- Drilling rigRecord the installed length and drilling conditions by location.
- Soil nailTie the bar, grout and test records to the installed element.
- Face supportInspect the mesh and facing before advancing the excavation stage.
Work scope and interfaces
What it is
Deep dynamic ground improvement by repeated controlled impact, covering two related techniques. Dynamic Compaction (DC) drops a heavy steel or concrete pounder (typically 8-25 t, up to ~40 t for deep work) in free fall from 10-30 m using a crawler crane onto a grid of print locations, transmitting impact energy that densifies loose, collapsible or poorly placed soils at depth. Rapid Impact Compaction (RIC) is the shallow analogue: a 7-16 t hammer falls ~1.2 m onto a ~1.5 m diameter articulated steel foot plate, delivered by an excavator-mounted hydraulic rig at 40-60 blows/minute, densifying the upper 3-6 m. Both reduce void ratio, increase relative density/stiffness and bearing capacity, mitigate liquefaction and collapse-settlement potential, and pre-induce settlement of fills before foundation or pavement construction. Output is a verified ground-improvement layer, not a structural element.
When used / ground suitability
Used to treat loose to medium-dense granular soils, uncontrolled/heterogeneous fills (including building rubble, mine spoil, reclamation and former-quarry/landfill platforms), collapsible and partially saturated soils, and loose hydraulic sand fills prone to liquefaction. Typical applications: reclamation platforms, large warehouse/industrial slabs, road and rail embankment foundations, storage-tank and laydown areas, and remediation of legacy fill. Ground suitability and limits: BEST in free-draining granular/cohesionless soils and granular fills above the water table; partially suitable for mixed/cohesive fills where pore pressures can dissipate (longer rest periods, multiple passes/ironing). POORLY suited to saturated soft clays, silts and organic/peaty soils where excess pore pressure cannot dissipate and remoulding/heave results (use surcharge + prefabricated vertical drains Prefabricated Vertical (Wick) Drains + Surcharge, vibro stone columns Vibro Stone Columns or vibro compaction instead — DC/RIC sit alongside these as the *granular-fill densification* sibling in the ground-improvement family, see methodology DISC-GEOTECH-METH-001). DC depth of influence D (m) approximates D = n*sqrt(W*H) with n ~ 0.3-0.5 (W = pounder mass in t, H = drop in m), practically 4-10 m+; RIC is limited to ~3-6 m and best near-surface / for trafficable working platforms. Key constraints: ground vibration (PPV) and ground-borne noise restrict use near existing structures, services and sensitive receptors (typical 20-40 m standoff, site-specific by PPV monitoring against AS 2187.2-type / BS 7385 criteria); high water table reduces effectiveness; soft surface crust may need a granular working blanket; not suitable where buried services/voids preclude impact. A pre-treatment geotechnical investigation to AS 1726 (and CPT/borehole baseline) is mandatory.
Related work packages
Construction sequence
- Geotechnical baseline and design: site investigation to AS 1726 (boreholes/CPT, groundwater, fill characterisation); set target depth D, required energy density (t.m/m2), grid, passes and acceptance criteria; vibration/settlement risk assessment and receptor/services standoff (dial-before-you-dig, potholing).
- Site establishment and platform preparation: clear and grub, strip topsoil, place and proof-roll a granular working blanket (MAT-FILL-001 / MAT-AGG-001) to give a trafficable, free-draining platform and protect plant; survey and peg the primary print grid.
- Baseline monitoring setup: install pre-treatment CPT/SPT reference points, settlement/level survey datum, pore-pressure piezometers in finer fills, and vibration (PPV) monitors at the nearest structures/services.
- Primary (high-energy) pass - DC: position crawler crane (PLANT-CRN-CRAWL-001) with free-fall pounder over each primary print; deliver the specified blows per print, logging crater depth per drop until the set/refusal or specified blow count is reached. RIC: track the excavator-mounted rig (PLANT-GROUND-001) across the grid delivering 40-60 blows/min per print to the specified compaction (auto-recorded set/penetration).
- Crater backfill and level-up: backfill primary craters with imported granular fill (MAT-FILL-001), grade and re-level the platform between passes.
- Pore-pressure dissipation / rest period: in mixed or finer fills, monitor piezometers and pause between passes until excess pore pressure dissipates to the specified threshold before re-impacting.
- Secondary and tertiary passes: repeat impact on offset/intermediate grid points (and additional passes) to achieve full plan coverage and the cumulative energy density; backfill and level each pass.
- Ironing pass: low-energy, low-drop blows on a close/overlapping grid (or a vibratory roller pass, PLANT-ROLLER-001) to densify the upper metre disturbed by high-energy impacts and tidy the surface.
- Final trim, level and proof-roll the treated platform to design level and tolerance.
- Verification testing: post-treatment CPT/SPT, plate-load or geophysical testing and settlement survey against the acceptance criteria (relative density / qc / N / modulus); compare to baseline; issue ground-improvement validation report. Re-treat any non-conforming zones.
- Demobilise; reinstate surface and hand over the validated platform for foundation/pavement works.
Plant, resources and measurement
Crew & plant: the spread is a ground-improvement crew (L.CREW.GROUND.IMPROVE) operating either the DC train — a heavy-duty crawler crane (PLANT-CRN-CRAWL-001, ~300 t class, G.PLANT.CRN.CRAWL300) free-falling a 10-30 t pounder (the dynamic-compaction rig family G.PLANT.GROUND.DYN) — or the RIC train — an excavator-mounted hydraulic hammer rig (PLANT-GROUND-001). Support plant: a tracked excavator (PLANT-EXC-001, G.PLANT.EXC.30T) for crater backfill, grading and platform level-up, and a vibratory roller (PLANT-ROLLER-001, G.PLANT.ROLLER) for the ironing pass and platform proof-roll.
Materials: imported granular crater backfill and the trafficable working blanket (MAT-FILL-001 M.FILL.PLATFORM, MAT-AGG-001) — the platform is consumable, re-graded between every pass, so backfill quantity rises with crater volume and the number of passes.
Measurement: DC/RIC are measured by treated plan area (m²), banded by target depth / specified energy density (t.m/m²), with mobilisation/demobilisation of the heavy rig spread carried as a separate lump item (rig establishment is a step-change cost that amortises over the treated area — a 2,000 m² job is far dearer $/m² than a 50,000 m² platform). Crater backfill and the working blanket price as supply-and-place fill sub-rates; verification testing (CPT/SPT/plate-load + settlement survey, TEST-INDEX-001) is its own priced line and is never deemed into the production rate — the same acceptance-gate discipline the stone-column zone load test follows. Specialist sub-contract item per SPEC-007 (Group A — ground engineering); the Library carries no dedicated DC build-up yet, so the rig-cycle rate is taken from the productivity band, tokenised against vendor rig data {{CONFIRM rig spread + energy-per-blow vs ground model}}.
Productivity: the verified band is PRD.MAR.020 (dynamic compaction, 800 – 2,000 – 4,000 m²/day; coverage {{CONFIRM}} per ground class and energy density) — the rate falls sharply with deeper treatment, higher specified energy density, more passes, and obstruction-prone/legacy fills. The RIC analogue has no separate Library band (shallower, faster, near-surface) — set it from the vendor rig output {{CONFIRM RIC rate}}; the nearest "grid is the quantity, rig-shift is the rate" neighbour is PRD.MAR.019 (PVD installation, 3,000 – 6,000 – 10,000 lm/rig/day), confirming the family signature.
Track rig setup, installed depth, material consumption, verification tests and monitoring separately.
View Geotechnical and ground improvement productivity referencesPackage productivity
Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.
| Component activity | Published basis | Low | Typical | High | Library source |
|---|---|---|---|---|---|
| Dynamic compaction (drop-weight) incl. ironing passGT.02.030.01 | m2/day (ref PRD.MAR.020) | — | 2000 | — | PROD-GEOTECH-001 |
| Rapid impact compaction (RIC) of fill / loose soilsGT.02.040.01 | m2/day | — | 2500 | — | PROD-GEOTECH-001 |
Survey conformance and lot release
- Observe
- Mark the treatment grid and survey the before-and-after platform surfaces.
- Compare
- Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
- Verify and hand over
- Issue treatment pass records and specified improvement test results by ground zone.
- Resolve exceptions
- Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Evidence and related work
Internal record GEO-DYNCOMP-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.