- Drilling rigRecord the installed length and drilling conditions by location.
- Soil nailTie the bar, grout and test records to the installed element.
- Face supportInspect the mesh and facing before advancing the excavation stage.
Construction and release sequence
- Define treatment zones from the ground model and trial results
- Prepare the platform, services and specialist spread
- Install elements in the approved pattern and record each cycle
- Verify test results and surveyed treatment extent before release
Work packages and conformance checks
Technique rates and labour allowances
The source records typical values. Its hourly allowances, output rates and shift quantities each retain their published basis.
| Component activity | Published basis | Low | Typical | High | Library source |
|---|---|---|---|---|---|
| Mobilise / demobilise geotechnical drilling rig and crewGT.01.010.01 | hr (direct) | — | 16 | — | PROD-GEOTECH-001 |
| Cased rotary / auger borehole in soil incl. loggingGT.01.020.01 | m/hr | — | 4 | — | PROD-GEOTECH-001 |
| Extra-over borehole for coring in rock (triple-tube)GT.01.020.02 | m/hr | — | 2.5 | — | PROD-GEOTECH-001 |
| Standard Penetration Test (SPT) with split-spoon sampleGT.01.030.01 | no/shift | — | 12 | — | PROD-GEOTECH-001 |
| Cone Penetration Test (CPTu) sounding incl. pore-pressureGT.01.030.02 | m/day | — | 80 | — | PROD-GEOTECH-001 |
| Test pit excavation, logging, sampling & reinstatementGT.01.040.01 | no/day | — | 6 | — | PROD-GEOTECH-001 |
| Undisturbed (U50/U75) tube sampling - per sampleGT.01.050.01 | no/day | — | 10 | — | PROD-GEOTECH-001 |
| Laboratory soil classification suite (Atterberg, PSD, moistuGT.01.060.01 | no/day | — | 8 | — | PROD-GEOTECH-001 |
| Geotechnical engineering test suite (CBR, shear, consolidatiGT.01.060.02 | no/day | — | 3 | — | PROD-GEOTECH-001 |
| Factual / interpretive geotechnical investigation reportGT.01.070.01 | hr (direct) | — | 80 | — | PROD-GEOTECH-001 |
| Vibro-compaction / vibro-flotation of granular soilsGT.02.010.01 | m/hr | — | 30 | — | PROD-GEOTECH-001 |
| Stone / aggregate column (vibro-replacement), by lengthGT.02.020.01 | m/hr | — | 20 | — | PROD-GEOTECH-001 |
| Dynamic compaction (drop-weight) incl. ironing passGT.02.030.01 | m2/day (ref PRD.MAR.020) | — | 2000 | — | PROD-GEOTECH-001 |
| Rapid impact compaction (RIC) of fill / loose soilsGT.02.040.01 | m2/day | — | 2500 | — | PROD-GEOTECH-001 |
| Pre-load / surcharge embankment with PVD-assisted consolidatGT.02.050.01 | m3/hr (ref PRD.EW.014) | — | 300 | — | PROD-GEOTECH-001 |
| Prefabricated vertical (wick) drain - supply & installGT.02.060.01 | lm/rig/day (ref PRD.MAR.019) | — | 6000 | — | PROD-GEOTECH-001 |
| Deep soil mixing (DSM / cement-bentonite) columnGT.03.010.01 | m3/hr | — | 12 | — | PROD-GEOTECH-001 |
| Wet soil mixing column, 600-1000 mm dia - by lengthGT.03.010.02 | m/hr | — | 24 | — | PROD-GEOTECH-001 |
| Jet grouting column - supply, mix design & installGT.03.020.01 | m/hr | — | 6 | — | PROD-GEOTECH-001 |
| Permeation / compaction grouting - injected groutGT.03.030.01 | m3/hr | — | 5 | — | PROD-GEOTECH-001 |
| Grout hole drilling & set-up for injection - by depthGT.03.030.02 | m/hr | — | 8 | — | PROD-GEOTECH-001 |
| Cavity / void / sinkhole infill grouting (cementitious)GT.03.040.01 | m3/hr | — | 6 | — | PROD-GEOTECH-001 |
| Controlled low-strength material (CLSM / flowable fill)GT.03.050.01 | m3/hr | — | 25 | — | PROD-GEOTECH-001 |
| Permanent ground anchor (double-corrosion-protected) - drillGT.04.010.01 | no/day | — | 4 | — | PROD-GEOTECH-001 |
| Temporary ground anchor - drill, install, stress & removeGT.04.010.02 | no/day | — | 5 | — | PROD-GEOTECH-001 |
| Soil nail (grouted bar) - drill, install & grout, by lengthGT.04.020.01 | m/day | — | 60 | — | PROD-GEOTECH-001 |
| Rock bolt / dowel - drill, install & groutGT.04.030.01 | no/day | — | 16 | — | PROD-GEOTECH-001 |
| Shotcrete facing to nailed cut (incl. mesh / fibre)GT.04.040.01 | m2/day | — | 120 | — | PROD-GEOTECH-001 |
| Anchor / nail proof & acceptance load testing - per testGT.04.050.01 | no/day | — | 6 | — | PROD-GEOTECH-001 |
| Reinforced soil wall (MSE) - facing, soil reinforcement & fiGT.05.010.01 | m2/day | — | 30 | — | PROD-GEOTECH-001 |
| Geogrid / geotextile reinforcement layer - supply & layGT.05.020.01 | m2/day | — | 1000 | — | PROD-GEOTECH-001 |
| Separation / filtration geotextile to subgrade or drainageGT.05.030.01 | m2/day | — | 1200 | — | PROD-GEOTECH-001 |
| Basal reinforcement / geocell mattress over soft groundGT.05.040.01 | m2/day | — | 600 | — | PROD-GEOTECH-001 |
| Working platform (geogrid-stabilised granular raft)GT.05.050.01 | m2/day | — | 400 | — | PROD-GEOTECH-001 |
| In-situ lime stabilisation of subgrade - spread, mix & compaGT.06.010.01 | m2/day | — | 4000 | — | PROD-GEOTECH-001 |
| In-situ cement / cement-blend stabilisation - spread, mix >.06.020.01 | m2/day | — | 3500 | — | PROD-GEOTECH-001 |
| Foamed bitumen / bitumen-stabilised subbase - in-situGT.06.040.01 | m2/day | — | 2500 | — | PROD-GEOTECH-001 |
| Soft-spot / unsuitable material treatment - excavate & replaGT.06.050.01 | m3/hr | — | 40 | — | PROD-GEOTECH-001 |
| Wellpoint dewatering system - install, operate & decommissioGT.07.010.01 | hr (direct) | — | 360 | — | PROD-GEOTECH-001 |
| Deep-well / spear-point dewatering - establish & operateGT.07.010.02 | hr (direct) | — | 90 | — | PROD-GEOTECH-001 |
| Sump / open-pumping dewatering - pump, settlement & dischargGT.07.020.01 | hr (direct) | — | 45 | — | PROD-GEOTECH-001 |
| Subsoil / fin drain (slotted pipe, aggregate, geotextile)GT.07.030.01 | m/day | — | 120 | — | PROD-GEOTECH-001 |
| Horizontal drain (weep / relief bore) into cut faceGT.07.040.01 | m/day | — | 40 | — | PROD-GEOTECH-001 |
| Cut-off wall (soil-bentonite) for seepage control - by faceGT.07.050.01 | m2/hr | — | 40 | — | PROD-GEOTECH-001 |
| Driven sheet-pile wall (permanent/temporary) - by face areaGT.07.050.02 | m2/hr | — | 12 | — | PROD-GEOTECH-001 |
| Standpipe / vibrating-wire piezometer - supply & installGT.08.010.01 | no/day | — | 3 | — | PROD-GEOTECH-001 |
| Settlement plate / magnetic extensometer - supply & installGT.08.020.01 | no/day | — | 6 | — | PROD-GEOTECH-001 |
| Inclinometer casing - supply, install & surveyGT.08.030.01 | no/day | — | 2 | — | PROD-GEOTECH-001 |
| Geotechnical monitoring & reporting - periodic read & reportGT.08.040.01 | hr (direct) | — | 12 | — | PROD-GEOTECH-001 |
| Acid sulfate soil (ASS) management - neutralise, treat & valGT.08.050.01 | m3/hr | — | 60 | — | PROD-GEOTECH-001 |
| Classify, load & dispose contaminated / unsuitable spoilGT.08.060.01 | t/hr | — | 60 | — | PROD-GEOTECH-001 |
| Mobilisation of plant, crews and facilities to site (establiGT.90.010.01 | hr (direct) | — | 72 | — | PROD-GEOTECH-001 |
| Demobilisation and site restoration on completionGT.90.020.01 | hr (direct) | — | 36 | — | PROD-GEOTECH-001 |
| Time-related site costs (supervision, facilities, plant stanGT.90.030.01 | hr (direct) | — | 45 | — | PROD-GEOTECH-001 |
| Standing time / standby due to Principal-caused delay (per hGT.90.040.01 | hr (direct) | — | 1 | — | PROD-GEOTECH-001 |
Production and measurement
Track rig setup, installed depth, material consumption, verification tests and monitoring separately.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
Use the linked discipline record and measured project outputs to establish the planning basis.
Construction references
- Ground Improvement Retention
- Dewatering and Groundwater Control
- Slope Stabilisation and Rockfall Protection