Surface mining and rehabilitation

Overburden removal and mine haulage

Compare bench and dump surfaces inside common monthly cutoffs and approved boundaries.

Surface mining and rehabilitation
  1. Face shovelBucket cycles and truck spotting determine loading output.
  2. Rigid haul truckTrack payload and cycle time on the same operating basis.
  3. Haul roadDistance, grade and condition affect the achieved fleet rate.
Construction context for Overburden removal and mine haulage

Construction sequence

  1. Release the surveyed bench and material destinations.
  2. Match excavator loading to available trucks and dump capacity.
  3. Reconcile dispatched quantities against the closing surface.

Plant, resources and measurement

Keep bank volume, loose volume and haul tonnes on explicit conversion bases. Separate road maintenance, queuing, placement and rehabilitation.

Track dispatched tonnes and surveyed bank volumes on comparable time and density bases.

View Surface mining and rehabilitation productivity references

Package productivity

Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.

Component activityPublished basisLowTypicalHighLibrary source
Large hydraulic excavator (200 t class) loading waste — free-digPRD.MN.001BCM/operating hr60010001500S-065
Rigid rear-dump haul truck, 1.5–2.5 km one-wayPRD.MN.004BCM/truck-hr150300500S-065
Dozer push (D11) rip/push weathered rock, short pushPRD.MN.005BCM/hr300600900S-065

Component duration

Survey conformance and lot release

Observe
Compare bench and dump surfaces inside common monthly cutoffs and approved boundaries.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Reconcile dispatch tonnes, material classification and surveyed bank volume with the adopted density.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.

Evidence and related work

Internal record MN-OVERBURDEN-HAUL-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.