Utility-scale solar
- Pile driverTravel and alignment between posts affect output per shift.
- Tracker postsSurvey the installed row and record departures against the design.
- ModulesProtect installation access and track the accepted array area.
Construction and release sequence
- Release trial piles, row set-out and material distribution
- Drive posts, survey tracker interfaces and assemble racking
- Mount modules, connect strings and install inverter and MV equipment
- Reconcile string tests, equipment records and grid handover
Work packages and conformance checks
Grid Connection, SCADA & CommissioningSurvey collector routes, joint bays, switchgear interfaces and metering asset locations.Inverters & MV Reticulation — DC-to-AC conversion, step-up & MV collectionSurvey skid pads, cable entries, earthing connections and equipment clearances.PV Modules & DC Array — module install, DC string cabling & combinersCheck module row alignment, string locations and installed clearances against the block layout.Mounting System — piling, racking & trackersCheck pile centre, head elevation, plumb and tracker axis alignment by row and pile ID.
Production and measurement
Use accepted piles, rows, modules and tested strings as distinct progress quantities.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.SF.001 | Driven steel pile — drive & set (the dominant volume rate, per rig) | no/rig-day | 120 | 250 | 450 | S-303 |
| PRD.SF.002 | Ground-screw pile — install (alternative mounting, per rig) | no/rig-day | 80 | 180 | 350 | S-303 |
| PRD.SF.003 | Pre-drill / rock-socket at refusal — extra-over (per rig) | no/rig-day | 20 | 50 | 100 | S-303 |
| PRD.SF.004 | Racking / torque-tube — assemble onto piles (per table/row) | tables/crew-day | 3 | 6 | 12 | S-303 |
| PRD.SF.005 | Single-axis tracker — motor/drive/controller fit & align | trackers/crew-day | 2 | 5 | 10 | S-303 |
| PRD.SF.006 | PV module — mount & clamp (the volume / logistics game) | no/crew-day | 150 | 350 | 600 | S-303 |
| PRD.SF.007 | DC string cabling / harness — lay & terminate | m/crew-day | 800 | 1500 | 3000 | S-303 |
| PRD.SF.008 | Combiner / recombiner box — install & terminate | no/crew-day | 4 | 8 | 16 | S-303 |
| PRD.SF.009 | String inverter — set & terminate | no/crew-day | 4 | 8 | 16 | S-303 |
| PRD.SF.010 | Central inverter / inverter-transformer skid — set & terminate | no/crew-day | 0.5 | 1 | 2 | S-303 |
| PRD.SF.011 | MV step-up transformer — set & terminate | no/crew-day | 0.5 | 1 | 2 | S-303 |
| PRD.SF.012 | MV collection cabling on tray / in trench — supply & lay | m/day per crew | 150 | 300 | 600 | S-303 |
| PRD.SF.013 | DC/AC verification (IEC 62446) + PR acceptance test (IEC 61724) | MWac/crew-week | 5 | 15 | 40 | S-303 |
| PRD.SF.014 | Grid-compliance / GPS hold-point campaign (R1/R2/full-output) + energisation/registration | weeks/campaign | 4 | 12 | 30 | S-303/215 |
Construction references
- Utility Scale Solar PV Construction