- Form faceInspect geometry and surface preparation before the pour.
- Secondary beamsConfirm the installed support arrangement and interfaces.
- Prop lineRecord support and striking release for the bay.
Work scope and interfaces
What it is & where used
Every bridge has substructure. Abutments at each end; piers/columns at intermediate supports; a headstock on each multi-column pier; a pile cap where founded on piles. Integral bridges merge the abutment with the deck (no bearing shelf).
Related work packages
Construction sequence
- Excavate / accept founding interface
- Pile cap on the foundation (ground engineering)
- Columns/piers in lifts (fix reo → erect formwork → place & cure concrete → strip)
- Headstock on falsework/needle beams (reo → form → pour → cure → strip)
- Set out & prepare the bearing shelf for the bearings (Bridge Bearings)
- Backfill abutments & compact behind. Over a live road/rail: staged with traffic management / possession.
The make-or-break: the headstock formwork/falsework over live traffic (a designed temporary works + staging cost the bare concrete rate misses), and the bearing-shelf level/set-out (the superstructure depends on it).
Plant, resources and measurement
L.CREW.STRUCT.CONC (form/fix/pour) + PLANT-EXC + PLANT-CRN-MOB (reo/form handling) + PLANT-CONC-PUMP; materials M.CONC.S40 (structural/special-class), M.REO (cage), M.FORM (formwork/falsework), M.GROUT. Measured per element: concrete m³ + reinforcement t + formwork m². Priced items: BR.01.020 (pile cap), BR.01.030 (pier/column), BR.01.040 (headstock/crosshead); the bored pile below is BR.01.010 (refers FN.01, ground engineering). Watch flat RC rates that ignore lift height, form complexity (blade/circular) and access/falsework.
Keep fabricated unit supply, erection possessions and temporary supports distinct.
View Bridges and structures productivity referencesPackage productivity
Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.
| Component activity | Published basis | Low | Typical | High | Library source |
|---|---|---|---|---|---|
| Bridge headstock / pier (in-situ RC) - per m3PRD.CONC.022 | m3/day | 2 | 6 | 12 | S-061 |
| Formwork - walls / columns (vertical, single face shown)PRD.CONC.007 | m2/day (set + strip) | 20 | 35 | 50 | S-061 |
Survey conformance and lot release
- Observe
- Check pier axes, headstock levels and bearing-seat coordinates against bridge control.
- Compare
- Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
- Verify and hand over
- Issue the seat survey and pour results before bearing installation.
- Resolve exceptions
- Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations
Founding-interface acceptance, reo cover/fixing, concrete grade/slump/cure (AS 5100.5), formwork/falsework certification (AS 3610), dimension & verticality, bearing-shelf level/set-out (Hold — superstructure interface). Risks: headstock falsework over live traffic (temporary-works design + possession); foundation interface to ground engineering (no drop/double-count); cover/exposure under-spec → durability; high-lift / complex-form productivity; concrete supply continuity for big pours. Pairs with the superstructure it carries (Bridge Superstructure) and the bearings on the shelf (Bridge Bearings).
Evidence and related work
Internal record BR-SUBSTRUCTURE-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.