Roads and pavements
- Material transferContinuity of mix delivery determines how often the paver stops.
- ScreedMeasure paving width and thickness against the issued layer design.
- RollerThe compaction train must keep up with the paving front.
Construction and release sequence
- Establish traffic staging, control and drainage access
- Release subgrade and pavement layers by chainage
- Place the specified seal, asphalt or concrete surface
- Survey levels and crossfall, close lot records and reopen
Work packages and conformance checks
Asphalt SurfacingObserve finished levels and crossfall on the accepted pavement grid, including joints and tie-ins.Kerb, Channel & FinishingCheck kerb face line, lip level, grade breaks and connections to pits.Unbound Granular PavementCompare the top and bottom surfaces of each lift using the same lot limits.Rigid (Concrete) PavementSet out slab edges, joints and dowels. Check the finished profile across panel boundaries.Sprayed Bituminous SealMap the spray-run polygon, feathered edges and uncovered islands by coat.Bound / Stabilised PavementStake treatment width and check measured treatment depth and finished levels by run.Subgrade & Formation PreparationMeasure formation levels and crossfall at the nominated sections after compaction.
Production and measurement
Use the road lot worksheet for route-dependent crew time, release waits and direct cost.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.PV.001 | Subgrade preparation & trim (top of formation) | m2/hr | 200 | 450 | 800 | S-061 |
| PRD.PV.002 | Capping / select-fill layer (supply + place + compact) | m3/hr (placing crew) | 60 | 110 | 170 | S-061 |
| PRD.PV.003 | Sub-base unbound granular Type 2.3 (supply + place + compact) | m3/hr (placing crew) | 55 | 100 | 160 | S-061 |
| PRD.PV.004 | Base unbound granular Type 2.1 / DGB20 (supply + place + compact) | m3/hr (placing crew, tighter tolerance) | 45 | 85 | 140 | S-061 |
| PRD.PV.005 | Unbound base/sub-base - per m2 basis (150 mm compacted lift) | m2/hr (at 150 mm lift) | 350 | 650 | 1100 | S-061 |
| PRD.PV.006 | In-situ stabilisation - lime (spread + mix + compact + cure) | m2/day (≈ 250-600 m2/hr) | 2000 | 4000 | 7000 | S-061 |
| PRD.PV.007 | In-situ stabilisation - cement (spread + mix + compact + cure) | m2/day (≈ 250-550 m2/hr) | 2000 | 3800 | 6500 | S-061 |
| PRD.PV.008 | In-situ stabilisation - foamed bitumen (FBS, recycler) | m2/day (≈ 350-700 m2/hr) | 3000 | 5000 | 8500 | S-061 |
| PRD.PV.009 | Prime coat (cutback / emulsion primer on unbound base) | m2/day (≈ 1,000-3,000 m2/hr) | 8000 | 15000 | 25000 | S-061 |
| PRD.PV.010 | Primer seal (primer binder + cover aggregate, 1 coat) | m2/day (≈ 800-2,500 m2/hr) | 6000 | 12000 | 20000 | S-061 |
| PRD.PV.011 | Sprayed seal - single/seal (14 mm, binder + cover aggregate) | m2/day (≈ 600-1,900 m2/hr) | 4000 | 8000 | 15000 | S-061 |
| PRD.PV.012 | Sprayed seal - double/two-coat (14/7 mm) | m2/day (≈ 450-1,400 m2/hr, two passes) | 3000 | 6000 | 11000 | S-061 |
| PRD.PV.013 | Asphalt AC10 wearing course - by thickness (m2) | m2/hr (at 40 mm lift) | 300 | 600 | 1100 | S-061 |
| PRD.PV.014 | Asphalt AC14 - by thickness (m2) | m2/hr (at 50 mm lift) | 300 | 600 | 1100 | S-061 |
| PRD.PV.015 | Asphalt AC20 base/intermediate course - by thickness (m2) | m2/hr (at 60-70 mm lift) | 280 | 550 | 1000 | S-061 |
| PRD.PV.016 | Asphalt - supply + lay + compact (tonnage basis) | t/hr (paver-and-crew limited; ≈ 350-650 t/day) | 40 | 60 | 85 | S-061 |
| PRD.PV.017 | Heavy-duty asphalt (EME2 / high-modulus / SMA) | t/hr (tighter temperature/compaction control) | 35 | 55 | 75 | S-061 |
| PRD.PV.018 | Profiling / cold planing - shallow (<=50 mm) | m2/hr (at <=50 mm depth) | 300 | 700 | 1300 | S-061 |
| PRD.PV.019 | Profiling / cold planing - deep / full-depth (>100 mm, multi-pass) | m2/hr (multi-pass to full depth) | 150 | 400 | 800 | S-061 |
| PRD.PV.020 | Pavement compaction / proof roll (acceptance) | m2/hr | 1500 | 3000 | 5000 | S-061 |
| PRD.PV.021 | Shoulder gravel (supply + place + trim + compact) | m3/hr (placing crew) | 50 | 95 | 150 | S-061 |
| PRD.RF.001 | W-beam guardrail install (drivable ground) | m/day | 90 | 150 | 220 | S-061 |
| PRD.RF.002 | W-beam guardrail install (rock / cored / bolted footings) | m/day | 40 | 80 | 120 | S-061 |
| PRD.RF.003 | Guardrail end terminal (crash-tested, MASH) | per day | 1.5 | 3 | 5 | S-061 |
| PRD.RF.004 | Wire-rope safety barrier (WRSB) install | m/day | 150 | 300 | 450 | S-061 |
| PRD.RF.005 | WRSB end anchor / tensioning assembly | per day | 0.5 | 1.5 | 3 | S-061 |
| PRD.RF.006 | Concrete barrier - precast F-shape / single-slope (placed) | m/day | 60 | 120 | 200 | S-061 |
| PRD.RF.007 | Concrete barrier - cast-in-situ (slip-form / fixed-form) | m/day (slip-form) / 20-50-90 m/day (fixed form) | 80 | 200 | 350 | S-061 |
| PRD.RF.008 | Bollards (fixed / removable) install | per day | 8 | 16 | 25 | S-061 |
| PRD.RF.009 | Guideposts / delineators install | per day | 60 | 120 | 200 | S-061 |
| PRD.RF.010 | Rural fencing - post-and-wire (4-6 line + barb) | m/day | 150 | 350 | 600 | S-061 |
| PRD.RF.011 | Chain-mesh / chain-link fencing (1.8-2.4 m) | m/day | 60 | 140 | 250 | S-061 |
| PRD.RF.012 | Security fencing (palisade / weldmesh, 2.1-3.0 m) | m/day | 30 | 90 | 160 | S-061 |
| PRD.RF.013 | Fauna / exclusion fencing (with floppy-top / apron) | m/day | 80 | 200 | 350 | S-061 |
| PRD.RF.014 | Gates (farm / pedestrian / vehicle access) | per day | 1.5 | 4 | 8 | S-061 |
| PRD.RF.015 | Regulatory / warning / guide sign on single post (<=2.2 m2) | per day | 8 | 18 | 30 | S-061 |
| PRD.RF.017 | Large / multi-post guide sign (3-10 m2, 2-3 posts) | per day | 0.5 | 2 | 4 | S-061 |
| PRD.RF.018 | Overhead gantry / cantilever sign structure (install) | per day (erect, ex foundation) | 0.2 | 0.5 | 1 | S-061 |
| PRD.RF.019 | Variable message sign (VMS) install - fixed | per day (mount + connect, ex foundation/comms) | 0.3 | 1 | 2 | S-061 |
| PRD.RF.020 | Longitudinal line marking - waterborne paint (single pass) | km/line-km per day | 8 | 12 | 15 | S-061 |
| PRD.RF.021 | Longitudinal line marking - thermoplastic (sprayed/extruded) | km/day (machine) / much slower hand-applied | 2 | 6 | 10 | S-061 |
| PRD.RF.022 | Raised pavement markers (RRPMs) install | per day | 150 | 350 | 600 | S-061 |
| PRD.RF.023 | Audio-tactile line marking (ATLM / rumble edge/centre) | km/day | 3 | 8 | 12 | S-061 |
| PRD.RF.024 | Pavement symbols / legends / arrows (applied) | per day (paint) / 10-30-60 (thermo) | 20 | 50 | 90 | S-061 |
| PRD.RF.025 | Kerb adaptor / kerb-and-channel transition unit install | per day | 3 | 8 | 15 | S-061 |
| PRD.RF.026 | Pre-mark / set-out + grind-off old lines (prep) | km/day (set-out) / 0.5-2-4 km/day (grind removal) | 1 | 4 | 8 | S-061 |
Construction references
- Asphalt Surfacing
- Granular and Insitu Stabilised Pavement
- Rigid Concrete Pavement Construction