Buildings and electrical services
- Table formRepetition depends on striking, moving and resetting each table.
- Shifting trolleyAllow for travel and handling access between slab bays.
- Floor bayLink survey and concrete records to the released pour area.
Construction and release sequence
- Set survey control and release substructure interfaces
- Erect the frame and release bays for envelope and services
- Coordinate service rough-in, fitout and finishes by zone
- Complete inspections, commissioning and asset handover by system
Work packages and conformance checks
Building Envelope — roofing, cladding, masonry & façadeObserve slab-edge alignment, façade grids, anchor positions and panel-to-panel offsets.External Works, Civil Structures & Commissioning — building-site externals + whole-of-building handoverCheck accessible paths, entry thresholds, external falls and drainage tie-ins.Internal Fitout — linings, finishes, doors, joinery & sanitaryCheck wall lines, door openings, finished floor transitions and service access clearances.Building Services (MEP) — hydraulic, mechanical, electrical & fireSurvey penetrations, risers, equipment bases and service clearances before ceiling closure.Structural Frame — steel, in-situ concrete & precast/tilt-upCarry grids and levels between floors and check column plumb, slab edge and connection positions.Building Substructure — footings, slabs & pilingLocate footings, pile heads, sleeves and holding-down bolts against the building grid.Communications, Fibre & SCADARecord cabinet, panel and route locations with the correct equipment and drawing identifiers.Road & Public LightingSurvey pole foundations, bolt orientation, conduit routes and luminaire locations.Traffic Signals & ITSCheck signal poles, device locations, duct crossings and detection zones against the approved layout.
Production and measurement
Shared hoists, crane time, access and floor-cycle releases affect several trades together.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.BS.001 | Place & finish industrial slab-on-ground (Class-A trowel, conventional reo/SFRC) | m2/crew-day | 300 | 600 | 1000 | S-065 |
| PRD.BS.002 | Place & finish superflat/defined-movement floor (FM2/DM, laser screed + survey) | m2/crew-day | 150 | 300 | 500 | S-065 |
| PRD.BS.003 | Concrete supply/place rate by pump on a slab pour | m3/hr | 20 | 40 | 60 | S-065 |
| PRD.BS.004 | Saw-cut control joints (early-entry) | m/hr | 60 | 120 | 200 | S-065 |
| PRD.BS.005 | Suspended-slab floor cycle (typical repeating floor, conventional/table forms) | days/floor | 5 | 7 | 14 | S-065 |
| PRD.BS.006 | Formwork/falsework erect + strip (soffit form to deck) | m2/crew-day | 25 | 45 | 70 | S-065 |
| PRD.BS.007 | Reinforcement fix to suspended slab | t/crew-day | 1.5 | 3 | 5 | S-065 |
| PRD.BS.008 | PT tendon install + stress (strand) | t/crew-day | 0.5 | 1 | 2 | S-065 |
| PRD.BS.009 | Tilt-up panel erection (mobile crane, standard warehouse panels) | panels/crane-day | 8 | 16 | 40 | S-065 |
| PRD.BS.010 | Precast structural element erection (columns/beams/spandrels) | elements/crane-day | 6 | 12 | 20 | S-065 |
| PRD.BS.011 | Hollowcore / double-tee plank erection | m2/crane-day | 250 | 500 | 900 | S-065 |
| PRD.BS.012 | Tilt-up panel casting (site bed turnover) | panels/crew-day | 2 | 4 | 6 | S-065 |
| PRD.BS.013 | Structural steel erection - pieces per crane/hook per shift | pieces/crane-shift | 15 | 25 | 60 | S-065 |
| PRD.BS.014 | Structural steel erection - tonnes per week (single hook, light pieces) | t/week | 50 | 80 | 120 | S-065 |
| PRD.BS.015 | Holding-down bolt / base-plate set + grout | bases/crew-day | 4 | 8 | 15 | S-065 |
| PRD.BS.016 | In-situ RC column & beam frame (form/reo/pour cycle) | m3/crew-day | 8 | 15 | 30 | S-065 |
| PRD.BS.017 | Concrete core wall lift (jump/climbing form) | days/floor-lift | 3 | 5 | 10 | S-065 |
| PRD.BS.018 | Self-climbing / slip-form continuous rise | m/day | 1.5 | 3 | 5 | S-065 |
| PRD.BS.019 | Core wall formwork (one/two-sided shutter) | m2/crew-day | 20 | 40 | 60 | S-065 |
| PRD.BS.020 | Core wall reinforcement fix | t/crew-day | 1.5 | 3 | 5 | S-065 |
| PRD.BS.021 | Passenger lift installation (per car, mid-rise, set-to-work excl. statutory test queue) | weeks/lift | 2 | 4 | 8 | S-065 |
| PRD.BS.022 | Escalator/travelator install & commission (per unit) | weeks/unit | 1 | 2 | 4 | S-065 |
| PRD.BS.023 | Guide-rail install up shaft | m/crew-day | 15 | 30 | 50 | S-065 |
| PRD.BS.024 | Tower-crane productive lifts (effective hook cycles) | lifts/hr | 3 | 6 | 12 | S-065 |
| PRD.BS.025 | Tower-crane erect / dismantle (per crane, with assist crane) | days/event | 1 | 3 | 7 | S-065 |
| PRD.BS.026 | Construction hoist availability / throughput | trips/hr | 6 | 12 | 20 | S-065 |
| PRD.BS.027 | Profiled metal roof/wall sheeting install | m2/crew-day | 60 | 120 | 250 | S-065 |
| PRD.BS.028 | Unitised curtain-wall panel install (crane/monorail hung) | panels/crew-day | 6 | 12 | 20 | S-065 |
| PRD.BS.029 | Aluminium window/door install | no/crew-day | 6 | 12 | 20 | S-065 |
| PRD.BS.030 | Applied waterproof membrane (wet areas / roof) | m2/crew-day | 40 | 80 | 150 | S-065 |
| PRD.BS.031 | Steel-stud + plasterboard partition (one side board) | m2/crew-day | 20 | 35 | 60 | S-065 |
| PRD.BS.032 | Suspended ceiling grid + tile | m2/crew-day | 30 | 60 | 100 | S-065 |
| PRD.BS.033 | Floor/wall tiling | m2/crew-day | 10 | 20 | 35 | S-065 |
| PRD.BS.034 | Internal painting (prep + 2 coats) | m2/crew-day | 80 | 150 | 250 | S-065 |
| PRD.BS.035 | Building services rough-in benchmark (typical commercial fit-out) | % of build cost | 25 | 35 | 45 | S-065 |
| PRD.BS.036 | Electrical rough-in (cable tray + conduit + wiring) | m/crew-day | 30 | 60 | 120 | S-065 |
| PRD.BS.037 | Hydraulic / fire pipework rough-in | m/crew-day | 20 | 40 | 80 | S-065 |
| PRD.BS.038 | Fire-stopping of service penetrations | no/crew-day | 15 | 30 | 60 | S-065 |
| PRD.EL.001 | LV cable termination & connection at feeder pillar / board / pit (per circuit) | no/day per crew | 4 | 8 | 15 | S-252 |
| PRD.EL.002 | Set & connect LV feeder pillar / distribution board / metering pillar | no/day per crew | 1 | 2 | 4 | S-252 |
| PRD.EL.003 | Lighting-column footing (auger/excavate, cage, pour ~0.5-1.5 m3 each) | no/day per crew | 3 | 6 | 10 | S-252 |
| PRD.EL.004 | Erect lighting column / pole + outreach arm (set on footing, plumb, base-wire) | no/day per crew | 4 | 8 | 14 | S-252 |
| PRD.EL.005 | Mount, wire, lamp & aim road-lighting luminaire (per luminaire) | no/day per crew | 6 | 12 | 20 | S-252 |
| PRD.EL.006 | High-mast lighting tower assemble, erect & lowering-frame (per mast) | mast/day | 0.5 | 1 | 2 | S-252 |
| PRD.EL.007 | Traffic-signal post / pole / mast-arm + footing (per post) | no/day per crew | 2 | 4 | 6 | S-252 |
| PRD.EL.008 | Mount & wire traffic-signal lantern group / pedestrian / display (per face) | no/day per crew | 4 | 8 | 14 | S-252 |
| PRD.EL.009 | Saw-cut & install inductive vehicle detector loop (per loop) | no/day per crew | 3 | 6 | 10 | S-252 |
| PRD.EL.010 | Set & wire signal controller cabinet + cutover/commission intersection | days/intersection | 1 | 2 | 3 | S-252 |
| PRD.EL.011 | Install ITS field device (CCTV / roadside VMS / ramp-meter / detector) + terminate | no/day per crew | 1 | 3 | 6 | S-252 |
| PRD.EL.012 | Haul optical-fibre / comms cable into conduit (roadside backbone) | m/day per crew | 300 | 600 | 1200 | S-252 |
| PRD.EL.013 | Optical-fibre splice & terminate + OTDR test (per splice/fusion) | no/day per splicer | 12 | 24 | 48 | S-252 |
| PRD.EL.014 | Establish & fit comms pit / node / roadside cabinet (per node) | no/day per crew | 2 | 4 | 8 | S-252 |
| PRD.EL.015 | Energise + functional & illuminance commission a lighting circuit/run (AS/NZS 1158) | days/circuit | 1 | 2 | 4 | S-252 |
| PRD.EL.016 | Functional commission + road-authority acceptance of signals/ITS (per intersection/device) | days/intersection | 1 | 3 | 6 | S-252 |
Construction references
- CivicIndustrial Building Construction
- Building Services MEP Fitout and Commissioning
- Demolition Strip Out and Structural Alteration
- HVLV Reticulation Cabling