- Table formRepetition depends on striking, moving and resetting each table.
- Shifting trolleyAllow for travel and handling access between slab bays.
- Floor bayLink survey and concrete records to the released pour area.
Work scope and interfaces
What it is & where used
Used under all buildings — commercial, industrial/warehouse, residential and basements. Footings vs piling is the geotech call: spread footings on good ground, piles/ground beams where bearing is poor, variable or reactive.
Construction sequence
- Geotech report + footing/pile design
- Detailed excavation (BS.02.020)
- [ground improvement BS.02.060 if poor ground — ground-engineering]
- Set out
- PILE (bore/drive + cage)
- INTEGRITY/PDA TEST (AS 2159)
- Trim/cut down
- Pile caps + ground beams (formwork + starter bars)
- Pad/strip footings
- Backfill
- Termite barrier (AS 3660.1)
- Vapour barrier + slab reo/mesh
- POUR SLAB (boom pump)
- Power-float/finish
- Cure
- Flatness survey (FM2)
- Tank below-ground faces (AS 4654).
The make-or-break: the founding-interface acceptance (founding stratum confirmed + pile integrity/load test PASSED before any cap is cast — ground risk owned by ground engineering), and the slab — vapour barrier + curing discipline and FM2 flatness/joint detail on heavy-duty floors (skip these and the floor fails the regularity survey and racks/AGVs won't run).
Plant, resources and measurement
L.CREW.PILING (piling) on G.PLANT.PILERIG.BG28; L.CREW.CONC placing via G.PLANT.PUMP.BOOM36; L.CREW.STEELFIX (reo) + L.CREW.FORMWORK (cap/footing forms); L.TEST.PDA for dynamic testing. Materials M.CONC.N32 / M.CONC.N40, M.REO.BAR.N, M.REO.MESH, M.MEMBRANE.WP (vapour/tanking), M.PILE.SCREW (driven screw piles), M.TERMITE.BARRIER. Priced items: BS.03.010 bored cast-in-situ piles (incl reo + integrity test), BS.03.020 driven precast/steel screw piles (AS 2159), BS.03.030 pile load testing — static/dynamic PDA (AS 2159), BS.03.040 pad & strip footings — N32 (AS 3600), BS.03.050 pile caps & ground beams — RC w/ starter bars, BS.03.060 reinforced slab-on-ground (AS 2870 / AS 3600, vapour barrier), BS.03.070 heavy-duty industrial slab — SFRC/dowelled joints, FM2, BS.03.080 suspended slab on steel decking, BS.03.090 tanking/waterproofing (AS 4654); interface items BS.02.020/050/060/070. Measured: piles m (or no by length band), test no, footings/caps m³ (reo t, forms m²), slab m² (by thickness + flatness class), tanking m², termite barrier m²/LS. Rate trap: pricing slab as a flat $/m² that ignores flatness class, joint type and surface regularity — FM2 + dowelled/SFRC joints carry a real finishing + setout premium over a domestic slab; and pile rates that omit the test regime and spoil disposal.
Shared hoists, crane time, access and floor-cycle releases affect several trades together.
View Buildings and electrical services productivity referencesPackage productivity
Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.
| Component activity | Published basis | Low | Typical | High | Library source |
|---|---|---|---|---|---|
| Place & finish industrial slab-on-ground (Class-A trowel, conventional reo/SFRC)PRD.BS.001 | m2/crew-day | 300 | 600 | 1000 | S-065 |
| Formwork - footings / edge / kicker (low height)PRD.CONC.009 | m2/day | 30 | 50 | 70 | S-061 |
Survey conformance and lot release
- Observe
- Locate footings, pile heads, sleeves and holding-down bolts against the building grid.
- Compare
- Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
- Verify and hand over
- Tie pre-pour observations and foundation acceptance to the next frame release.
- Resolve exceptions
- Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations
Hold points: founding-stratum sign-off (engineer at base), pile integrity/PDA + load test (AS 2159) BEFORE cap, reo/cover + holding-down/starter set-out before pour, slab subgrade + vapour barrier + termite barrier before cover, concrete supply conformance (AS 1379, slump/strength cylinders), formwork release (AS 3610), and the FM2 flatness survey + curing record on heavy-duty slabs; tanking integrity/flood test (AS 4654). Risks: ground risk — founding deeper/poorer than report (extra pile length, ground improvement) → handed to ground engineering; pile defect/necking; reactive-soil/site-class movement (AS 2870); water table / dewatering at excavation; slab cracking/curling from poor curing or wrong joint layout; flatness non-conformance; termite/durability non-compliance (AS 3660.1 / NCC). Pairs with the building overview (DISC-BUILD-OVW-001), build methodology (DISC-BUILD-METH-001) and the founding/ground scope owned by ground engineering.
Evidence and related work
Internal record BS-SUBSTRUCTURE-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.