Discipline library

Gas pipelines and crossings

Release the corridor, resolve crossings, assemble and inspect pipe, record the as-laid string, then test and hand over each authorised section.

Gas pipelines and crossings
  1. SideboomPlan the lowering spread against available access and lifting points.
  2. Pipe stringTie welding and coating records to the installed section.
  3. Trench beddingInspect support and alignment before backfill conceals the pipe.
Illustrative workfront within Gas pipelines and crossings.
Open the Cross-country pipeline lowering and placement calculator

Construction and release sequence

  1. Release the corridor, crossings and pipe-string delivery sequence
  2. Excavate, weld, inspect and lower accepted strings
  3. Complete tie-ins, coating checks, backfill and reinstatement
  4. Reconcile test sections, cathodic protection and turnover records

Work packages and conformance checks

Production and measurement

Keep mainline spread metres, individual welds, crossings and test sections on separate bases.

View the discipline reference figureGas pipelines and crossings reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.OG.001Mainline lay (string->weld->lower->backfill), open terrain, DN300-600m/day3006001200S-065
PRD.OG.002Girth weld - mainline manual (per weld, DN300-600)weld/welder-day4812S-065
PRD.OG.003Trench excavation, common material, 1.5-2.0 m deepm/day200500900S-065
PRD.OG.004HDD - short/urban crossing (<=150 m, <=DN300)crossing/day0.512S-065
PRD.OG.005HDD pilot bore - drillable groundm/day80200400S-065
PRD.OG.006HDD large-diameter river crossing (DN600+, 600-1500 m)crossing/weeks248S-065
PRD.OG.007S-lay - single-joint welding, 12" line, idealkm/day235S-065
PRD.OG.008S-lay - joints welded (12 m joints)joints/day150300420S-065
PRD.OG.009J-lay - deepwater single-position weldingkm/day123.5S-065
PRD.OG.010Reel-lay - smaller-diameter, no offshore weldingkm/day4815S-065
PRD.OG.011Process piping erection & weld (field, CS, by inch-dia)inch-dia/welder-day202735S-065
PRD.OG.012Mechanical equipment setting & alignment (skid/package)package/crew-day0.30.71.5S-065
PRD.OG.013RC equipment foundation (form/reo/pour plinth)m3/crew-day4814S-065
PRD.OG.014Structural steel erection (process plant, field)man-hour/tonne152540S-065
PRD.OG.015Structural steel erection - outputt/crew-day41020S-065
PRD.OG.016Process piping - field weldinch-dia/welder-day202735S-065
PRD.OG.017Piping fabrication & install (overall)man-hour/inch-dia11.83.5S-065
PRD.OG.018Tank shell plate welding (vertical/horizontal seams, CS)man-hour/tonne4080140S-065
PRD.OG.019Tank erection - overall (small-mid API 650, by capacity)man-hour/tonne steel5090160S-065
PRD.OG.020Shell course erection (jack-up method)course/day0.512S-065
PRD.OG.021Subsea spool/jumper tie-in (per connection)connection/vessel-day0.512S-065
PRD.OG.022Umbilical/flowline laykm/day2510S-065
PRD.OG.023Rock-dump seabed stabilisationt/day2000600015000S-065
PRD.OG.024Hook-up spool tie-in (offshore HUC)tie-in/crew-day0.51.53S-065
PRD.OG.025Module integration (yard, per integrated module)module/weeks138S-065
PRD.OG.026Commissioning systems handoversystem/week2510S-065
PRD.OG.027Lease pad earthworks & surface (per pad)pad/crew-days1410S-065
PRD.OG.028Pad bulk earthworks (push/spread/compact)m3/day100030006000S-065
PRD.OG.029PE gathering flowline lay & fusem/day3007001200S-065
PRD.OG.030Cleaning/gauging pig runkm/day52050S-065
PRD.OG.031Hydrostatic test - fill/pressurise/hold/report (per section)section/days137S-065
PRD.OG.032Drying to dewpoint (nitrogen/air)km/day21030S-065

Construction references

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.