Roads and pavements

Asphalt Surfacing

Observe finished levels and crossfall on the accepted pavement grid, including joints and tie-ins.

Roads and pavements
  1. Material transferContinuity of mix delivery determines how often the paver stops.
  2. ScreedMeasure paving width and thickness against the issued layer design.
  3. RollerThe compaction train must keep up with the paving front.
Construction context for Asphalt Surfacing

Work scope and interfaces

What it is & where used

Laid as a wearing course over a granular base (Unbound Granular Pavement) or over a sprayed prime/SAMI (Sprayed Bituminous Seal), and as structural intermediate/base layers. Used on roads, intersections, hardstands and airport flexible pavements (heavy-duty mixes — TMR MRTS31).

Related work packages

Construction sequence

  1. (Profile/mill existing — RD.05.030, sweep)
  2. Spray tack coat at design rate (RD.05.060)
  3. Deliver hot mix in insulated trucks
  4. Charge paver (± shuttle/MTV)
  5. Lay mat to thickness & width behind paver
  6. IMMEDIATELY roll in the temperature window: breakdown (steel-drum)
  7. Intermediate (PTR)
  8. Finish (steel-drum)
  9. Construct hot/saw-cut joints (longitudinal/transverse)
  10. Core/density-test the LOT
  11. (open to traffic on cool-down).

The make-or-break is the paver+roller train staying continuous in the mat-temperature window — a stop-start paver, a cold haul, or under-rolling a thin lift = density non-conformance and joint failure, no matter the $/t.

Plant, resources and measurement

L.CREW.ASPHALT + G.PLANT.PAVER.STD (lay) + G.PLANT.PROFILER (mill) + G.PLANT.ROLLER.SMOOTH (breakdown/ finish) + G.PLANT.ROLLER.PTR (intermediate) + G.PLANT.BROOM (sweep) + G.PLANT.SPRAYER (tack); materials M.ASPH.DGA / M.ASPH.SMA / M.ASPH.OGA / M.ASPH.AC + M.BIT.EMULSION (tack). Measured by tonne of mix laid (supply+lay+compact), with milling and tack by m². Priced items: RD.05.010 (DGA wearing, 40 mm), RD.05.020 (SMA wearing), RD.05.030 (mill & dispose, m²), RD.05.040 (AC intermediate/base), RD.05.050 (OGA wearing), RD.05.060 (tack coat, m²). Rate trap: a flat $/t hides the laydown collapse on thin lifts, hand-work around furniture, night works and long haul — convert t↔area via layer thickness × mix density (~2.4 t/m³). Density/core testing via TEST-INDEX-001 §A.

Use the road lot worksheet for route-dependent crew time, release waits and direct cost.

View Roads and pavements productivity references

Package productivity

Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.

Component activityPublished basisLowTypicalHighLibrary source
Asphalt AC10 wearing course - by thickness (m2)PRD.PV.013m2/hr (at 40 mm lift)3006001100S-061
Asphalt - supply + lay + compact (tonnage basis)PRD.PV.016t/hr (paver-and-crew limited; ≈ 350-650 t/day)406085S-061
Profiling / cold planing - shallow (<=50 mm)PRD.PV.018m2/hr (at <=50 mm depth)3007001300S-061

Component duration

Survey conformance and lot release

Observe
Observe finished levels and crossfall on the accepted pavement grid, including joints and tie-ins.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Pair the conformance surface with paving lots, delivery dockets and compaction results.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations

Lot acceptance on field density / air voids (cores, AS/NZS 2891, ≥ N per lot), mat & joint temperature log, layer thickness & level/ride, tack-coat application-rate check, and mix conformance (grading/binder content/voids, AS/NZS 2891). Risks: compaction outside the temperature window (low density → ravelling/ rutting), joint failure (cold/poorly-tacked longitudinal & transverse joints — the durability trap), haul distance & truck temperature loss, segregation, thin-lift cooling, hand-work productivity loss around furniture, night-works and traffic windows. Tightly sequenced over the granular base / prime below (Unbound Granular Pavement / Sprayed Bituminous Seal) and with the staging/methodology above (DISC-ROAD-METH-001).

Evidence and related work

Internal record RD-ASPHALT-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.