Gas pipelines and crossings
- SideboomPlan the lowering spread against available access and lifting points.
- Pipe stringTie welding and coating records to the installed section.
- Trench beddingInspect support and alignment before backfill conceals the pipe.
Construction and release sequence
- Release the corridor, crossings and pipe-string delivery sequence
- Excavate, weld, inspect and lower accepted strings
- Complete tie-ins, coating checks, backfill and reinstatement
- Reconcile test sections, cathodic protection and turnover records
Work packages and conformance checks
Pipeline Cathodic Protection & Pre-CommissioningSurvey test posts, isolation points and buried connections before cover.Open-Cut Pipeline SpreadSurvey pipe centreline, bend locations, crossings and cover before backfill.Pipeline Trenchless & Special CrossingsTie entry and exit points and the verified bore trajectory to a common control network.Flexible & Non-Steel Trunk Mains — PE, DICL, GRP & MSCLPick up joints, valves, bends and cover at crossings before trench closure.Pipeline Girth Welding, NDT & CoatingRecord joint chainage and orientation against the traceable pipe string.
Production and measurement
Keep mainline spread metres, individual welds, crossings and test sections on separate bases.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.OG.001 | Mainline lay (string->weld->lower->backfill), open terrain, DN300-600 | m/day | 300 | 600 | 1200 | S-065 |
| PRD.OG.002 | Girth weld - mainline manual (per weld, DN300-600) | weld/welder-day | 4 | 8 | 12 | S-065 |
| PRD.OG.003 | Trench excavation, common material, 1.5-2.0 m deep | m/day | 200 | 500 | 900 | S-065 |
| PRD.OG.004 | HDD - short/urban crossing (<=150 m, <=DN300) | crossing/day | 0.5 | 1 | 2 | S-065 |
| PRD.OG.005 | HDD pilot bore - drillable ground | m/day | 80 | 200 | 400 | S-065 |
| PRD.OG.006 | HDD large-diameter river crossing (DN600+, 600-1500 m) | crossing/weeks | 2 | 4 | 8 | S-065 |
| PRD.OG.007 | S-lay - single-joint welding, 12" line, ideal | km/day | 2 | 3 | 5 | S-065 |
| PRD.OG.008 | S-lay - joints welded (12 m joints) | joints/day | 150 | 300 | 420 | S-065 |
| PRD.OG.009 | J-lay - deepwater single-position welding | km/day | 1 | 2 | 3.5 | S-065 |
| PRD.OG.010 | Reel-lay - smaller-diameter, no offshore welding | km/day | 4 | 8 | 15 | S-065 |
| PRD.OG.011 | Process piping erection & weld (field, CS, by inch-dia) | inch-dia/welder-day | 20 | 27 | 35 | S-065 |
| PRD.OG.012 | Mechanical equipment setting & alignment (skid/package) | package/crew-day | 0.3 | 0.7 | 1.5 | S-065 |
| PRD.OG.013 | RC equipment foundation (form/reo/pour plinth) | m3/crew-day | 4 | 8 | 14 | S-065 |
| PRD.OG.014 | Structural steel erection (process plant, field) | man-hour/tonne | 15 | 25 | 40 | S-065 |
| PRD.OG.015 | Structural steel erection - output | t/crew-day | 4 | 10 | 20 | S-065 |
| PRD.OG.016 | Process piping - field weld | inch-dia/welder-day | 20 | 27 | 35 | S-065 |
| PRD.OG.017 | Piping fabrication & install (overall) | man-hour/inch-dia | 1 | 1.8 | 3.5 | S-065 |
| PRD.OG.018 | Tank shell plate welding (vertical/horizontal seams, CS) | man-hour/tonne | 40 | 80 | 140 | S-065 |
| PRD.OG.019 | Tank erection - overall (small-mid API 650, by capacity) | man-hour/tonne steel | 50 | 90 | 160 | S-065 |
| PRD.OG.020 | Shell course erection (jack-up method) | course/day | 0.5 | 1 | 2 | S-065 |
| PRD.OG.021 | Subsea spool/jumper tie-in (per connection) | connection/vessel-day | 0.5 | 1 | 2 | S-065 |
| PRD.OG.022 | Umbilical/flowline lay | km/day | 2 | 5 | 10 | S-065 |
| PRD.OG.023 | Rock-dump seabed stabilisation | t/day | 2000 | 6000 | 15000 | S-065 |
| PRD.OG.024 | Hook-up spool tie-in (offshore HUC) | tie-in/crew-day | 0.5 | 1.5 | 3 | S-065 |
| PRD.OG.025 | Module integration (yard, per integrated module) | module/weeks | 1 | 3 | 8 | S-065 |
| PRD.OG.026 | Commissioning systems handover | system/week | 2 | 5 | 10 | S-065 |
| PRD.OG.027 | Lease pad earthworks & surface (per pad) | pad/crew-days | 1 | 4 | 10 | S-065 |
| PRD.OG.028 | Pad bulk earthworks (push/spread/compact) | m3/day | 1000 | 3000 | 6000 | S-065 |
| PRD.OG.029 | PE gathering flowline lay & fuse | m/day | 300 | 700 | 1200 | S-065 |
| PRD.OG.030 | Cleaning/gauging pig run | km/day | 5 | 20 | 50 | S-065 |
| PRD.OG.031 | Hydrostatic test - fill/pressurise/hold/report (per section) | section/days | 1 | 3 | 7 | S-065 |
| PRD.OG.032 | Drying to dewpoint (nitrogen/air) | km/day | 2 | 10 | 30 | S-065 |
Construction references
- Cross-Country Pipeline Construction
- Facilities Stations Construction and Commissioning
- Special Crossings HDD Bore and Watercourse