Oil facilities

Process equipment skid placement and alignment

Oil and process facilities
  1. Hydraulic gantrySetup and controlled transfer contribute to placement time.
  2. Process skidKeep equipment and assembly records against the skid ID.
  3. FoundationVerify plinth and anchor alignment before final installation.
Illustrative workfront for Process equipment skid placement and alignment.

Hydraulic lifting gantry

Compare gantry placement with mobile crane or slide-track installation where buildings, pipe racks or operating plant restrict headroom or access.

Supplier information to obtain

Request package mass, lift points and centre of gravity, clear height, travel path, civil release and vendor alignment tolerances.

Supporting plant and crew

Hydraulic gantry, header beams, skidding or transport equipment, survey and alignment crew. Include mobilisation and specialist supervision.

Enerpac lists hydraulic gantries, header beams and side-shift equipment for heavy-load handling. Enerpac hydraulic gantry systems

Construction method

Release the workfront

Release the foundation and route, verify package delivery condition and schedule the approved outage or handover window where applicable.

Execute the work

Receive and transfer the package, place it on the foundation, then survey and align to the vendor interface.

Measure and hand over

Record packages mechanically set and aligned. Pipe tie-ins, grout cure, electrical connections and commissioning have distinct completion criteria.

Productivity calculator

Group repeat packages of comparable geometry. Build separate durations for unique packages, site access restrictions and post-set work.

Example values demonstrate the arithmetic. Use shift records, supplier programmes or a measured trial for an estimate.

Calculation basis and shift treatment

One spread completes all three stages in sequence. Repeat interval = sum of the three stage times. Productive minutes per shift = rostered hours × 60 − lost minutes. Repeat output = batch quantity × productive minutes ÷ repeat interval. Package minutes = first batch time + (number of batches − 1) × repeat interval. Shift equivalents = package minutes ÷ productive minutes per shift.

Rounded rostered shifts assume work can carry across shift boundaries. Continuous weather windows, indivisible lifts, startup, mobilisation, handovers and shutdowns need separate programme allowances. Count losses once across observed stage times and shift losses.

Productivity evidence

Mechanical equipment setting & alignment (skid / package)

Low 0.3 · Typical 0.7 · High 1.5   package/crew-day

Check package mass, access, alignment scope and crew-day length before comparing.

PRD.OG.012 · Vaultix source S-065 · Indicative internal benchmark

Related methodologies

The equipment citation supports the machine function. The method and timing boundaries are estimating assumptions. Record the project source, date, observed quantity, time basis and loss treatment when adopting a rate.

Discipline work packages and survey requirements

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.