- CutterheadGround conditions and interventions affect the boring cycle.
- ShieldSeparate excavation time from stoppages and maintenance.
- Segment ringSurvey the ring and reconcile accepted advance.
Construction sequence
- Establish compounds
- Guide wall + embedded shaft wall (secant/diaphragm)
- Dewater & excavate in stages with propping
- Base slab + base seal
- Headworks, working platform, guide rails
- Thrust block / reaction frame
- Soft-eye breakout
- TBM assembly & launch
- (portal: bulk excavation → scale → soil-nail/dowel + mesh + shotcrete face)
Make-or-break: the shaft and its thrust block sit on the critical path of the whole drive — get the box watertight, in-tolerance and the reaction frame to full jacking capacity before launch, or the TBM start (and everything downstream) slips TBM & Mechanised Tunnel Excavation.
Plant, resources and measurement
• Crews/plant: L.CREW.GEOTECH (face/ground support), L.CREW.PILING (embedded-wall + base), L.CREW.SHOTCRETE; G.PLANT.PILERIG.BG28 (secant/diaphragm bores), G.PLANT.EXC.30T (shaft dig / portal bulk), G.PLANT.CRN.CRAWL300 (segment/cage/headworks lifts). Materials M.NAIL.SOIL, M.SHOT.WET, M.CONC.S40, M.REO.BAR.N.
• Priced items: TU.01.010 establishment & disestablishment (LS); TU.01.020.01 portal excavation & forming (m³); TU.01.020.02 portal stabilisation — nails/dowels, mesh & shotcrete (m²); TU.01.030.01 launch/reception shaft — secant/diaphragm or sheet-piled (m depth); TU.01.030.02 caisson/sunk shaft (m sink); TU.01.040 shaft headworks, platform, guide rails & TBM/MTBM thrust (no.).
• Measurement basis: shafts paid per metre of sunk/walled depth (TU.01.030.*); portal cut by in-situ m³, face support by treated m² (deemed to include nail/dowel, mesh and shotcrete); establishment and headworks/thrust as lump-sum / enumerated.
• Rate trap: shaft m-rate is not linear with depth — wall thickness, propping count, dewatering and base-seal complexity escalate with head and adjacent-structure sensitivity; pricing a deep shaft off a shallow m-rate (and omitting the thrust block / reaction frame design as a real item) understates the critical-path box.
Split drive advance, ring or support time, shaft logistics, interventions and fit-out by reach.
View Tunnels and underground works productivity referencesPackage productivity
Select a component that matches the method, spread and ground conditions. Programme the remaining activities and hold points separately.
Survey conformance and lot release
- Observe
- Transfer surface control into the shaft and independently close the level and alignment check.
- Compare
- Identify the lot and asset, issued drawing revision, coordinate and height datum, control mark and observation method. Compare design and as-built values on a common basis using the specified sampling rule, permissible deviation and measurement uncertainty.
- Verify and hand over
- Release launch or reception geometry with the control transfer and support inspection.
- Resolve exceptions
- Map the affected extent, retain the original observation and record the authorised disposition. Recheck corrected work against the same criterion and link the result to the original lot before release.
Inspection considerations
• Embedded-wall verticality, panel/pile continuity (secant overlap), toe embedment and base-slab seal verified before dewatering down.
• Wall deflection and adjacent-structure settlement monitored against trigger levels (owned with ground engineering); base-heave/piping FoS checked under design head.
• Portal face support is designed temporary works — nail/dowel pull-out tests, shotcrete thickness/early-strength and mesh cover confirmed; rock scaling before access.
• Thrust block / reaction frame proof-checked to full TBM/MTBM jacking force prior to launch; soft-eye breakout sequence agreed.
• Confined-space, fall and lifting controls for deep vertical work per WHS excavation & tunnels CoP; emergency egress from shaft maintained throughout the drive.
Evidence and related work
Internal record TUN-PORTAL-SHAFT-001 · review · 2026-06-21. Use the issued project acceptance documents for contractual limits, inspection frequency and release authority.