Bridges and structures
- Launching gantryMoving and setting the gantry contributes to each erection cycle.
- GirderTrack each fabricated beam from delivery to its accepted position.
- Bearing seatSurvey seat position and level before releasing the span.
Construction and release sequence
- Confirm access, temporary works and substructure release
- Set bearings and erect the selected superstructure
- Complete deck, joints, finishes and protection
- Reconcile span survey, connection records and inspection access
Work packages and conformance checks
Bridge Deck Finishing & RehabilitationSurvey deck profile, drainage low points, barrier faces and joint interfaces.Bridge Substructure — abutments, piers, columns & headstocksCheck pier axes, headstock levels and bearing-seat coordinates against bridge control.Bridge Superstructure — girders, in-situ deck & erectionObserve girder lines, seat elevations, camber and finished deck profile at the specified stage.Bridge BearingsCompare seat level, centre marks, orientation and installed offset against the bearing schedule.FRP / Carbon-Fibre StrengtheningLocate strengthening extents and terminations on the marked-up structure.Expansion & Movement JointsMeasure joint gap, skew and finished road level at the observation temperature.Precast & Segmental ErectionSurvey erection bearings and record beam or segment position after placement.Post-TensioningLocate ducts, anchor recesses and tendon profiles before concealment.
Production and measurement
Keep fabricated unit supply, erection possessions and temporary supports distinct.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.CONC.001 | Kerb & channel - machine extruded (B1/B2/barrier) | m/day | 150 | 250 | 350 | S-061 |
| PRD.CONC.002 | Kerb & channel - hand formed | m/day | 40 | 80 | 120 | S-061 |
| PRD.CONC.003 | Concrete footpath / shared path - 100 mm | m2/day | 80 | 150 | 220 | S-061 |
| PRD.CONC.004 | Concrete shared path / cyclepath - 150 mm reinforced | m2/day | 60 | 120 | 180 | S-061 |
| PRD.CONC.005 | Vehicle crossing / driveway (residential-commercial) | m2/day | 50 | 110 | 160 | S-061 |
| PRD.CONC.006 | Blinding / lean-mix concrete (under footings/slabs) | m3/day placed | 20 | 40 | 60 | S-061 |
| PRD.CONC.007 | Formwork - walls / columns (vertical, single face shown) | m2/day (set + strip) | 20 | 35 | 50 | S-061 |
| PRD.CONC.008 | Formwork - soffit / suspended slab & beam (incl shoring) | m2/day (incl prop/strike) | 15 | 28 | 40 | S-061 |
| PRD.CONC.009 | Formwork - footings / edge / kicker (low height) | m2/day | 30 | 50 | 70 | S-061 |
| PRD.CONC.011 | Reinforcement - FIX (place & tie bar) | t/day per gang | 1 | 2 | 3.5 | S-061 |
| PRD.CONC.012 | Reinforcement - mesh (supply + fix, slabs/paths) | t/day (sheets) | 2.5 | 4 | 6 | S-061 |
| PRD.CONC.015 | Concrete - PLACE & VIBRATE (pump) | m3/day (element dependent) | 40 | 80 | 140 | S-061 |
| PRD.CONC.016 | Concrete - PLACE & VIBRATE (crane & kibble) | m3/day | 20 | 45 | 80 | S-061 |
| PRD.CONC.017 | Concrete - FINISH & CURE (slabs/flatwork) | m2/day | 150 | 350 | 600 | S-061 |
| PRD.CONC.018 | Precast plank / deck unit install (bridge/building) | units/day | 4 | 10 | 16 | S-061 |
| PRD.CONC.019 | Precast box culvert (RCBC) unit install - per cell | m/day per cell | 6 | 15 | 25 | S-061 |
| PRD.CONC.020 | Retaining wall - segmental block / reinforced soil (m2 face) | m2 face/day | 15 | 35 | 60 | S-061 |
| PRD.CONC.021 | Retaining wall - cast in-situ RC (m2 face) | m2 face/day | 5 | 15 | 30 | S-061 |
| PRD.CONC.022 | Bridge headstock / pier (in-situ RC) - per m3 | m3/day | 2 | 6 | 12 | S-061 |
| PRD.CONC.023 | Bridge deck slab (in-situ on planks/Super-T) - per m2 | m2/day | 40 | 90 | 160 | S-061 |
| PRD.CONC.024 | Bridge barrier / parapet (in-situ or precast) - per m | m/day (slipform) / 6-15-25 m/day (formed) | 20 | 60 | 120 | S-061 |
| PRD.CONC.025 | Grout - bedding / bearing pads / starter bars (cementitious) | m3/day (placed) | 0.3 | 1 | 2 | S-061 |
| PRD.CONC.026 | Bridge bearings - supply & install (elastomeric/pot) | per day install (ex supply) | 1 | 3 | 5 | S-061 |
Construction references
- Bridge Construction
- Superstructure Erection and Temporary Works
- Bridge Refurbishment Strengthening and Durability