Substations
- Modular transporterAllow for the transfer route, setup and final positioning.
- TransformerMaintain the equipment identity through delivery and placement.
- PlinthConfirm the surveyed set-down position and civil release.
Construction and release sequence
- Release civil platforms, earthing grid and plinths
- Set and align primary equipment within each bay
- Install secondary wiring, controls and test interfaces
- Close bay test packs and obtain the designated energisation release
Work packages and conformance checks
Substation Earthing Grid & Lightning ProtectionSurvey buried grid conductors, bonds and test locations before backfill.Substation Primary PlantCheck plinth centres, rails, bolt groups, bay spacing and equipment interfaces before set.Substation Secondary SystemsRecord cabinet, panel and route locations with the correct equipment and drawing identifiers.
Production and measurement
Track transformer moves, bay items, cable terminations and testing windows independently.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.SS.001 | Bulk cut-to-fill, place & compact selected fill (30 t excavator + roller crew, free-digging) | m3/day | 400 | 800 | 1500 | S-065 |
| PRD.SS.002 | Trim & compact subgrade/capping to AS 3798 (grader + roller) | m2/day | 1500 | 3000 | 5000 | S-065 |
| PRD.SS.003 | Place crushed-rock yard surfacing blinding (loader + grader + roller) | m2/day | 600 | 1200 | 2000 | S-065 |
| PRD.SS.004 | Excavate, lay & backfill buried Cu grid conductor (trencher + earthing crew, soil) | m/day | 150 | 300 | 500 | S-065 |
| PRD.SS.005 | Exothermic (cadweld) connections | no/day per crew | 20 | 35 | 60 | S-065 |
| PRD.SS.006 | Drive & connect earth electrode/rod | no/day | 8 | 15 | 25 | S-065 |
| PRD.SS.007 | Equipment / structure earth bond with riser & lug | no/day | 15 | 30 | 50 | S-065 |
| PRD.SS.008 | Equipment footing / pedestal (exc, reo, form, pour ~1-4 m3 each) | no/day per crew | 1 | 3 | 6 | S-065 |
| PRD.SS.009 | Reinforced concrete placement (plinth/slab, pump-placed) | m3/day | 20 | 50 | 100 | S-065 |
| PRD.SS.010 | Reinforcement fix & fit (steelfixer crew) | t/day per crew | 1 | 2 | 3.5 | S-065 |
| PRD.SS.011 | Cable trench / trough construction (excavate, precast set, backfill) | m/day | 20 | 40 | 80 | S-065 |
| PRD.SS.012 | Erect galvanised structural steel / stands / gantries (crane + rigging crew) | t/day | 3 | 8 | 15 | S-065 |
| PRD.SS.013 | Set & grout equipment support stand on footing | no/day | 4 | 8 | 14 | S-065 |
| PRD.SS.014 | Erect overhead gantry / line-take-off structure (set) | no/day | 0.5 | 1 | 2 | S-065 |
| PRD.SS.015 | Heavy-haul, offload & set transformer onto plinth (whole operation) | days/transformer | 2 | 5 | 10 | S-065 |
| PRD.SS.016 | Assemble accessories, vacuum-process & oil-fill | days/transformer | 5 | 10 | 20 | S-065 |
| PRD.SS.017 | Set & assemble HV circuit breaker (per pole/unit, crane + HV crew) | days/CB | 1 | 2.5 | 5 | S-065 |
| PRD.SS.018 | Set & connect disconnector / CT / VT / SA (per element) | no/day per crew | 1 | 3 | 6 | S-065 |
| PRD.SS.019 | Erect complete AIS bay as a set (per-bay benchmark, banded by kV) | days/bay | 8 | 20 | 40 | S-065 |
| PRD.SS.020 | Install rigid Al tube busbar (cut, fit, support, fittings) | m/day per crew | 15 | 30 | 60 | S-065 |
| PRD.SS.021 | Install & tension strung busbar / droppers | m/day per crew | 30 | 60 | 120 | S-065 |
| PRD.SS.022 | HV connection / dropper / bimetallic clamp set | no/day per crew | 6 | 12 | 24 | S-065 |
| PRD.SS.023 | HV cable sealing end / termination (per end, by kV) | no/day per jointer | 0.5 | 1 | 2 | S-065 |
| PRD.SS.024 | Stand, fix & wire protection/control cubicle (per panel) | days/panel | 1 | 2 | 4 | S-065 |
| PRD.SS.025 | Install & configure SCADA RTU / station automation | days/station | 3 | 8 | 20 | S-065 |
| PRD.SS.026 | Install DC system (battery bank + chargers + DCDB) | days/system | 2 | 5 | 10 | S-065 |
| PRD.SS.027 | Pull control / multicore secondary cable (in trough/conduit) | m/day per crew | 200 | 500 | 1000 | S-065 |
| PRD.SS.028 | Terminate control cable (per multicore termination) | no/day per crew | 4 | 10 | 20 | S-065 |
| PRD.SS.029 | Install cable ladder / tray / containment | m/day per crew | 30 | 60 | 120 | S-065 |
| PRD.SS.030 | Place & fit out modular control building | days/building | 3 | 8 | 20 | S-065 |
| PRD.SS.031 | Building services fit-out (HVAC, lighting, small power) | days/building | 5 | 12 | 25 | S-065 |
| PRD.SS.032 | Pre-commissioning install checks per bay (IR, Ductor, SF6, torque) | days/bay | 1 | 2 | 4 | S-065 |
| PRD.SS.033 | Secondary + primary injection & scheme proving per bay | days/bay | 3 | 8 | 15 | S-065 |
| PRD.SS.034 | End-to-end teleprotection test (per circuit, with remote end) | days/circuit | 1 | 3 | 6 | S-065 |
| PRD.SS.035 | Live-yard productivity de-rate vs greenfield (apply to install work-types) | factor | 0.4 | 0.65 | 0.85 | S-065 |
| PRD.SS.036 | Outage planning / permit-to-work per access window | days/outage | 1 | 3 | 7 | S-065 |
Construction references
- Substation Civil Plant Installation
- Secondary Systems and Commissioning
- GIS Gas Insulated Switchgear Substation