Bridges and structures

Release foundations and substructure, verify bearing seats, erect the selected superstructure and close the deck, joints and approaches.

Bridges and structures
  1. Launching gantryMoving and setting the gantry contributes to each erection cycle.
  2. GirderTrack each fabricated beam from delivery to its accepted position.
  3. Bearing seatSurvey seat position and level before releasing the span.
Illustrative workfront within Bridges and structures.
Open the Precast girder erection by launching gantry calculator

Construction and release sequence

  1. Confirm access, temporary works and substructure release
  2. Set bearings and erect the selected superstructure
  3. Complete deck, joints, finishes and protection
  4. Reconcile span survey, connection records and inspection access

Work packages and conformance checks

Production and measurement

Keep fabricated unit supply, erection possessions and temporary supports distinct.

View the discipline reference figureBridges and structures reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.CONC.001Kerb & channel - machine extruded (B1/B2/barrier)m/day150250350S-061
PRD.CONC.002Kerb & channel - hand formedm/day4080120S-061
PRD.CONC.003Concrete footpath / shared path - 100 mmm2/day80150220S-061
PRD.CONC.004Concrete shared path / cyclepath - 150 mm reinforcedm2/day60120180S-061
PRD.CONC.005Vehicle crossing / driveway (residential-commercial)m2/day50110160S-061
PRD.CONC.006Blinding / lean-mix concrete (under footings/slabs)m3/day placed204060S-061
PRD.CONC.007Formwork - walls / columns (vertical, single face shown)m2/day (set + strip)203550S-061
PRD.CONC.008Formwork - soffit / suspended slab & beam (incl shoring)m2/day (incl prop/strike)152840S-061
PRD.CONC.009Formwork - footings / edge / kicker (low height)m2/day305070S-061
PRD.CONC.011Reinforcement - FIX (place & tie bar)t/day per gang123.5S-061
PRD.CONC.012Reinforcement - mesh (supply + fix, slabs/paths)t/day (sheets)2.546S-061
PRD.CONC.015Concrete - PLACE & VIBRATE (pump)m3/day (element dependent)4080140S-061
PRD.CONC.016Concrete - PLACE & VIBRATE (crane & kibble)m3/day204580S-061
PRD.CONC.017Concrete - FINISH & CURE (slabs/flatwork)m2/day150350600S-061
PRD.CONC.018Precast plank / deck unit install (bridge/building)units/day41016S-061
PRD.CONC.019Precast box culvert (RCBC) unit install - per cellm/day per cell61525S-061
PRD.CONC.020Retaining wall - segmental block / reinforced soil (m2 face)m2 face/day153560S-061
PRD.CONC.021Retaining wall - cast in-situ RC (m2 face)m2 face/day51530S-061
PRD.CONC.022Bridge headstock / pier (in-situ RC) - per m3m3/day2612S-061
PRD.CONC.023Bridge deck slab (in-situ on planks/Super-T) - per m2m2/day4090160S-061
PRD.CONC.024Bridge barrier / parapet (in-situ or precast) - per mm/day (slipform) / 6-15-25 m/day (formed)2060120S-061
PRD.CONC.025Grout - bedding / bearing pads / starter bars (cementitious)m3/day (placed)0.312S-061
PRD.CONC.026Bridge bearings - supply & install (elastomeric/pot)per day install (ex supply)135S-061