Substations

Substation Primary Plant

Check plinth centres, rails, bolt groups, bay spacing and equipment interfaces before set.

Substations
  1. Modular transporterAllow for the transfer route, setup and final positioning.
  2. TransformerMaintain the equipment identity through delivery and placement.
  3. PlinthConfirm the surveyed set-down position and civil release.
Construction context for Substation Primary Plant

Work scope and interfaces

Related work packages

Construction sequence

  1. (Civil + earthing + structures first — SS-EARTHING-001 + DISC-SUBSTN-METH-001)
  2. Receive & heavy-haul transformer to plinth (jack-and-pack)
  3. Assemble (radiators/bushings/conservator)
  4. Vacuum oil-fill & oil-processing
  5. Erect CBs/disconnectors/CTs/VTs/surge-arresters on structures per bay
  6. Install busbars (rigid tube / strung) + droppers & connections
  7. Primary-plant pre-commissioning checks
  8. (secondary tie-in: SS-SECONDARY-001)
  9. Staged energisation.

The make-or-break: the transformer (heavy haul, jack-and-pack, vacuum oil-fill & processing — long, weather- sensitive) and long-lead procurement (transformer/GIS order dates gate the whole job).

Plant, resources and measurement

L.CREW.HVELEC + heavy crane (G.PLANT.CRN.AT220 / G.PLANT.CRN.CRAWL300); plant M.PLANT.TRANSFORMER (by MVA), M.CB.HV/M.DISC.HV/M.ESW.HV/CT/VT/SA (by kV), M.BUSBAR.TUBE.AL/strung, M.REACTOR.SHUNT/M.CAPBANK, M.GIS.BAY. Measured: transformer no by MVA (supply + set/assemble/oil-fill split), switchgear no by kV per bay, busbar m, GIS per bay. Priced items: SS.04.* (transformers), SS.05.* (switchgear), SS.06.* (busbars/reactive). Transformer/GIS/reactor are documented big-tickets ([validate.CODE_CEIL]).

Track transformer moves, bay items, cable terminations and testing windows independently.

View Substations productivity references

Package productivity

Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.

Component activityPublished basisLowTypicalHighLibrary source
Heavy-haul, offload & set transformer onto plinth (whole operation)PRD.SS.015days/transformer2510S-065
Set & assemble HV circuit breaker (per pole/unit, crane + HV crew)PRD.SS.017days/CB12.55S-065
Erect complete AIS bay as a set (per-bay benchmark, banded by kV)PRD.SS.019days/bay82040S-065

Component duration

Survey conformance and lot release

Observe
Check plinth centres, rails, bolt groups, bay spacing and equipment interfaces before set.
Compare
Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
Verify and hand over
Reconcile signed setting surveys with supplier installation checks and bay release.
Resolve exceptions
Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations

Transformer FAT + site tests (ratio, winding resistance, vector group, tan-δ/SFRA, DGA/oil AS 1767), CB timing/contact-resistance/SF₆ density, disconnector interlocks, CT/VT ratio/polarity/knee-point, busbar contact resistance, insulation coordination. Risks: long-lead plant, heavy-haul access & lift, oil-processing weather window, SF₆ handling, free-issue boundary disputes, brownfield/live-yard staging (SS.10). Ties to secondary (Substation Secondary Systems) at the protection/control interface and to earthing (Substation Earthing Grid & Lightning Protection).

Evidence and related work

Internal record SS-PRIMARY-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.

The software behind Vaultix

Measure it in Spark. Price it in Trinity.

Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.