Surface mining and rehabilitation
- Face shovelBucket cycles and truck spotting determine loading output.
- Rigid haul truckTrack payload and cycle time on the same operating basis.
- Haul roadDistance, grade and condition affect the achieved fleet rate.
Construction and release sequence
- Release haul routes, cut boundaries and receiving areas
- Match excavator or shovel loads to the available haul fleet
- Reconcile dispatch, containment lifts, drainage and rehabilitation
- Survey completed surfaces and record accepted material destinations
Work packages and conformance checks
Production and measurement
Track dispatched tonnes and surveyed bank volumes on comparable time and density bases.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.MN.001 | Large hydraulic excavator (200 t class) loading waste — free-dig | BCM/operating hr | 600 | 1000 | 1500 | S-065 |
| PRD.MN.004 | Rigid rear-dump haul truck, 1.5–2.5 km one-way | BCM/truck-hr | 150 | 300 | 500 | S-065 |
| PRD.MN.005 | Dozer push (D11) rip/push weathered rock, short push | BCM/hr | 300 | 600 | 900 | S-065 |
| PRD.MN.006 | Grader trim / spread of haul-road wearing course | m²/hr | 600 | 1200 | 2500 | S-065 |
| PRD.MN.007 | Place & compact unbound pavement layer (sub-base / wearing) | m³/day (crew) | 400 | 800 | 1500 | S-065 |
| PRD.MN.008 | Smooth-drum roller compaction of granular layer | m²/hr | 1500 | 3000 | 5000 | S-065 |
| PRD.MN.009 | Structural-steel erection, plant / conveyor structures (mobile crane) | t/day (crew) | 4 | 8 | 15 | S-065 |
| PRD.MN.010 | Reinforced-concrete foundations to plant (supply/fix/pour, in-situ) | m³/day (crew) | 15 | 30 | 60 | S-065 |
| PRD.MN.011 | Overland conveyor structure + belt install (ground trestle) | m/day (crew) | 20 | 50 | 100 | S-065 |
| PRD.MN.012 | Reinforcement fix to heavy plant footings | t/day (crew) | 1.5 | 3 | 5 | S-065 |
| PRD.MN.013 | Zoned earthfill / rockfill embankment placement & compaction | m³/day (fleet) | 800 | 2000 | 4000 | S-065 |
| PRD.MN.014 | HDPE geomembrane liner deployment & welding (incl QA) — TSF | m²/day (crew) | 1000 | 2500 | 4000 | S-065 |
| PRD.MN.015 | Filter / transition zone placement & compaction | m³/day (crew) | 300 | 700 | 1200 | S-065 |
| PRD.MN.016 | HDPE return-water / tailings pipeline (butt-fusion) install | m/day (crew) | 150 | 300 | 600 | S-065 |
| PRD.MN.017 | Geomembrane (LLDPE/HDPE) deployment & welding — leach pad (incl QA) | m²/day (crew) | 2000 | 4000 | 6000 | S-065 |
| PRD.MN.018 | Compacted soil liner (CCL) placement to low permeability | m²/day (crew) | 500 | 1200 | 2500 | S-065 |
| PRD.MN.019 | Overliner drainage gravel placement (LGP dozer, liner protection) | m³/day (crew) | 300 | 700 | 1500 | S-065 |
| PRD.MN.022 | Raise-bore pilot + reaming advance | m/day | 3 | 8 | 20 | S-065 |
| PRD.MN.023 | Wet shotcrete (fibrecrete) application underground | m³/hr | 4 | 8 | 15 | S-065 |
| PRD.MN.024 | Heavy-haul track laying (ballast/sleeper/rail), spur / loop | track-m/day (crew) | 150 | 300 | 600 | S-065 |
| PRD.MN.025 | Structural-steel erection, TLO / stockyard / shiploader | t/day (crew) | 4 | 8 | 15 | S-065 |
| PRD.MN.026 | Yard / shiploader conveyor structure + belt install | m/day (crew) | 20 | 50 | 100 | S-065 |
| PRD.MN.027 | Reinforced-concrete TLO / receival foundations (in-situ) | m³/day (crew) | 15 | 30 | 60 | S-065 |