Discipline library

Geotechnical and ground improvement

Work from investigated ground zones. Release trial treatment, install by grid or wall panel and verify the treatment before excavation or foundation loading.

Geotechnical and ground improvement
  1. Drilling rigRecord the installed length and drilling conditions by location.
  2. Soil nailTie the bar, grout and test records to the installed element.
  3. Face supportInspect the mesh and facing before advancing the excavation stage.
Illustrative workfront within Geotechnical and ground improvement.

Construction and release sequence

  1. Define treatment zones from the ground model and trial results
  2. Prepare the platform, services and specialist spread
  3. Install elements in the approved pattern and record each cycle
  4. Verify test results and surveyed treatment extent before release

Work packages and conformance checks

Ground AnchorsSet out collar position, inclination and row spacing and reconcile installed length with the drill log.Secant & Contiguous Bored Pile WallsSurvey wall line, top and toe evidence, verticality and interfaces with excavation supports.Dewatering & Groundwater ControlRecord well and piezometer coordinates, screen intervals and reference levels.Deep Soil Mixing (DSM / CSM)Survey treatment centres, overlap patterns and top and bottom elevations from logged depths.Diaphragm WallsSurvey wall line, top and toe evidence, verticality and interfaces with excavation supports.Dynamic Compaction & Rapid Impact CompactionMark the treatment grid and survey the before-and-after platform surfaces.Artificial Ground FreezingLocate treatment holes and monitoring points in the same grid as adjacent structures.Geotechnical Grouting — Permeation, Compaction & FractureLocate treatment holes and monitoring points in the same grid as adjacent structures.Jet GroutingSurvey treatment centres, overlap patterns and top and bottom elevations from logged depths.Micropiles (Minipiles)Locate each pile head and inclination. Tie socket or bond length to the drilling log and reference level.Reinforced Soil / MSE WallsSurvey face batter, panel line and reinforcement limits by lift before burial.Prefabricated Vertical (Wick) Drains + SurchargeSet out drain centres and record installed depths relative to the working platform.Rock Bolts & DowelsSet out collar position, inclination and row spacing and reconcile installed length with the drill log.Sheet PilesSurvey wall line, top and toe evidence, verticality and interfaces with excavation supports.Excavation Support — Soldier-Pile & Soil-Nail WallsSurvey wall line, top and toe evidence, verticality and interfaces with excavation supports.Soil NailsSet out collar position, inclination and row spacing and reconcile installed length with the drill log.In-Situ Stabilisation — Lime, Cement & Foamed BitumenMark the treatment grid and survey the before-and-after platform surfaces.Vibro Stone ColumnsSurvey treatment centres, overlap patterns and top and bottom elevations from logged depths.Shotcrete / Sprayed ConcreteCompare substrate and finished profiles at reference pins or scan sections.

Technique rates and labour allowances

The source records typical values. Its hourly allowances, output rates and shift quantities each retain their published basis.

Component activityPublished basisLowTypicalHighLibrary source
Mobilise / demobilise geotechnical drilling rig and crewGT.01.010.01hr (direct)—16—PROD-GEOTECH-001
Cased rotary / auger borehole in soil incl. loggingGT.01.020.01m/hr—4—PROD-GEOTECH-001
Extra-over borehole for coring in rock (triple-tube)GT.01.020.02m/hr—2.5—PROD-GEOTECH-001
Standard Penetration Test (SPT) with split-spoon sampleGT.01.030.01no/shift—12—PROD-GEOTECH-001
Cone Penetration Test (CPTu) sounding incl. pore-pressureGT.01.030.02m/day—80—PROD-GEOTECH-001
Test pit excavation, logging, sampling & reinstatementGT.01.040.01no/day—6—PROD-GEOTECH-001
Undisturbed (U50/U75) tube sampling - per sampleGT.01.050.01no/day—10—PROD-GEOTECH-001
Laboratory soil classification suite (Atterberg, PSD, moistuGT.01.060.01no/day—8—PROD-GEOTECH-001
Geotechnical engineering test suite (CBR, shear, consolidatiGT.01.060.02no/day—3—PROD-GEOTECH-001
Factual / interpretive geotechnical investigation reportGT.01.070.01hr (direct)—80—PROD-GEOTECH-001
Vibro-compaction / vibro-flotation of granular soilsGT.02.010.01m/hr—30—PROD-GEOTECH-001
Stone / aggregate column (vibro-replacement), by lengthGT.02.020.01m/hr—20—PROD-GEOTECH-001
Dynamic compaction (drop-weight) incl. ironing passGT.02.030.01m2/day (ref PRD.MAR.020)—2000—PROD-GEOTECH-001
Rapid impact compaction (RIC) of fill / loose soilsGT.02.040.01m2/day—2500—PROD-GEOTECH-001
Pre-load / surcharge embankment with PVD-assisted consolidatGT.02.050.01m3/hr (ref PRD.EW.014)—300—PROD-GEOTECH-001
Prefabricated vertical (wick) drain - supply & installGT.02.060.01lm/rig/day (ref PRD.MAR.019)—6000—PROD-GEOTECH-001
Deep soil mixing (DSM / cement-bentonite) columnGT.03.010.01m3/hr—12—PROD-GEOTECH-001
Wet soil mixing column, 600-1000 mm dia - by lengthGT.03.010.02m/hr—24—PROD-GEOTECH-001
Jet grouting column - supply, mix design & installGT.03.020.01m/hr—6—PROD-GEOTECH-001
Permeation / compaction grouting - injected groutGT.03.030.01m3/hr—5—PROD-GEOTECH-001
Grout hole drilling & set-up for injection - by depthGT.03.030.02m/hr—8—PROD-GEOTECH-001
Cavity / void / sinkhole infill grouting (cementitious)GT.03.040.01m3/hr—6—PROD-GEOTECH-001
Controlled low-strength material (CLSM / flowable fill)GT.03.050.01m3/hr—25—PROD-GEOTECH-001
Permanent ground anchor (double-corrosion-protected) - drillGT.04.010.01no/day—4—PROD-GEOTECH-001
Temporary ground anchor - drill, install, stress & removeGT.04.010.02no/day—5—PROD-GEOTECH-001
Soil nail (grouted bar) - drill, install & grout, by lengthGT.04.020.01m/day—60—PROD-GEOTECH-001
Rock bolt / dowel - drill, install & groutGT.04.030.01no/day—16—PROD-GEOTECH-001
Shotcrete facing to nailed cut (incl. mesh / fibre)GT.04.040.01m2/day—120—PROD-GEOTECH-001
Anchor / nail proof & acceptance load testing - per testGT.04.050.01no/day—6—PROD-GEOTECH-001
Reinforced soil wall (MSE) - facing, soil reinforcement & fiGT.05.010.01m2/day—30—PROD-GEOTECH-001
Geogrid / geotextile reinforcement layer - supply & layGT.05.020.01m2/day—1000—PROD-GEOTECH-001
Separation / filtration geotextile to subgrade or drainageGT.05.030.01m2/day—1200—PROD-GEOTECH-001
Basal reinforcement / geocell mattress over soft groundGT.05.040.01m2/day—600—PROD-GEOTECH-001
Working platform (geogrid-stabilised granular raft)GT.05.050.01m2/day—400—PROD-GEOTECH-001
In-situ lime stabilisation of subgrade - spread, mix & compaGT.06.010.01m2/day—4000—PROD-GEOTECH-001
In-situ cement / cement-blend stabilisation - spread, mix &GT.06.020.01m2/day—3500—PROD-GEOTECH-001
Foamed bitumen / bitumen-stabilised subbase - in-situGT.06.040.01m2/day—2500—PROD-GEOTECH-001
Soft-spot / unsuitable material treatment - excavate & replaGT.06.050.01m3/hr—40—PROD-GEOTECH-001
Wellpoint dewatering system - install, operate & decommissioGT.07.010.01hr (direct)—360—PROD-GEOTECH-001
Deep-well / spear-point dewatering - establish & operateGT.07.010.02hr (direct)—90—PROD-GEOTECH-001
Sump / open-pumping dewatering - pump, settlement & dischargGT.07.020.01hr (direct)—45—PROD-GEOTECH-001
Subsoil / fin drain (slotted pipe, aggregate, geotextile)GT.07.030.01m/day—120—PROD-GEOTECH-001
Horizontal drain (weep / relief bore) into cut faceGT.07.040.01m/day—40—PROD-GEOTECH-001
Cut-off wall (soil-bentonite) for seepage control - by faceGT.07.050.01m2/hr—40—PROD-GEOTECH-001
Driven sheet-pile wall (permanent/temporary) - by face areaGT.07.050.02m2/hr—12—PROD-GEOTECH-001
Standpipe / vibrating-wire piezometer - supply & installGT.08.010.01no/day—3—PROD-GEOTECH-001
Settlement plate / magnetic extensometer - supply & installGT.08.020.01no/day—6—PROD-GEOTECH-001
Inclinometer casing - supply, install & surveyGT.08.030.01no/day—2—PROD-GEOTECH-001
Geotechnical monitoring & reporting - periodic read & reportGT.08.040.01hr (direct)—12—PROD-GEOTECH-001
Acid sulfate soil (ASS) management - neutralise, treat & valGT.08.050.01m3/hr—60—PROD-GEOTECH-001
Classify, load & dispose contaminated / unsuitable spoilGT.08.060.01t/hr—60—PROD-GEOTECH-001
Mobilisation of plant, crews and facilities to site (establiGT.90.010.01hr (direct)—72—PROD-GEOTECH-001
Demobilisation and site restoration on completionGT.90.020.01hr (direct)—36—PROD-GEOTECH-001
Time-related site costs (supervision, facilities, plant stanGT.90.030.01hr (direct)—45—PROD-GEOTECH-001
Standing time / standby due to Principal-caused delay (per hGT.90.040.01hr (direct)—1—PROD-GEOTECH-001

Production and measurement

Track rig setup, installed depth, material consumption, verification tests and monitoring separately.

View the discipline reference figureGeotechnical and ground improvement reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

Use the linked discipline record and measured project outputs to establish the planning basis.