Gas pipelines and crossings

Pipeline Trenchless & Special Crossings

Tie entry and exit points and the verified bore trajectory to a common control network.

Horizontal Directional Drilling Rig
  1. Feed carriageTrack pilot, reaming and pullback as distinct operations.
  2. Drill rodsInclude rod changes and handling in the cycle.
  3. Anchor systemAllow for rig positioning and setup at the entry point.
Plant reference for Pipeline Trenchless & Special Crossings

Work scope and interfaces

Related work packages

Construction sequence

  1. Geotech & approvals (road/rail/waterway authority)
  2. Set up rig + launch/reception sites
  3. HDD: pilot bore (steered/tracked)
  4. Ream
  5. Fabricate & test the crossing string (welded+coated+weight-coated) on the layout area
  6. Pull-back through the bore; (bore/microtunnel: install casing/MTBM, insert carrier, grout annulus)
  7. Tie-in to the open-cut line each end
  8. As-bored survey + pressure test of the crossing
  9. Site reinstatement.

The make-or-break: ground investigation before committing (a refusal/obstruction mid-bore is the classic blow-out), frac-out control on river HDD (environmental), and buoyancy/weight-coating on wet crossings.

Plant, resources and measurement

L.CREW.PIPELINE.SPREAD + method rig (G.PLANT.HDD / G.PLANT.MTBM.OP / G.PLANT.PILERIG.BG28) + M.CASING.STEEL (bore) + weight-coat/grout. Measured per crossing (by method × DN × length) — each a discrete item with its own mob. Priced items: PL.05.010.01 (HDD), PL.05.020.01 (auger/pipe-jack bore), PL.05.030.01 (microtunnel), PL.05.040.01 (open-cut watercourse), PL.05.050.01 (road/rail encasement). Rig mob/demob per crossing is a major line.

Keep mainline spread metres, individual welds, crossings and test sections on separate bases.

View Gas pipelines and crossings productivity references

Package productivity

Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.

Component activityPublished basisLowTypicalHighLibrary source
HDD - short/urban crossing (<=150 m, <=DN300)PRD.OG.004crossing/day0.512S-065
HDD pilot bore - drillable groundPRD.OG.005m/day80200400S-065

Component duration

Survey conformance and lot release

Observe
Tie entry and exit points and the verified bore trajectory to a common control network.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Retain the tracking log, crossing clearances and installation acceptance evidence.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations

As-bored line/grade survey, crossing-string weld+coat+holiday before pull, pull-tension & bend-radius records, annulus grout (bore), pressure test of the crossing, frac-out/environmental monitoring, authority/approval compliance. Risks: latent ground (refusal/obstruction — price ground risk explicitly; route to the site conditions geotechnical review), frac-out into a waterway, buoyancy on wet crossings, road/rail/waterway approval lead time, rig availability & per-crossing mob. Each crossing is its own mini-project.

Evidence and related work

Internal record PL-TRENCHLESS-XING-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.