Supplier information to obtain
Request package mass, lift points and centre of gravity, clear height, travel path, civil release and vendor alignment tolerances.
Compare gantry placement with mobile crane or slide-track installation where buildings, pipe racks or operating plant restrict headroom or access.
Request package mass, lift points and centre of gravity, clear height, travel path, civil release and vendor alignment tolerances.
Hydraulic gantry, header beams, skidding or transport equipment, survey and alignment crew. Include mobilisation and specialist supervision.
Enerpac lists hydraulic gantries, header beams and side-shift equipment for heavy-load handling. Enerpac hydraulic gantry systems
Release the foundation and route, verify package delivery condition and schedule the approved outage or handover window where applicable.
Receive and transfer the package, place it on the foundation, then survey and align to the vendor interface.
Record packages mechanically set and aligned. Pipe tie-ins, grout cure, electrical connections and commissioning have distinct completion criteria.
Group repeat packages of comparable geometry. Build separate durations for unique packages, site access restrictions and post-set work.
One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.
Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.
Low 0.3 · Typical 0.7 · High 1.5 package/crew-day
Check package mass, access, alignment scope and crew-day length before comparing.
PRD.OG.012 · Vaultix source S-065 · Indicative internal benchmark
The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.