- Pole and mastCheck support geometry and installation records.
- Cable pitTrack conduits, connections and as-built location.
- Access platformAllow for traffic staging and the workable access window.
Work scope and interfaces
What it is & where used
Used at signalised intersections, on motorways (ITS/managed-motorway), and at any monitored/controlled roadside location. Each ITS device = cabinet + device + power tail + comms tail.
Related work packages
Construction sequence
- Conduit + pits + footings (civil first)
- Erect posts/mast-arms + footings
- Install lanterns + detection (loops cut into pavement / cameras)
- Install controller / ITS cabinet
- Pull power + comms cables
- Terminate & configure
- FUNCTIONAL COMMISSIONING (phasing, detection, fail-safe)
- CONNECT to the authority's traffic-control / ITS system
- Handover. ITS device: cabinet
- Device (CCTV/VMS/sensor)
- Power + comms
- Configure
- Integrate & prove end-to-end (Communications, Fibre & SCADA).
The make-or-break: functional commissioning + authority connection (the signal/ITS isn't done until it works in the authority's system — the schedule risk), and detection accuracy (loops/cameras).
Plant, resources and measurement
L.CREW.CABLE (install + terminate) + civil for footings/conduit/pits; materials M.SIGNAL.POST/.MASTARM/ .LANTERN/controller, M.ITS.CABINET/M.ITS.CCTV/M.ITS.VMS/sensors. Measured: signals per intersection (LS) or per element (no), ITS devices per no (cabinet+device+tails), commissioning + authority connection LS. Priced items: EL.04.* (signals — post/mast-arm/lantern/controller/detection), EL.05.* (ITS — cabinet/ CCTV/VMS/sensors). VMS/sign-gantry & signal-install are documented big-tickets.
Shared hoists, crane time, access and floor-cycle releases affect several trades together.
View Buildings and electrical services productivity referencesPackage productivity
Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.
| Component activity | Published basis | Low | Typical | High | Library source |
|---|---|---|---|---|---|
| Traffic-signal post / pole / mast-arm + footing (per post)PRD.EL.007 | no/day per crew | 2 | 4 | 6 | S-252 |
| Set & wire signal controller cabinet + cutover/commission intersectionPRD.EL.010 | days/intersection | 1 | 2 | 3 | S-252 |
Survey conformance and lot release
- Observe
- Check signal poles, device locations, duct crossings and detection zones against the approved layout.
- Compare
- Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
- Verify and hand over
- Link asset IDs and controller acceptance records to the authorised traffic switch.
- Resolve exceptions
- Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations
Conduit/pit & footing set-out, cable test, controller configuration & phasing, detection calibration, functional commissioning (fail-safe, conflict monitor), authority connection/acceptance, ITS end-to-end proving. Risks: authority connection/commissioning lead time (the dominant schedule risk), detection accuracy, controller/ITS-device lead time, comms dependency (Communications, Fibre & SCADA), traffic staging for loop cutting/pole erection. Pairs with the road-furniture side (Traffic discipline) and comms (Communications, Fibre & SCADA).
Evidence and related work
Internal record EL-SIGNALS-ITS-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.