Work scope and interfaces
What it is & where used
Temporary anchors (typ. < 2 years — basement/excavation tie-backs, removed or de-stressed on completion) vs permanent anchors (design-life retention, dam tie-down, anti-flotation — double corrosion protection (DCP) mandatory). Used for: anchored retaining walls (soldier-pile Excavation Support, secant/contiguous Secant & Contiguous Bored Pile Walls, diaphragm Diaphragm Walls, sheet-pile Sheet Piles); tie-down against uplift/overturning (dams, basements, buoyant slabs, tension footings); rock-slope stabilisation; dolphin/quay-wall tie-backs.
Related work packages
Construction sequence
- Set out & drill the anchor hole (cased where unstable)
- Install the prepared tendon (strand bundle or bar, with free-length sheathing + DCP for permanent)
- Primary-grout the bond zone (gravity tremie or pressure/post-grout)
- Cure
- (suitability/investigation test on sacrificial anchors)
- Stress & PROOF-TEST each anchor against the waling/wall
- LOCK-OFF to design load
- Grout/protect the free length & fit the protective cap (permanent)
- Monitor / re-stress as required.
The make-or-break: the bond-length capacity actually achieved (proven by the proof test — if it fails, the anchor is re-drilled/post-grouted/replaced, the hidden re-work cost), the double corrosion protection on permanent anchors (a tendon-fabrication + grouting cost a bare drilled-metre rate misses), and the excavate-then-support staging where each anchor row is installed and stressed before the cut below is taken (support-before-dig).
Plant, resources and measurement
Crew [L.CREW.GEOTECH] + anchor drill rig [G.PLANT.ANCHOR] (or surface rig [G.PLANT.DRILL]) + grout pump [G.PLANT.GROUTPUMP] + stressing jack; materials ground-anchor tendon [M.ANCHOR.GROUND] (permanent, DCP) / [M.ANCHOR.TEMP] (temporary), strand/bar [M.PRESTRESS.STRAND] / [M.PRESTRESS.ANCHOR], annulus/bond grout [M.GROUT.ANNULUS], galvanising/coating [M.COAT.GALV]. Component docs: PLANT-ANCHOR-001, PLANT-DRILL-001, MAT-GROUT-001, MAT-PRESTRESS-001.
Measured/priced through the GT.04 anchor spine in DB-GT-001 (measurement & deemed-inclusions in PS-GT-D1-001):
• GT.04.010.01 Permanent ground anchor (double-corrosion-protected) — drill, install, grout, stress, lock-off — unit: no. (per installed, stressed & locked-off anchor)
• GT.04.010.02 Temporary ground anchor — drill, install, stress & (later) remove/de-stress — unit: no.
• GT.04.050.01 Anchor / nail proof & acceptance load testing — unit: no. per test (the reinforcement gate — priced explicitly, never deemed into the anchor rate)
The element is the quantity; the drill-grout-stress cycle is the rate. Watch flat per-anchor rates that bury the proof test, the DCP premium on permanent anchors, casing through unstable ground, and the excavate-then- support staging (a programme/access cost, not a unit rate).
Track rig setup, installed depth, material consumption, verification tests and monitoring separately.
View Geotechnical and ground improvement productivity referencesPackage productivity
Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.
| Component activity | Published basis | Low | Typical | High | Library source |
|---|---|---|---|---|---|
| Permanent ground anchor (double-corrosion-protected) - drillGT.04.010.01 | no/day | — | 4 | — | PROD-GEOTECH-001 |
| Temporary ground anchor - drill, install, stress & removeGT.04.010.02 | no/day | — | 5 | — | PROD-GEOTECH-001 |
Survey conformance and lot release
- Observe
- Set out collar position, inclination and row spacing and reconcile installed length with the drill log.
- Compare
- Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
- Verify and hand over
- Identify each element on the grouting and proof or acceptance testing register.
- Resolve exceptions
- Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations
Hold points / tests: investigation/suitability test on sacrificial anchors (bond capacity), proof test on each anchor (load–extension to acceptance, no excessive creep), acceptance/lock-off to design load with verified residual load; grout strength & bond-length verification; DCP integrity (sheath/grout cover) on permanent anchors; anchor-head/cap detail. Risks: bond capacity not achieved in weaker-than-baseline ground → post-grout / re- drill / additional anchors (latent-conditions exposure); proof test omitted from price (the specialist gate); DCP under-specified on permanent anchors → durability/de-bond failure; load loss/creep at lock-off requiring re-stress; excavate-then-support staging mismanaged (cut taken before the row is stressed); free-length grouting of a temporary anchor that must later be de-stressed. Pairs with the wall it ties back (Excavation Support, Secant & Contiguous Bored Pile Walls, Diaphragm Walls, Sheet Piles) and the shotcrete/facing on a nailed face (Shotcrete / Sprayed Concrete); method spine in DISC-GEOTECH-METH-001; test register TEST-INDEX-001.
Evidence and related work
Internal record GEO-ANCHOR-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.