Oil and process facilities
- Hydraulic gantrySetup and controlled transfer contribute to placement time.
- Process skidKeep equipment and assembly records against the skid ID.
- FoundationVerify plinth and anchor alignment before final installation.
Construction and release sequence
- Release civil foundations, tie-in limits and vendor deliveries
- Set structural steel, process skids, piping and tanks
- Inspect connections and close mechanical completion by system
- Reconcile pre-commissioning tests and authorised turnover
Work packages and conformance checks
Pre-Commissioning & Commissioning — clean, test, dry, inert & introduce to serviceIdentify system boundaries and as-built equipment and tie-in locations on the turnover drawings.Process Facility Civils & SMP — Structural, Mechanical & PipingSurvey anchor grids, foundations, pipe-rack alignment and tie-in coordinates before fabrication release.AGI / Compressor, Pump & Metering Stations — above-ground installationsCheck slab levels, skid rails, manifold and battery-limit connections on the common plant grid.Tank Farms & Storage — API 650/620 welded tanks, bunds & ringwallsCheck ringwall level, shell roundness, verticality and nozzle orientation at the specified stage.
Production and measurement
Separate civil quantities, mechanical setting, pipe fabrication, tie-ins and testing attendance.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.OG.007 | Offshore S-lay - single-joint welding, 12" line, ideal | km/day | 2 | 3 | 5 | S-065 |
| PRD.OG.008 | Offshore S-lay - joints welded (12 m joints) | joints/day | 150 | 300 | 420 | S-065 |
| PRD.OG.009 | J-lay - deepwater single-position welding | km/day | 1 | 2 | 3.5 | S-065 |
| PRD.OG.010 | Reel-lay - smaller-diameter, no offshore welding | km/day | 4 | 8 | 15 | S-065 |
| PRD.OG.011 | Process piping erection & weld (field, CS, by inch-dia) | inch-dia/welder-day | 20 | 27 | 35 | S-065 |
| PRD.OG.012 | Mechanical equipment setting & alignment (skid / package) | package/crew-day | 0.3 | 0.7 | 1.5 | S-065 |
| PRD.OG.013 | RC equipment foundation (form / reo / pour plinth) | m3/crew-day | 4 | 8 | 14 | S-065 |
| PRD.OG.014 | Structural steel erection (process plant, field) - input | man-hour/tonne | 15 | 25 | 40 | S-065 |
| PRD.OG.015 | Structural steel erection - output | t/crew-day | 4 | 10 | 20 | S-065 |
| PRD.OG.016 | Process piping - field weld | inch-dia/welder-day | 20 | 27 | 35 | S-065 |
| PRD.OG.017 | Piping fabrication & install (overall) | man-hour/inch-dia | 1 | 1.8 | 3.5 | S-065 |
| PRD.OG.018 | Tank shell plate welding (vertical/horizontal seams, CS) | man-hour/tonne | 40 | 80 | 140 | S-065 |
| PRD.OG.019 | Tank erection - overall (small-mid API 650, by capacity) | man-hour/tonne steel | 50 | 90 | 160 | S-065 |
| PRD.OG.020 | Shell course erection (jack-up method) | course/day | 0.5 | 1 | 2 | S-065 |
| PRD.OG.021 | Subsea spool / jumper tie-in (per connection) | connection/vessel-day | 0.5 | 1 | 2 | S-065 |
| PRD.OG.022 | Umbilical / flowline lay | km/day | 2 | 5 | 10 | S-065 |
| PRD.OG.023 | Rock-dump seabed stabilisation | t/day | 2000 | 6000 | 15000 | S-065 |
| PRD.OG.024 | Hook-up spool tie-in (offshore HUC) | tie-in/crew-day | 0.5 | 1.5 | 3 | S-065 |
| PRD.OG.025 | Module integration (yard, per integrated module) | module/weeks | 1 | 3 | 8 | S-065 |
| PRD.OG.026 | Commissioning systems handover | system/week | 2 | 5 | 10 | S-065 |
| PRD.OG.029 | PE gathering flowline lay & fuse | m/day | 300 | 700 | 1200 | S-065 |
| PRD.OG.030 | Cleaning / gauging pig run | km/day | 5 | 20 | 50 | S-065 |
| PRD.OG.031 | Hydrostatic test - fill / pressurise / hold / report (per section) | section/days | 1 | 3 | 7 | S-065 |
| PRD.OG.032 | Drying to dewpoint (nitrogen / air) | km/day | 2 | 10 | 30 | S-065 |
Construction references
- Oil and Gas Facility Construction