Discipline library

Buildings and electrical services

Transfer the building grid from foundations to each floor. Release frame, envelope and rough-ins by zone before fit-out and system commissioning.

Buildings and electrical services
  1. Table formRepetition depends on striking, moving and resetting each table.
  2. Shifting trolleyAllow for travel and handling access between slab bays.
  3. Floor bayLink survey and concrete records to the released pour area.
Illustrative workfront within Buildings and electrical services.
Open the Repeat-floor table formwork calculator

Construction and release sequence

  1. Set survey control and release substructure interfaces
  2. Erect the frame and release bays for envelope and services
  3. Coordinate service rough-in, fitout and finishes by zone
  4. Complete inspections, commissioning and asset handover by system

Work packages and conformance checks

Production and measurement

Shared hoists, crane time, access and floor-cycle releases affect several trades together.

View the discipline reference figureBuildings and electrical services reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.BS.001Place & finish industrial slab-on-ground (Class-A trowel, conventional reo/SFRC)m2/crew-day3006001000S-065
PRD.BS.002Place & finish superflat/defined-movement floor (FM2/DM, laser screed + survey)m2/crew-day150300500S-065
PRD.BS.003Concrete supply/place rate by pump on a slab pourm3/hr204060S-065
PRD.BS.004Saw-cut control joints (early-entry)m/hr60120200S-065
PRD.BS.005Suspended-slab floor cycle (typical repeating floor, conventional/table forms)days/floor5714S-065
PRD.BS.006Formwork/falsework erect + strip (soffit form to deck)m2/crew-day254570S-065
PRD.BS.007Reinforcement fix to suspended slabt/crew-day1.535S-065
PRD.BS.008PT tendon install + stress (strand)t/crew-day0.512S-065
PRD.BS.009Tilt-up panel erection (mobile crane, standard warehouse panels)panels/crane-day81640S-065
PRD.BS.010Precast structural element erection (columns/beams/spandrels)elements/crane-day61220S-065
PRD.BS.011Hollowcore / double-tee plank erectionm2/crane-day250500900S-065
PRD.BS.012Tilt-up panel casting (site bed turnover)panels/crew-day246S-065
PRD.BS.013Structural steel erection - pieces per crane/hook per shiftpieces/crane-shift152560S-065
PRD.BS.014Structural steel erection - tonnes per week (single hook, light pieces)t/week5080120S-065
PRD.BS.015Holding-down bolt / base-plate set + groutbases/crew-day4815S-065
PRD.BS.016In-situ RC column & beam frame (form/reo/pour cycle)m3/crew-day81530S-065
PRD.BS.017Concrete core wall lift (jump/climbing form)days/floor-lift3510S-065
PRD.BS.018Self-climbing / slip-form continuous risem/day1.535S-065
PRD.BS.019Core wall formwork (one/two-sided shutter)m2/crew-day204060S-065
PRD.BS.020Core wall reinforcement fixt/crew-day1.535S-065
PRD.BS.021Passenger lift installation (per car, mid-rise, set-to-work excl. statutory test queue)weeks/lift248S-065
PRD.BS.022Escalator/travelator install & commission (per unit)weeks/unit124S-065
PRD.BS.023Guide-rail install up shaftm/crew-day153050S-065
PRD.BS.024Tower-crane productive lifts (effective hook cycles)lifts/hr3612S-065
PRD.BS.025Tower-crane erect / dismantle (per crane, with assist crane)days/event137S-065
PRD.BS.026Construction hoist availability / throughputtrips/hr61220S-065
PRD.BS.027Profiled metal roof/wall sheeting installm2/crew-day60120250S-065
PRD.BS.028Unitised curtain-wall panel install (crane/monorail hung)panels/crew-day61220S-065
PRD.BS.029Aluminium window/door installno/crew-day61220S-065
PRD.BS.030Applied waterproof membrane (wet areas / roof)m2/crew-day4080150S-065
PRD.BS.031Steel-stud + plasterboard partition (one side board)m2/crew-day203560S-065
PRD.BS.032Suspended ceiling grid + tilem2/crew-day3060100S-065
PRD.BS.033Floor/wall tilingm2/crew-day102035S-065
PRD.BS.034Internal painting (prep + 2 coats)m2/crew-day80150250S-065
PRD.BS.035Building services rough-in benchmark (typical commercial fit-out)% of build cost253545S-065
PRD.BS.036Electrical rough-in (cable tray + conduit + wiring)m/crew-day3060120S-065
PRD.BS.037Hydraulic / fire pipework rough-inm/crew-day204080S-065
PRD.BS.038Fire-stopping of service penetrationsno/crew-day153060S-065
PRD.EL.001LV cable termination & connection at feeder pillar / board / pit (per circuit)no/day per crew4815S-252
PRD.EL.002Set & connect LV feeder pillar / distribution board / metering pillarno/day per crew124S-252
PRD.EL.003Lighting-column footing (auger/excavate, cage, pour ~0.5-1.5 m3 each)no/day per crew3610S-252
PRD.EL.004Erect lighting column / pole + outreach arm (set on footing, plumb, base-wire)no/day per crew4814S-252
PRD.EL.005Mount, wire, lamp & aim road-lighting luminaire (per luminaire)no/day per crew61220S-252
PRD.EL.006High-mast lighting tower assemble, erect & lowering-frame (per mast)mast/day0.512S-252
PRD.EL.007Traffic-signal post / pole / mast-arm + footing (per post)no/day per crew246S-252
PRD.EL.008Mount & wire traffic-signal lantern group / pedestrian / display (per face)no/day per crew4814S-252
PRD.EL.009Saw-cut & install inductive vehicle detector loop (per loop)no/day per crew3610S-252
PRD.EL.010Set & wire signal controller cabinet + cutover/commission intersectiondays/intersection123S-252
PRD.EL.011Install ITS field device (CCTV / roadside VMS / ramp-meter / detector) + terminateno/day per crew136S-252
PRD.EL.012Haul optical-fibre / comms cable into conduit (roadside backbone)m/day per crew3006001200S-252
PRD.EL.013Optical-fibre splice & terminate + OTDR test (per splice/fusion)no/day per splicer122448S-252
PRD.EL.014Establish & fit comms pit / node / roadside cabinet (per node)no/day per crew248S-252
PRD.EL.015Energise + functional & illuminance commission a lighting circuit/run (AS/NZS 1158)days/circuit124S-252
PRD.EL.016Functional commission + road-authority acceptance of signals/ITS (per intersection/device)days/intersection136S-252