Supplier information to obtain
Obtain the deck arrangement, crane reactions, vessel stability assessment, mooring or spud arrangement, tow plan and the operating window from the marine contractor.
Compare a floating spud pontoon with a jack-up platform. Water depth, seabed conditions, exposure, reach and access for supply barges determine which spread can serve each pile group.
Obtain the deck arrangement, crane reactions, vessel stability assessment, mooring or spud arrangement, tow plan and the operating window from the marine contractor.
Crane and hammer, pile guides, survey boat, workboat and pile supply barge. Check which vessel is on hire during weather standby.
Damen lists crane work, drilling and piling among the platform applications. Damen modular pontoon 3015
Release the pile grid and marine work area. Deliver piles in installation order and allow a separate tow and initial setup.
Set the guide, pitch and install each pile. Record positioning time separately from driving, splicing and inspection.
Reconcile the accepted pile log with survey and installation records before releasing pile caps. Allow for relocations between bents.
Use one typical pile as a batch. Separate long or spliced piles by location. Charge a barge move once per group, or apportion it across that group.
One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Low 1 · Typical 2.5 · High 4 no/shift
The floating-barge row is expressed per shift. Match its ground and marine exposure before comparing.
PRD.MAR.002 · Vaultix source S-065 · Indicative internal benchmark
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.