Tunnels and underground works
- CutterheadGround conditions and interventions affect the boring cycle.
- ShieldSeparate excavation time from stoppages and maintenance.
- Segment ringSurvey the ring and reconcile accepted advance.
Construction and release sequence
- Release portal, shafts, control and monitoring baseline
- Advance the selected excavation and support spread by reach
- Verify lining geometry and release services access
- Reconcile chainage, instrumentation and system records
Work packages and conformance checks
Compensation (TAM) GroutingLocate injection arrays and monitoring points in the same project reference frame.Cut-and-Cover & Underground Structures — retention, box & reinstatementSurvey excavation supports, slab levels, wall lines and the final clearance envelope.Mechanically excavated tunnel headingsCompare profiles of the mechanically excavated heading with the design envelope by chainage.Tunnel Fit-Out — roadway, walkway & mechanical/electrical (M&E) systemsScan installed brackets, walkways, ducts and equipment against the maintained clearance envelope.Forepoling, Spiling & Canopy TubesCheck canopy collar locations and record drilling direction against the approved support layout.Instrumentation, Monitoring, Testing & Commissioning — observational-method feedback, dilapidation & handoverEstablish monitoring baselines and reference checks outside the expected movement zone.Tunnel Establishment, Portals & Shafts — launch/reception compounds, portal stabilisation & launch shaftsTransfer surface control into the shaft and independently close the level and alignment check.Sprayed Concrete Lining (SCL / NATM)Compare excavation and lining scans on the same alignment and chainage slices.Segmental Tunnel LiningRecord ring centre, roll, steps and joint offsets against the alignment model.TBM & Mechanised Tunnel ExcavationCheck machine guidance against independent tunnel control and compare ring chainage with the design trajectory.
Production and measurement
Split drive advance, ring or support time, shaft logistics, interventions and fit-out by reach.
View the discipline reference figure

Vaultix planning references retain their original output units. Confirm operating hours, crew, ground or access conditions and scope before adopting a figure. Time per unit and output per shift require different calculations.
| Reference | Activity | Source unit | Low | Typical | High | Source key |
|---|---|---|---|---|---|---|
| PRD.TU.001 | EPB/slurry advance, urban soft ground, single shield | m/day | 8 | 12 | 18 | S-065 |
| PRD.TU.002 | Favourable homogeneous ground, optimised logistics | m/day | 18 | 28 | 40 | S-065 |
| PRD.TU.003 | Ring build (erect + bolt + gasket + grout) | min/ring | 25 | 40 | 70 | S-065 |
| PRD.TU.004 | Hard-rock TBM advance, good competent rock | m/day | 15 | 25 | 40 | S-065 |
| PRD.TU.005 | Advance in poor/faulted rock (heavy support) | m/day | 2 | 6 | 12 | S-065 |
| PRD.TU.006 | Disc-cutter consumption | cutters/m | 0.05 | 0.15 | 0.4 | S-065 |
| PRD.TU.008 | Diaphragm-wall panel excavation (grab/hydromill) | m2/day | 30 | 60 | 120 | S-065 |
| PRD.TU.009 | Secant pile install (CFA/cased) | no/day | 4 | 8 | 14 | S-065 |
| PRD.TU.010 | Shaft excavation muck-out (soft ground, crane+grab) | m/day depth | 0.5 | 1.5 | 3 | S-065 |
| PRD.TU.011 | Ring erection cycle (erect+bolt+gasket) | min/ring | 20 | 35 | 60 | S-065 |
| PRD.TU.012 | Annulus grout volume | m3/ring | 0.5 | 1.2 | 3 | S-065 |
| PRD.TU.013 | Casting-yard segment production | rings/day | 4 | 8 | 14 | S-065 |
| PRD.TU.014 | SCL top-heading advance, fair rock, roadheader | m/day | 2 | 4 | 8 | S-065 |
| PRD.TU.015 | Wet-mix sprayed concrete application | m3/hr | 6 | 12 | 20 | S-065 |
| PRD.TU.016 | Sprayed-concrete rebound/overbreak allowance | % | 5 | 12 | 25 | S-065 |
| PRD.TU.017 | Rock-bolt installation | no/shift | 20 | 40 | 70 | S-065 |
| PRD.TU.018 | Ground-freeze formation (brine) | weeks/passage | 3 | 6 | 12 | S-065 |
| PRD.TU.019 | Cross-passage mining & support (SCL) | m/day | 0.5 | 1.5 | 3 | S-065 |
| PRD.TU.020 | Cross-passage complete (treat+break+mine+line) | weeks/passage | 6 | 12 | 24 | S-065 |
| PRD.TU.021 | Cut-and-cover box RC (place & finish) | m3/day | 20 | 50 | 100 | S-065 |
| PRD.TU.022 | Soldier-pile / contiguous wall install | m2/day | 25 | 50 | 90 | S-065 |
| PRD.TU.023 | Portal cutting bulk excavation | m3/day | 400 | 1000 | 2500 | S-065 |
| PRD.TU.024 | Pre-excavation grouting drill & inject | m/day drilled | 30 | 80 | 150 | S-065 |
| PRD.TU.025 | Grout take (permeation, granular ground) | L/m hole | 20 | 100 | 400 | S-065 |
| PRD.TU.026 | Forepole / canopy-tube installation | m/day | 40 | 90 | 160 | S-065 |
| PRD.TU.027 | Jet-grout column production | m/day | 30 | 70 | 130 | S-065 |
| PRD.TU.028 | Bulking factor (in-situ to loose spoil) | ratio | 1.2 | 1.4 | 1.8 | S-065 |
| PRD.TU.029 | Slurry separation-plant throughput | m3/hr | 200 | 600 | 1500 | S-065 |
| PRD.TU.030 | Continuous tunnel conveyor capacity | t/hr | 400 | 1000 | 2500 | S-065 |
| PRD.TU.031 | Sheet membrane installation (incl. fleece & fixing) | m2/day | 150 | 300 | 600 | S-065 |
| PRD.TU.032 | Secondary in-situ lining (travelling shutter pour) | m/day | 4 | 8 | 15 | S-065 |
| PRD.TU.033 | Spray-applied membrane | m2/day | 100 | 250 | 450 | S-065 |
| PRD.TU.034 | Construction vent duct extension (flexible) | m/day | 100 | 250 | 500 | S-065 |
| PRD.TU.035 | Minimum face air quantity (diesel dilution) | m3/s per kW diesel | 0.04 | 0.06 | 0.08 | S-065 |
| PRD.TU.036 | Permanent jet-fan install | no/day | 1 | 3 | 6 | S-065 |
| PRD.TU.037 | Cable installation (pull & terminate) | m/day per crew | 200 | 500 | 1000 | S-065 |
| PRD.TU.038 | Cable tray / walkway support install | m/day | 30 | 60 | 120 | S-065 |
| PRD.TU.039 | Integrated testing & commissioning duration | weeks/tunnel | 8 | 20 | 52 | S-065 |
| PRD.TU.040 | Surface settlement-array installation | points/day | 10 | 25 | 50 | S-065 |
| PRD.TU.041 | Inclinometer / extensometer install (drilled) | no/day | 1 | 3 | 6 | S-065 |
| PRD.TU.042 | Volume loss target (urban EPB) | % | 0.5 | 1 | 2 | S-065 |