Substations

Release the yard and plinths, survey buried earth grid before cover, set primary plant and complete secondary systems. Hand over by bay and test boundary.

Substations
  1. Modular transporterAllow for the transfer route, setup and final positioning.
  2. TransformerMaintain the equipment identity through delivery and placement.
  3. PlinthConfirm the surveyed set-down position and civil release.
Illustrative workfront within Substations.
Open the Transformer transfer and set on plinth calculator

Construction and release sequence

  1. Release civil platforms, earthing grid and plinths
  2. Set and align primary equipment within each bay
  3. Install secondary wiring, controls and test interfaces
  4. Close bay test packs and obtain the designated energisation release

Work packages and conformance checks

Production and measurement

Track transformer moves, bay items, cable terminations and testing windows independently.

View the discipline reference figureSubstations reference production bands from the Vaultix source register

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.

ReferenceActivitySource unitLowTypicalHighSource key
PRD.SS.001Bulk cut-to-fill, place & compact selected fill (30 t excavator + roller crew, free-digging)m3/day4008001500S-065
PRD.SS.002Trim & compact subgrade/capping to AS 3798 (grader + roller)m2/day150030005000S-065
PRD.SS.003Place crushed-rock yard surfacing blinding (loader + grader + roller)m2/day60012002000S-065
PRD.SS.004Excavate, lay & backfill buried Cu grid conductor (trencher + earthing crew, soil)m/day150300500S-065
PRD.SS.005Exothermic (cadweld) connectionsno/day per crew203560S-065
PRD.SS.006Drive & connect earth electrode/rodno/day81525S-065
PRD.SS.007Equipment / structure earth bond with riser & lugno/day153050S-065
PRD.SS.008Equipment footing / pedestal (exc, reo, form, pour ~1-4 m3 each)no/day per crew136S-065
PRD.SS.009Reinforced concrete placement (plinth/slab, pump-placed)m3/day2050100S-065
PRD.SS.010Reinforcement fix & fit (steelfixer crew)t/day per crew123.5S-065
PRD.SS.011Cable trench / trough construction (excavate, precast set, backfill)m/day204080S-065
PRD.SS.012Erect galvanised structural steel / stands / gantries (crane + rigging crew)t/day3815S-065
PRD.SS.013Set & grout equipment support stand on footingno/day4814S-065
PRD.SS.014Erect overhead gantry / line-take-off structure (set)no/day0.512S-065
PRD.SS.015Heavy-haul, offload & set transformer onto plinth (whole operation)days/transformer2510S-065
PRD.SS.016Assemble accessories, vacuum-process & oil-filldays/transformer51020S-065
PRD.SS.017Set & assemble HV circuit breaker (per pole/unit, crane + HV crew)days/CB12.55S-065
PRD.SS.018Set & connect disconnector / CT / VT / SA (per element)no/day per crew136S-065
PRD.SS.019Erect complete AIS bay as a set (per-bay benchmark, banded by kV)days/bay82040S-065
PRD.SS.020Install rigid Al tube busbar (cut, fit, support, fittings)m/day per crew153060S-065
PRD.SS.021Install & tension strung busbar / droppersm/day per crew3060120S-065
PRD.SS.022HV connection / dropper / bimetallic clamp setno/day per crew61224S-065
PRD.SS.023HV cable sealing end / termination (per end, by kV)no/day per jointer0.512S-065
PRD.SS.024Stand, fix & wire protection/control cubicle (per panel)days/panel124S-065
PRD.SS.025Install & configure SCADA RTU / station automationdays/station3820S-065
PRD.SS.026Install DC system (battery bank + chargers + DCDB)days/system2510S-065
PRD.SS.027Pull control / multicore secondary cable (in trough/conduit)m/day per crew2005001000S-065
PRD.SS.028Terminate control cable (per multicore termination)no/day per crew41020S-065
PRD.SS.029Install cable ladder / tray / containmentm/day per crew3060120S-065
PRD.SS.030Place & fit out modular control buildingdays/building3820S-065
PRD.SS.031Building services fit-out (HVAC, lighting, small power)days/building51225S-065
PRD.SS.032Pre-commissioning install checks per bay (IR, Ductor, SF6, torque)days/bay124S-065
PRD.SS.033Secondary + primary injection & scheme proving per baydays/bay3815S-065
PRD.SS.034End-to-end teleprotection test (per circuit, with remote end)days/circuit136S-065
PRD.SS.035Live-yard productivity de-rate vs greenfield (apply to install work-types)factor0.40.650.85S-065
PRD.SS.036Outage planning / permit-to-work per access windowdays/outage137S-065