exposure before comparing.

PRD.MAR.002 · Vaultix source S-065 · Indicative internal benchmark

Related methodologies

The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.

Discipline work packages and survey requirements