Utility-scale solar

Mounting System — piling, racking & trackers

Check pile centre, head elevation, plumb and tracker axis alignment by row and pile ID.

Utility-scale solar
  1. Pile driverTravel and alignment between posts affect output per shift.
  2. Tracker postsSurvey the installed row and record departures against the design.
  3. ModulesProtect installation access and track the accepted array area.
Construction context for Mounting System — piling, racking & trackers

Work scope and interfaces

What it is & where used

Every PV array sits on a mounting system. Driven steel posts are the default across the field; ground-screws or pre-drilled/rock-socket piles appear in pockets where the ground dictates. Fixed-tilt racking is the baseline; single-axis trackers are an extra-over chosen for yield uplift (at the cost of motors + maintenance).

Related work packages

Construction sequence

  1. Geotech + pile-test program (SF.02.030 → sets embedment/section, ground engineering)
  2. Row set-out & survey
  3. Drive steel piles to design/refusal (pre-drill / rock-socket where refusal; ground-screw where pull-out fails)
  4. Survey-check pile tops (line, level, plumb, reveal)
  5. Assemble racking / torque-tube structure to piles (fixed-tilt)
  6. Install tracker motors, drive line, bearings & controllers (single-axis, extra over)
  7. Ready for module install (PV Modules & DC Array — module install, DC string cabling & combiners). Repeated rig-by-rig, block-by-block across the field.

The make-or-break: the pile is a geotechnical bet — SF.02.030 sets the design, and ground worse than predicted (rock refusal → pre-drill; low pull-out in soft/sandy ground → longer piles or ground-screws) wrecks the cost/programme; productivity is piles/day × rigs across 100s of ha (weather, access, set-out & supply chain govern, not single-pile time).

Plant, resources and measurement

L.CREW.PILING (driving rig crew) + L.CREW.SF.INSTALL (racking/tracker assembly) + L.STAFF.ENGINEER (geotech/set-out oversight); plant G.PLANT.PILEDRIVER.SOLAR (the production driving rig) + G.PLANT.EXC.20T (pre-drill/handling/access); materials M.PILE.STEEL.SOLAR (steel posts), M.RACK.SOLAR (torque tube/purlins), M.TRACKER.SOLAR (motors/drive-line/controllers). Measured per pile (No.) and per row / per MW / per kWp for racking & trackers. Priced items: SF.03.010.01 (driven steel pile — supply & drive, the dominant repeated foundation), SF.03.020.01 (ground-screw/screw pile alternative), SF.03.030.01 (pre-drill / rock socket — extra over on refusal), SF.03.040.01 (racking/torque-tube — supply & assemble, fixed-tilt), SF.03.050.01 (single-axis tracker — extra over fixed-tilt); the geotech that sets the design is SF.02.030 (test-pile program). Rate trap: a flat per-pile rate that assumes the predicted ground — ignoring pre-drill %, refusal/longer-pile risk, ground-screw substitution and piles/day × rig count — under- prices the single biggest, most variable line on the job. Tracker extra-over adds motors + lifetime maintenance.

Use accepted piles, rows, modules and tested strings as distinct progress quantities.

View Utility-scale solar productivity references

Package productivity

Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.

Component activityPublished basisLowTypicalHighLibrary source
Driven steel pile — drive & set (the dominant volume rate, per rig)PRD.SF.001no/rig-day120250450S-303
Ground-screw pile — install (alternative mounting, per rig)PRD.SF.002no/rig-day80180350S-303
Racking / torque-tube — assemble onto piles (per table/row)PRD.SF.004tables/crew-day3612S-303

Component duration

Survey conformance and lot release

Observe
Check pile centre, head elevation, plumb and tracker axis alignment by row and pile ID.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Link pile trial results, refusal treatment, rack inspection and released tracker geometry.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations

Test-pile / load-test program acceptance (AS 2159 — pull-out, lateral, embedment), driving records & refusal logs, pile-top survey (line, level, plumb, reveal), galvanising/coating integrity, torque-to-spec on racking bolts, tracker drive/controller commissioning. Risks: ground worse than the test piles predicted (rock refusal → pre-drill cost/programme; low pull-out in soft/sandy ground → longer piles or ground-screw substitution) — the #1 cost risk; wind-uplift (AS/NZS 1170.2) under-design → pile pull-out failure; productivity shortfall (piles/day × rigs missing target on weather/access/set-out/supply); set-out tolerance feeding into the modules; tracker motor/controller availability & lifetime maintenance. Pairs with the geotech that designs the pile (ground engineering, SF.02.030) and carries the modules it founds (PV Modules & DC Array).

Evidence and related work

Internal record SF-PILING-RACKING-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.