Discipline library

Utility-scale solar

Release trial piles and rows, survey tracker alignment, install modules and DC strings, then hand over inverter blocks and the collector connection.

Utility-scale solar
  1. Pile driverTravel and alignment between posts affect output per shift.
  2. Tracker postsSurvey the installed row and record departures against the design.
  3. ModulesProtect installation access and track the accepted array area.
Illustrative workfront within Utility-scale solar.
Open the Tracker foundation pile installation calculator

Construction and release sequence

  1. Release trial piles, row set-out and material distribution
  2. Drive posts, survey tracker interfaces and assemble racking
  3. Mount modules, connect strings and install inverter and MV equipment
  4. Reconcile string tests, equipment records and grid handover

Work packages and conformance checks

Production and measurement

Use accepted piles, rows, modules and tested strings as distinct progress quantities.

View the discipline reference figureUtility-scale solar reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.SF.001Driven steel pile — drive & set (the dominant volume rate, per rig)no/rig-day120250450S-303
PRD.SF.002Ground-screw pile — install (alternative mounting, per rig)no/rig-day80180350S-303
PRD.SF.003Pre-drill / rock-socket at refusal — extra-over (per rig)no/rig-day2050100S-303
PRD.SF.004Racking / torque-tube — assemble onto piles (per table/row)tables/crew-day3612S-303
PRD.SF.005Single-axis tracker — motor/drive/controller fit & aligntrackers/crew-day2510S-303
PRD.SF.006PV module — mount & clamp (the volume / logistics game)no/crew-day150350600S-303
PRD.SF.007DC string cabling / harness — lay & terminatem/crew-day80015003000S-303
PRD.SF.008Combiner / recombiner box — install & terminateno/crew-day4816S-303
PRD.SF.009String inverter — set & terminateno/crew-day4816S-303
PRD.SF.010Central inverter / inverter-transformer skid — set & terminateno/crew-day0.512S-303
PRD.SF.011MV step-up transformer — set & terminateno/crew-day0.512S-303
PRD.SF.012MV collection cabling on tray / in trench — supply & laym/day per crew150300600S-303
PRD.SF.013DC/AC verification (IEC 62446) + PR acceptance test (IEC 61724)MWac/crew-week51540S-303
PRD.SF.014Grid-compliance / GPS hold-point campaign (R1/R2/full-output) + energisation/registrationweeks/campaign41230S-303/215

Construction references