Roads and pavements

Choose the asphalt, sprayed seal, concrete or rehabilitation route. Drainage, kerb and formation can govern the release to surfacing.

Roads and pavements
  1. Material transferContinuity of mix delivery determines how often the paver stops.
  2. ScreedMeasure paving width and thickness against the issued layer design.
  3. RollerThe compaction train must keep up with the paving front.
Illustrative workfront within Roads and pavements.
Open the 28 road packages and lot programmeOpen the Continuous asphalt paving train calculator

Construction and release sequence

  1. Establish traffic staging, control and drainage access
  2. Release subgrade and pavement layers by chainage
  3. Place the specified seal, asphalt or concrete surface
  4. Survey levels and crossfall, close lot records and reopen

Work packages and conformance checks

Production and measurement

Use the road lot worksheet for route-dependent crew time, release waits and direct cost.

View the discipline reference figureRoads and pavements reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.PV.001Subgrade preparation & trim (top of formation)m2/hr200450800S-061
PRD.PV.002Capping / select-fill layer (supply + place + compact)m3/hr (placing crew)60110170S-061
PRD.PV.003Sub-base unbound granular Type 2.3 (supply + place + compact)m3/hr (placing crew)55100160S-061
PRD.PV.004Base unbound granular Type 2.1 / DGB20 (supply + place + compact)m3/hr (placing crew, tighter tolerance)4585140S-061
PRD.PV.005Unbound base/sub-base - per m2 basis (150 mm compacted lift)m2/hr (at 150 mm lift)3506501100S-061
PRD.PV.006In-situ stabilisation - lime (spread + mix + compact + cure)m2/day (≈ 250-600 m2/hr)200040007000S-061
PRD.PV.007In-situ stabilisation - cement (spread + mix + compact + cure)m2/day (≈ 250-550 m2/hr)200038006500S-061
PRD.PV.008In-situ stabilisation - foamed bitumen (FBS, recycler)m2/day (≈ 350-700 m2/hr)300050008500S-061
PRD.PV.009Prime coat (cutback / emulsion primer on unbound base)m2/day (≈ 1,000-3,000 m2/hr)80001500025000S-061
PRD.PV.010Primer seal (primer binder + cover aggregate, 1 coat)m2/day (≈ 800-2,500 m2/hr)60001200020000S-061
PRD.PV.011Sprayed seal - single/seal (14 mm, binder + cover aggregate)m2/day (≈ 600-1,900 m2/hr)4000800015000S-061
PRD.PV.012Sprayed seal - double/two-coat (14/7 mm)m2/day (≈ 450-1,400 m2/hr, two passes)3000600011000S-061
PRD.PV.013Asphalt AC10 wearing course - by thickness (m2)m2/hr (at 40 mm lift)3006001100S-061
PRD.PV.014Asphalt AC14 - by thickness (m2)m2/hr (at 50 mm lift)3006001100S-061
PRD.PV.015Asphalt AC20 base/intermediate course - by thickness (m2)m2/hr (at 60-70 mm lift)2805501000S-061
PRD.PV.016Asphalt - supply + lay + compact (tonnage basis)t/hr (paver-and-crew limited; ≈ 350-650 t/day)406085S-061
PRD.PV.017Heavy-duty asphalt (EME2 / high-modulus / SMA)t/hr (tighter temperature/compaction control)355575S-061
PRD.PV.018Profiling / cold planing - shallow (<=50 mm)m2/hr (at <=50 mm depth)3007001300S-061
PRD.PV.019Profiling / cold planing - deep / full-depth (>100 mm, multi-pass)m2/hr (multi-pass to full depth)150400800S-061
PRD.PV.020Pavement compaction / proof roll (acceptance)m2/hr150030005000S-061
PRD.PV.021Shoulder gravel (supply + place + trim + compact)m3/hr (placing crew)5095150S-061
PRD.RF.001W-beam guardrail install (drivable ground)m/day90150220S-061
PRD.RF.002W-beam guardrail install (rock / cored / bolted footings)m/day4080120S-061
PRD.RF.003Guardrail end terminal (crash-tested, MASH)per day1.535S-061
PRD.RF.004Wire-rope safety barrier (WRSB) installm/day150300450S-061
PRD.RF.005WRSB end anchor / tensioning assemblyper day0.51.53S-061
PRD.RF.006Concrete barrier - precast F-shape / single-slope (placed)m/day60120200S-061
PRD.RF.007Concrete barrier - cast-in-situ (slip-form / fixed-form)m/day (slip-form) / 20-50-90 m/day (fixed form)80200350S-061
PRD.RF.008Bollards (fixed / removable) installper day81625S-061
PRD.RF.009Guideposts / delineators installper day60120200S-061
PRD.RF.010Rural fencing - post-and-wire (4-6 line + barb)m/day150350600S-061
PRD.RF.011Chain-mesh / chain-link fencing (1.8-2.4 m)m/day60140250S-061
PRD.RF.012Security fencing (palisade / weldmesh, 2.1-3.0 m)m/day3090160S-061
PRD.RF.013Fauna / exclusion fencing (with floppy-top / apron)m/day80200350S-061
PRD.RF.014Gates (farm / pedestrian / vehicle access)per day1.548S-061
PRD.RF.015Regulatory / warning / guide sign on single post (<=2.2 m2)per day81830S-061
PRD.RF.017Large / multi-post guide sign (3-10 m2, 2-3 posts)per day0.524S-061
PRD.RF.018Overhead gantry / cantilever sign structure (install)per day (erect, ex foundation)0.20.51S-061
PRD.RF.019Variable message sign (VMS) install - fixedper day (mount + connect, ex foundation/comms)0.312S-061
PRD.RF.020Longitudinal line marking - waterborne paint (single pass)km/line-km per day81215S-061
PRD.RF.021Longitudinal line marking - thermoplastic (sprayed/extruded)km/day (machine) / much slower hand-applied2610S-061
PRD.RF.022Raised pavement markers (RRPMs) installper day150350600S-061
PRD.RF.023Audio-tactile line marking (ATLM / rumble edge/centre)km/day3812S-061
PRD.RF.024Pavement symbols / legends / arrows (applied)per day (paint) / 10-30-60 (thermo)205090S-061
PRD.RF.025Kerb adaptor / kerb-and-channel transition unit installper day3815S-061
PRD.RF.026Pre-mark / set-out + grind-off old lines (prep)km/day (set-out) / 0.5-2-4 km/day (grind removal)148S-061