Discipline library

Surface mining and rehabilitation

Reconcile cut, haul and dump by bench and material domain. Verify containment and final rehabilitation surfaces against the approved landform.

Surface mining and rehabilitation
  1. Face shovelBucket cycles and truck spotting determine loading output.
  2. Rigid haul truckTrack payload and cycle time on the same operating basis.
  3. Haul roadDistance, grade and condition affect the achieved fleet rate.
Illustrative workfront within Surface mining and rehabilitation.
Open the Shovel and rigid-truck load and haul calculator

Construction and release sequence

  1. Release haul routes, cut boundaries and receiving areas
  2. Match excavator or shovel loads to the available haul fleet
  3. Reconcile dispatch, containment lifts, drainage and rehabilitation
  4. Survey completed surfaces and record accepted material destinations

Work packages and conformance checks

Production and measurement

Track dispatched tonnes and surveyed bank volumes on comparable time and density bases.

View the discipline reference figureSurface mining and rehabilitation reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.MN.001Large hydraulic excavator (200 t class) loading waste — free-digBCM/operating hr60010001500S-065
PRD.MN.004Rigid rear-dump haul truck, 1.5–2.5 km one-wayBCM/truck-hr150300500S-065
PRD.MN.005Dozer push (D11) rip/push weathered rock, short pushBCM/hr300600900S-065
PRD.MN.006Grader trim / spread of haul-road wearing coursem²/hr60012002500S-065
PRD.MN.007Place & compact unbound pavement layer (sub-base / wearing)m³/day (crew)4008001500S-065
PRD.MN.008Smooth-drum roller compaction of granular layerm²/hr150030005000S-065
PRD.MN.009Structural-steel erection, plant / conveyor structures (mobile crane)t/day (crew)4815S-065
PRD.MN.010Reinforced-concrete foundations to plant (supply/fix/pour, in-situ)m³/day (crew)153060S-065
PRD.MN.011Overland conveyor structure + belt install (ground trestle)m/day (crew)2050100S-065
PRD.MN.012Reinforcement fix to heavy plant footingst/day (crew)1.535S-065
PRD.MN.013Zoned earthfill / rockfill embankment placement & compactionm³/day (fleet)80020004000S-065
PRD.MN.014HDPE geomembrane liner deployment & welding (incl QA) — TSFm²/day (crew)100025004000S-065
PRD.MN.015Filter / transition zone placement & compactionm³/day (crew)3007001200S-065
PRD.MN.016HDPE return-water / tailings pipeline (butt-fusion) installm/day (crew)150300600S-065
PRD.MN.017Geomembrane (LLDPE/HDPE) deployment & welding — leach pad (incl QA)m²/day (crew)200040006000S-065
PRD.MN.018Compacted soil liner (CCL) placement to low permeabilitym²/day (crew)50012002500S-065
PRD.MN.019Overliner drainage gravel placement (LGP dozer, liner protection)m³/day (crew)3007001500S-065
PRD.MN.022Raise-bore pilot + reaming advancem/day3820S-065
PRD.MN.023Wet shotcrete (fibrecrete) application undergroundm³/hr4815S-065
PRD.MN.024Heavy-haul track laying (ballast/sleeper/rail), spur / looptrack-m/day (crew)150300600S-065
PRD.MN.025Structural-steel erection, TLO / stockyard / shiploadert/day (crew)4815S-065
PRD.MN.026Yard / shiploader conveyor structure + belt installm/day (crew)2050100S-065
PRD.MN.027Reinforced-concrete TLO / receival foundations (in-situ)m³/day (crew)153060S-065